| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹16.5 CrAccepted-AOC S 6 IIND FLOOR FRIENDS TRADE CENTRE NEHRU NAGAR AGRA | AGRA | UTTAR PRADESH | ₹16.5 Cr Quoted ₹23.9 Cr | L-1 | Accepted-AOC AOC |
| 2 | L-2₹24.2 CrRejected-Finance BIRPARA PO BIRPARA DIST JALPAIGURI W B PIN 735204 | ALIPURDUAR | WEST BENGAL | 735204 | ₹24.2 Cr | L-2 | Rejected-Finance Reject |
| 3 | L-3₹25.3 CrRejected-Finance MOHSINPUR MANSURPUR AKBARPUR AMBEDKAR NAGAR | ₹25.3 Cr | L-3 | Rejected-Finance Reject |
| 4 | L-4₹26.2 CrRejected-Finance | ₹26.2 Cr | L-4 | Rejected-Finance Reject |
| 5 | L-5₹26.7 CrRejected-Finance | ₹26.7 Cr | L-5 | Rejected-Finance Reject |
Tender Value
₹31 Cr
EMD Value
₹46.5 L
Closing Date
10 Aug 2023, 12:00 pmClosed
OFFICE OF THE SE BANDA CIRLCE PWD BANDA
OFFICE OF THE SE BANDA CIRLCE PWD BANDA
Widening and strengthening work (including 5-year maintenance work) in kilometer 1 to 16 (740) of Banda-Hamirpur road other district road in district Banda under NABARD funded RIDF-29 scheme
2023_CEJNS_822390_1
2811/35 C-BANDA-CIRCLE/2022-23 DATE-10-07-2023
Open Tender
Civil Works
365 days
Banda
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,260
₹46.5 L
OFFICE OF THE SE BANDA CIRLCE PWD BANDA
26 Oct 2023
20 Jul 2023
10 Aug 2023
20 Jul 2023
10 Aug 2023
20 Jul 2023
24 Jul 2023
Amount
Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m As Per Specification No.301(3.60)
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2. As Per Specification No. 305(3.16)
Compaction of embankment with approved materials deposited at site from road way cutting (Trench Cutting) and excavation from drain and foundation of other structure graded and compacted to meet requirement of table 300.2. As per MORTH No.-305.
Construction of embankment with approved materials obtained from borrow pits with all lifts and leads transpoting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2 (Lead 4 Km.)
Construction of granular sub-base by providing close Graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401 .
Providing laying, spreading and compacting graded stone aggregate to wet mix macadam specification inlcuding premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site laying in uniform layers with machanical paver in sub-base/base course on wall prepared surface and compacting with vibratory roller to achieve the desired density. As per MOR&TH specification No. 406
Providing laying, spreading and compacting graded stone aggregate (WMM) after mixing with water at OMC in mechanical mix plant carriage of mixe material by tipper to site, laying 1% OPC cement and 3.5% Emlusion in uniform single layer on sub base/subgrade and compacting with the road roller to acheive the desire density.
Providing and laying dense graded bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all respects.
Providing and applying tack coat with V.G. 10 grade bitumen using emlusion pressure dristributor @ 0.20 kg. per sqm. on the prepared bituminous surface cleaned with machenical broom. As per MORT&H on wmm steblization as perClause 503
Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder as per job mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects
Earth filling in patri in including rolling with road roller upto required M.D.D., dressing the surface to required level and slope & also including 1.50 m. lift and 30 m. lead, cost of labour, T&P and hire charges of machinery etc. complete work as per direction of Engineer-in-Charge.
Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical specifications
Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8 Km from the site of work & including watering, dressing etc. Rate to include cost of all materials, labour and tools & plants etc. required for proper completion of the work. (S.I.No. 255)
Cement concrete with 4cm (1/2'') gauge approved stone ballast, approved coarse sand. cement in the proportion 1:4:8 including supply of all materials,labour and tools and plants etc. required for proper completion of the work.
Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical specification
Random course Rubble massonary in 1:4 cement and fine sand mortar in foundation and plinth, including supply of all materials, labour & T&P etc. required for proper completion of the work.
Cement concrete with 2cm gauge approved stone ballast, approved coarse sand. cement in the proportion 1:2:4 including supply of all materials,labour and tools and plants etc. required for proper completion of the work.
RCC work with cement approved coarse sand and 2cm. (3/4'') gauge approved stone ballast in the proportion 1:2:4 in lintels of doors and windows, excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.I wire.and including necessary cantering and suttering etc and also including supply of all materials,labour and tools and plants etc. required for proper completion of the work. binding wire to be supplied by the contractor free of cost. As in Item (283)
Mild steel of iron in plain work such as reinforced concrete/ brick work (when not included in over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel, its wastage and hooks and authorised over lapping shall be measured.
CONSTRUCTION OF CULVERT. Excavation in foundation in B.C soil including lift up to 15 meter and lead upto 30 m (100 ft) and including filling, watering & ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30 M from the foundation trenches.(S.I.No. 251)
Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8 Km from the site of work & including watering, dressing etc. Rate to include cost of all materials, labour and tools & plants etc. required for proper completion of the work. (S.I.No. 255)
Cement concrete with 4cm (1/2'') gauge approved stone ballast, approved coarse sand. cement in the proportion 1:4:8 including supply of all materials,labour and tools and plants etc. required for proper completion of the work.
Class-150 brick work in 1:4 cement and fine sand of 1.25 fineness modulus mortar in foundation and plinth including supply of all materials, labour and tools and plants etc. Required for proper completion of the work.
Providing and laying reinforced concrete pipe NP3 in single row for culverts on 'Type A' (Concrete cradle) bedding with M 15 grade cement concrete including fixing coller with cement mortar 1:2 but excuding excavation protrction work, backfilling, concrete and masonary works in head walls and parapets clause 1106 as per Data Book item No. 9.3 (B) 1000 mm Dai Hume Pipe
Providing and laying reinforced concrete pipe NP3 in single row for culverts on 'Type A' (Concrete cradle) bedding with M 15 grade cement concrete including fixing coller with cement mortar 1:2 but excuding excavation protrction work, backfilling, concrete and masonary works in head walls and parapets clause 1106 as per Data Book item No. 9.3 (B) 600 mm Dai Hume Pipe
Providing and laying reinforced concrete pipe NP3 in single row for culverts on 'Type A' (Concrete cradle) bedding with M 15 grade cement concrete including fixing coller with cement mortar 1:2 but excuding excavation protrction work, backfilling, concrete and masonary works in head walls and parapets clause 1106 as per Data Book item No. 9.3 (B) 350 mm Dai Hume Pipe
12mm thick plaster on brick work minimum thickness not less than 10mm with 1part of cement and 4 part of find sand of 1.25 fineness modulus. As per SI. No.-584
Cement concrete with 2cm gauge approved stone ballast, approved coarse sand. cement in the proportion 1:2:4 including supply of all materials,labour and tools and plants etc. required for proper completion of the work.
Maintainance of First Year (@1% of Total Work Amount of 1 to 30)
Maintainance of Second Year (@1.5% of Total Work Amount of 1 to 30)
Maintainance of Third Year (@2% of Total Work Amount of 1 to 30)
Maintainance of Fourth Year (@2.5% of Total Work Amount of 1 to 30)
Maintainance of Fifth Year (@3% of Total Work Amount of 1 to 30)
M/s Nav Bharat Trading Company
surya construction co.
SIDDHARTH CONSTRUCTION
Raja Infraconstruction Pvt Ltd
M/S ARUNIMA CONSTRUCTIONS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid