| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.9 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | Rejected-Technical | - | Rejected-Technical Not Qualified |
| Sl No | Description | Qty | Unit | M MARIMUTHU L2 | SAMIYAPPAN N L1 |
|---|---|---|---|---|---|
| 1.00 | Dismantling ,Brick Masonry in cement mortar walls under 3M Height clearing away and carefully stacking materials useful for reuse for any thickness of walls including all charges etc ., complete as per standard specifications. | 7.7 | 1M3( One cubic meter) | 235 ₹1,809.5 | 231 ₹1,778.7 Lowest |
| 2.00 | Dismantling Reinforced Cement Concrete by manual /by using deploying machineries including cost and conveyance of all material etc complete as per standard specification . | 1 | 1M3( One cubic meter) | 4,310 ₹4,310 | 4,308 ₹4,308 Lowest |
| 3.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum | 10 | 1M3( One cubic meter) | 220 ₹2,200 | 217 ₹2,170 Lowest |
| 4.00 | Removal of Excavated Excess Earth away from the site to 2K.M including loading and transportation charges etc, complete as per standard specification. For 1M3 | 13 | 1M3( One cubic meter) | 70 ₹910 | 67 ₹871 Lowest |
| 5.00 | Supplying and filling in foundation and basement with Well Gravel in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. | 3 | 1M3( One cubic meter) | 270 ₹810 | 268 ₹804 Lowest |
| 6.00 | Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and Eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification | 2.2 | 1M3( One cubic meter) | 5,109 ₹11,239.8 | 5,105 ₹11,231 Lowest |
| 7.00 | Brick work in CM 1:5 (one cement & five Crushed stone Sand ) using II class ground moulded bricks of size 9"X43/8"X 2 3/4" including finishing, curing, etc., complete complying with standard specification - 100CFTetc complete. | 1.5 | 1M3( One cubic meter) | 7,100 ₹10,650 | 7,095 ₹10,642.5 Lowest |
| 8.00Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 | |||||
| 8.10 | a) Footing & Grade Beam | 13 | 1M2( One square meter) | 615 ₹7,995 | 613 ₹7,969 Lowest |
| 8.20 | b) Column | 16 | 1M2( One square meter) | 1,230 ₹19,680 | 1,228 ₹19,648 Lowest |
Tender Value
₹3.5 L
EMD Value
₹3,500
Closing Date
23 Oct 2025, 3:00 pmClosed
Commissioner, Dharapuram Municipality
Dhrapuram Municipality, 207A, Park Road, Dharapuram 638656
Dismantling the Damaged pump room and Construction of RCC Plate form at Ward 07 kottai medu in Dharapuram Municipality
2025_MAWS_616034_1
3245/2025/E2
Open Tender
Miscellaneous Works
Works
Dharapuram Municipality
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹3,500
5 Jan 2026
22 Oct 2025
23 Oct 2025
22 Oct 2025
23 Oct 2025
22 Oct 2025
22 Oct 2025 - 23 Oct 2025
Amount
Dismantling ,Brick Masonry in cement mortar walls under 3M Height clearing away and carefully stacking materials useful for reuse for any thickness of walls including all charges etc ., complete as per standard specifications.
Dismantling Reinforced Cement Concrete by manual /by using deploying machineries including cost and conveyance of all material etc complete as per standard specification .
Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum
Removal of Excavated Excess Earth away from the site to 2K.M including loading and transportation charges etc, complete as per standard specification. For 1M3
Supplying and filling in foundation and basement with Well Gravel in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification.
Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and Eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification
Brick work in CM 1:5 (one cement & five Crushed stone Sand ) using II class ground moulded bricks of size 9"X43/8"X 2 3/4" including finishing, curing, etc., complete complying with standard specification - 100CFTetc complete.
Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38
a) Footing & Grade Beam
b) Column
c) Slab
Reinforced Cement concrete 1:1.5 :3 (one cement, one and half M.sand & three course aggregate) using 20mm gauge hand broken/ and broken granite stone for all RCC items of works excluding centering shuttering and cost of reinforcement but including curing etc.,complete and also including fixing fan clamps and fixtures in rcc works wherever necessary as directed by departmental officer etc., complete.
a) Up to Basement
b)Above Ground level
c)Slab
Suppling and fabricating and placing in position MS (or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors.
Plastering with cement mortar 1:5 (One part of Cement and Five part of Plastering Sand (P- Sand)) 12mm, thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications
Plastering with cement mortar 1:3 (One part of Cement and Three part of Plastering Sand (P- Sand)), 10mm thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications
Painting two coats for Interior surface with approved Interior Plastic Emulsion paint approved quality and colour over a priming coat, including thorough scrapping, clean removal of dirt, etc complete and including necessary plaster of paris, putty, wherever required etc, complete as per standard specification.
Supply and delivery of MS Kiosk of size 0.75m x 0.45m x 0.75m made up of MS angle of size 50mm x 50mmx 4mm all-round covered with 16 gauge MS sheet and kiosk door charges etc.,locking arrangements and labour including cutting, welding, grinding locking arrangement and, labour charges etc., complete
Supply and run of 2 of 4 sq.mm (56/0.3) PVC insulated cu.conductor of 1100 V grade in 25mm GI pipe,bend and bolt with necessary angle iron up night and end supports for service mains etc., complete Service pipe
Supply and run of 2 of 4 sq.mm (56/0.3) PVC insulated cu.conductor of 1100 V grade on 7/20 GI bearer wire and reals for service connection main from EB pole to service pipe
Supply and fixing of Miniature circuit breakers 240V/415V 50HZ AC Supply suitable for Both lighting and Motor circuits.All other ISI makes with ISI (std.) /HPL /Havell's /equivalent) Four pole 6A to 32A, 10 KA
Supply and fixing of Fuse Units (Anchor/Equivalent) 32 Amps Porcelain fuse unit (500V)
Manufacturing, supplying and fixing in position plain cement concrete precast kerb slab of size 600mm x 600mm x 100mm in Cement Concrete 1:1.5:3 (One cement, Two M - sand and Four jelly) using 20mm HBG stone jelly including cost of moulding charges, casting of slab, finishing, curing, fixing and pointing the slab with CM 1:3 (One Cement and Three Sand) to full depth of slab etc., complete complying with standard specification and as directed
Supply and delivery and fixing of HDPE tank as per IS 12701/1996 including loading and unloading transportation and labour charge for fixing GI Pipe and specials for pipe connection works including cutting ,threading and fixing charges etc.
Labour charge for laying GI material including all cost etc complete as per Standard Specification.
Supply and Fixing of PVC & GI Pipe including all cost of material and labour charge etc
25MM GI Pipe
25MM GI Coupling
25MM GI Union
25MM Elbow
25MM Tee
25MM GM Gate Valve
M MARIMUTHU (BID ID -1492950)
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.31 MB
WSTenderNotice23102025.pdf
Tender Documents • 0.30 MB
BOQ_736085.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .