| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.0 CrAccepted-AOC | ₹1.0 Cr | L1 | Accepted-AOC Lowest Amount Quoted BY KSM CONSTRUCTION PRIVATE LIMITED(10056590.29) accepted |
| 2 | L2₹1.1 Cr+₹7.5 L (7.49%)Rejected-Finance 50 36 KAVARAI STREET SAIDAPET CHENNAI 15 | 15 | ₹1.1 Cr+₹7.5 L (7.49%) | L2 | Rejected-Finance Above Estimate Rate |
Tender Value
₹1.0 Cr
EMD Value
₹1.0 L
Closing Date
5 May 2023, 3:00 pmClosed
COLLECTOR / CHAIRMAN
AC D DRDA TIRUVALLUR
1.Strengthening of BT road from G.N.T.ROAD TO METTUKUPPAM Km 0/0-1/0 2.Strengthening of BT road from RAJAPALAIYAM TOMANGAVARAM ROAD Km 0/0-0/9103.Strengthening of BT road from PERIAOBALAPURAM THASILDARMEDU TO JANAKIRAMAN CHETTY CHATRAM Km 0/0-0/64
2023_RDTN_305652_1
DIPR/2142/TENDER/2023
Open Tender
Civil Works
Item Rate
180 days
Gummidipoondi
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹1.0 L
Yes
AC D DRDA TIRUVALLUR
10 Jul 2023
24 Apr 2023
5 May 2023
24 Apr 2023
5 May 2023
24 Apr 2023
25 Apr 2023
Amount
Strengthening of BT road from G.N.T.ROAD TO METTUKUPPAM Km 0/0-1/0
Picking the Worn-out BT Surface including incidential charges and cleaning of all labour charges and machinery charges etc,..complet
Clearing the Scrub jungle removing from away site including incidential charges and all labour charges with burning and ashes including all labour charges etc,..complete.
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 150mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete
Applying PRIMECOAT over WBM/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying TACKCOAT over WBM/ WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and Plastic Waste Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for and compaction with power roller etc.complete, for Side berms etc,.complete,.
Provision for HM Stone Charges etc,..
Provision for KM Stone Charges etc,..
Provision for Name Board Charges with painting etc,..
Provision for Sign Board
Provision for White board line
Provision for Rumble stripes
Provision for Reflectors
Routine Maintenance after completion of work the road sufrace and shoulder to be maintained in proper condition to make them free from excessive edge drop offs, roughness, scouring and pot holes and cleaning of surface drain including culverts for frre flow of water. Relettering name boards and K.M & H.M stone and other maintenance operation required to keep the road traffic worthly at all the time for the maintenance period for the following years. As per General condition of contract para 32.2.2
For 1st Year
For 2nd Year
For 3rd Year
For 4th Year
For 5th Year
2. Strengthening of BT road from RAJAPALAIYAM TO MANGAVARAM ROAD Km 0/0-0/910
Picking the Worn-out BT Surface including incidential charges and cleaning of all labour charges and machinery charges etc,..complet
Clearing the Scrub jungle removing from away site including incidential charges and all labour charges with burning and ashes including all labour charges etc,..complete.
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 150mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete
Applying PRIMECOAT over WBM/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying TACKCOAT over WBM/ WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and Plastic Waste Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for and compaction with power roller etc.complete, for Side berms etc,.complete,.
Provision for HM Stone Charges etc,..
Provision for KM Stone Charges etc,..
Provision for Name Board Charges with painting etc,..
Provision for Sign Board
Provision for White board line
Provision for Rumble stripes
Provision for Reflectors
Routine Maintenance after completion of work the road sufrace and shoulder to be maintained in proper condition to make them free from excessive edge drop offs, roughness, scouring and pot holes and cleaning of surface drain including culverts for frre flow of water. Relettering name boards and K.M & H.M stone and other maintenance operation required to keep the road traffic worthly at all the time for the maintenance period for the following years. As per General condition of contract para 32.2.2
For 1st Year
For 2nd Year
For 3rd Year
For 4th Year
For 5th Year
3.Strengthening of BT road from PERIAOBALAPURAM THASILDARMEDU TO JANAKIRAMAN CHETTY CHATRAM Km 0/0-0/645
Picking the Worn-out BT Surface including incidential charges and cleaning of all labour charges and machinery charges etc,..complet
Clearing the Scrub jungle removing from away site including incidential charges and all labour charges with burning and ashes including all labour charges etc,..complete.
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 150mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete
Applying PRIMECOAT over WBM/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying TACKCOAT over WBM/ WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and Plastic Waste Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for and compaction with power roller etc.complete, for Side berms etc,.complete,.
Provision for HM Stone Charges etc,..
Provision for Name Board Charges with painting etc,..
Provision for Sign Board
Provision for White board line
Provision for Rumble stripes
Provision for Reflectors
Routine Maintenance after completion of work the road sufrace and shoulder to be maintained in proper condition to make them free from excessive edge drop offs, roughness, scouring and pot holes and cleaning of surface drain including culverts for frre flow of water. Relettering name boards and K.M & H.M stone and other maintenance operation required to keep the road traffic worthly at all the time for the maintenance period for the following years. As per General condition of contract para 32.2.2
For 1st Year
For 2nd Year
For 3rd Year
For 4th Year
For 5th Year
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Babuji Civil Construction
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.06 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .