| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 LAccepted-Finance | ₹2.4 L | L1 | Accepted-Finance ACCEPTED |
| 2 | L2₹2.4 L+₹5,658.08 (2.40%)Rejected-Finance | ₹2.4 L+₹5,658.08 (2.40%) | L2 | Rejected-Finance REJECTED |
| 3 | L3₹2.4 L+₹6,601.09 (2.80%)Rejected-Finance DATTWAD SHIRALA TALUKA | SANGLI | MAHARASHTRA | 415301 | ₹2.4 L+₹6,601.09 (2.80%) | L3 | Rejected-Finance REJECTED |
Tender Value
₹2.4 L
EMD Value
₹2,358
Closing Date
14 Jul 2026, 11:00 amClosed
SARPANCH AND GRAMVIKAS ADHIKARI AURWAD
SARPANCH AND GRAMVIKAS ADHIKARI AURWAD
PROVIDING DISTRIBUTION SYSTEM AT-AURWAD TAL-SHIROL DIST-KOLHAPUR
2026_KOLHA_1315211_1
04/2026-27
Open Tender
Civil Works - Water Works
Percentage
180 days
AP AURWAD TAL SHIROL DIST KOLHAPUR
PROVIDING DISTRIBUTION SYSTEM AT-AURWAD TAL-SHIROL DIST-KOLHAPUR
2 documents required · 2 mandatory
₹200
₹2,358
16 Jul 2026
7 Jul 2026
15 Jul 2026
7 Jul 2026
14 Jul 2026
7 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation for foundation / pipe trenches in earth, soils of all types, sand, gravel and soft murum, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. (Bd- A 1/259) Lift 0 to 1.5 M SSR MJP 23-24 ,P/l-37/1 Rs.165+5%=173.25 For 90 mm 4Kg/Sq.cm | 65.6 | Cubic Metre | 173.25 | ₹11,365.2 |
| 2 | Excavation for foundation / pipe trenches in hard murum including removing the excavated material upto a distance of 50 M and lifts as below, stacking and spreading as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. Complete. SSR MJP 23-24 ,P/l-37/2 Rs.187+5%= 196.35 For 90 mm 4Kg/Sq.cm | 45 | Cubic Metre | 196.35 | ₹8,835.75 |
| 3 | Excavation for foundation / pipe trenches in earth, soils of all types, sand, gravel and soft murum, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. (Bd- A 1/259) Lift 0 to 1.5 M SSR MJP 23-24 ,P/l-37/1 Rs.165+5%=173.25 For 75 mm 4Kg/Sq.cm | 68.9 | Cubic Metre | 173.25 | ₹11,936.93 |
| 4 | Excavation for foundation / pipe trenches in hard murum including removing the excavated material upto a distance of 50 M and lifts as below, stacking and spreading as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. SSR MJP 23-24 ,P/l-37/2 Rs.187+5%= 196.35 For 75 mm 4Kg/Sq.cm | 60.8 | Cubic Metre | 196.35 | ₹11,938.08 |
| 5 | Filling in plinth and floors murum bedding in trenches with approved murum from excavated materials from foundation in 15 cm to 20 cm layers including watering and compaction, etc. complete. (Bd-A-10/263) Rs.92+5%=96.6 | 18.9 | Cubic Metre | 96.6 | ₹1,825.74 |
| 6 | Filling in plinth and floors murum bedding in trenches with approved murum from excavated materials from foundation in 15 cm to 20 cm layers including watering and compaction, etc. complete. (Bd-A-10/263) Rs.92+5%=96.6 | 24.68 | Cubic Metre | 96.6 | ₹2,384.09 |
| 7 | Providing and supplying in standard lengths Isl made rigid unplasticised PVC pipes suitable for potable water with solvent cement joints including cost of couplers, as per IS specification no. 4985 / 1988 excluding GST levied by GOI and GOM in all respect, including transportation, freight charges, inspection charges, loading, unloading, conveyance to the departmental stores and stacking the same in closed shed duly protected from sun rays and rains including cost of jointing material i.e. solvent cement, etc. complete (selffit type to be jointed with cement solvent) For 90mm 4kg/Sq.cm pvc pipe | 165 | Rmt | 160 | ₹26,400 |
| 8 | Providing and supplying in standard lengths ISI mark rigid unplasticised PVC pipes suitable for potable water with solvent cement joints including cost of couplets, as per IS specification no. 4985 / 1988 excluding GST levied by GOI and GOM in all respect, including transportation, freight charges, inspection charges, loading, unloading, conveyance to the departmental stores and stacking the same in closed shed duly protected from sun rays and rains including cost of jointing material i.e. solvent cement, etc. complete (selffit type to be jointed with cement solvent) For 75mm 4kg/Sq.cm pvc pipe | 185 | Rmt | 115 | ₹21,275 |
| 9 | Lowering, laying and jointing with P.V.C. pipes and specials of following class and diameter including cost of conveyance from stores to site of works including cost of all labour, material, except cement solvent, rubber ring, as per IS code, elc. complete (with cement solvent joint / ring fit joint) For 90mm 4kg/Sq.cm pvc pipe | 145 | Rmt | 36.75 | ₹5,328.75 |
| 10 | Lowering, laying and jointing with P.V.C. pipes and specials of following class and diameter including cost of conveyance from stores to site of works including cost of all labour, material, except cement solvent, rubber ring, as per IS code, elc. complete (with cement solvent joint / ring fit joint) For75mm 4kg/Sq.cm pvc pipe | 220 | Rmt | 29.4 | ₹6,468 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.24 MB
BOQ_2255358.xls
BOQ • 0.34 MB
SBDMAIN.pdf
Tender Documents • 3.01 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .