Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹55.1 CrAdmitted-Finance | ₹55.1 Cr | L1 | Admitted-Finance |
| Sl No | Description | Qty | Unit | SARAN BUILDWELL PVT. LTD. L1 |
|---|---|---|---|---|
| 1.00 | Item: 6.26 Silt Clearance/ Removal of blown sand/ Berm Unloading undressed with combined lead upto 50 m. for lined canal section.
6.26.3 For FSD more than 2 m. | 6,059.19 | Cum | 11.5 ₹69,680.69 Lowest |
| 2.00 | Uprooting Juli Flora /sarkanda
Uprooting Juli Flora /sarkanda, pahari kikar or arrows upto 0.50m. depth below ground level. | 8,02,299 | Sqm | 0.75 ₹6,01,724.25 Lowest |
| 3.00 | Earth work excavation in ordinary soil for main canal and branches having discharge 10 cumecs and above;
6.2.2 Earthwork undressed with combined lead upto 50m. | 88,386.38 | Cum | 15 ₹13,25,795.7 Lowest |
| 4.00 | Earth work excavation in ordinary soil for main canal and branches having discharge 10 cumecs and above;
6.2.1 Kassi work undressed. | 1,60,745.56 | Cum | 15 ₹24,11,183.4 Lowest |
| 5.00 | Compaction of earthwork by mechanically operated Vibro-Compactor/ any other mechanical means to attain a density 95% of Maximum Dry Density. | 39,899.25 | Cum | 14 ₹5,58,589.5 Lowest |
| 6.00 | Dressing of earthwork. | 1,19,269.26 | Cum | 1.3 ₹1,55,050.04 Lowest |
| 7.00 | Add extra for earth taken from private land, land to be arranged by the contractor through private negotiations. Item applicable on certification by Ex. En. that no earth is available within canal boundary.
10.2.2 for uncommand area | 69,265.83 | Cum | 1 ₹69,265.83 Lowest |
| 8.00 | Rubbing and clearing the surface of existing brick/ tile lining to be used as subgrade both in bed and side slopes by means of wire brushes water/ air applied under pressure through nozzle to get rid of dirt, sand etc. deposited on it, complete in all respect, as per specifications and the instructions of the engineer incharge for preparation of surface. | 5,19,734 | Sqm | 1.8 ₹9,35,521.2 Lowest |
| 9.00 | Extra on earthwork for laying in 15 to 25 cms layers including Dressing and Watering as per specifications (Water to be made available by the department at one place of work site). | 39,899.25 | Cum | 1 ₹39,899.25 Lowest |
| 10.00 | Carriage of Bats Ballast, Kankar, Sand, Bajri, Stone, Grit, Murram, Soling Stones For Road, Water, Good Earth.
2 KM Katcha | 99,885.25 | Cum | 1 ₹99,885.25 Lowest |
Tender Value
₹57.0 Cr
EMD Value
₹1.1 Cr
Closing Date
17 Jul 2024, 6:00 pmClosed
Chief Engineer
Office of the Chief Engineer Water Resources(North) Hanumangarh
Rehabilitation of different reaches of various canals of Raslana Distributary 0 to km 40.480 sub-project, District Hanumangarh
2024_WRDAS_394001_2
CE_NIB_01_2024-25
Open Tender
Civil Works
Item Rate
1095 days
Bhadra
As per bid documents
3 documents required · 3 mandatory
₹20,000
Executive Engineer, Water Resources Division
₹1.1 Cr
Hanumangarh
17 Sept 2024
13 Jun 2024
18 Jul 2024
13 Jun 2024
17 Jul 2024
13 Jun 2024
24 Jun 2024
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Item: 6.26 Silt Clearance/ Removal of blown sand/ Berm Unloading undressed with combined lead upto 50 m. for lined canal section.
6.26.3 For FSD more than 2 m. | 6,059.19 | Cum | - | - |
| 2 | Uprooting Juli Flora /sarkanda
Uprooting Juli Flora /sarkanda, pahari kikar or arrows upto 0.50m. depth below ground level. | 8,02,299 | Sqm | - | - |
| 3 | Earth work excavation in ordinary soil for main canal and branches having discharge 10 cumecs and above;
6.2.2 Earthwork undressed with combined lead upto 50m. | 88,386.38 | Cum | - | - |
| 4 | Earth work excavation in ordinary soil for main canal and branches having discharge 10 cumecs and above;
6.2.1 Kassi work undressed. | 1,60,745.56 | Cum | - | - |
| 5 | Compaction of earthwork by mechanically operated Vibro-Compactor/ any other mechanical means to attain a density 95% of Maximum Dry Density. | 39,899.25 | Cum | - | - |
| 6 | Dressing of earthwork. | 1,19,269.26 | Cum | - | - |
| 7 | Add extra for earth taken from private land, land to be arranged by the contractor through private negotiations. Item applicable on certification by Ex. En. that no earth is available within canal boundary.
10.2.2 for uncommand area | 69,265.83 | Cum | - | - |
| 8 | Rubbing and clearing the surface of existing brick/ tile lining to be used as subgrade both in bed and side slopes by means of wire brushes water/ air applied under pressure through nozzle to get rid of dirt, sand etc. deposited on it, complete in all respect, as per specifications and the instructions of the engineer incharge for preparation of surface. | 5,19,734 | Sqm | - | - |
| 9 | Extra on earthwork for laying in 15 to 25 cms layers including Dressing and Watering as per specifications (Water to be made available by the department at one place of work site). | 39,899.25 | Cum | - | - |
| 10 | Carriage of Bats Ballast, Kankar, Sand, Bajri, Stone, Grit, Murram, Soling Stones For Road, Water, Good Earth.
2 KM Katcha | 99,885.25 | Cum | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.07 MB
BiD_DoC_B_SiD.pdf
Tender Documents • 3.85 MB
BOQ_706256.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .