| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.9 LAdmitted-Finance TAMIL NADU TN | COIMBATORE | TAMIL NADU | 638459 | ₹9.9 L | L1 | Admitted-Finance |
| 2 | L2₹10.2 LAdmitted-Finance | ₹10.2 L | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | PRV INFRASTRUCTURE L2 | MUTHU CONSTRUCTION L1 |
|---|---|---|---|---|---|
| 1.001)Construction of Passenger shelter at Ullikottai Keelatheru petrol bunk Opposite in Ullikottai Panchayat | |||||
| 2.00 | Earth work excavation depositing on bank with initial lead and lift as per SS 20 B incl cost and conveyance of all charges etc complete | 30.83 | Cum | 270 ₹8,324.10 | 263 ₹8,108.29 |
| 3.00 | Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification. | 5 | Cum | 125 ₹625 | 120 ₹600 |
| 4.00 | Supplying and Filling foundation and basement with fillin Cartted Earth not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification. | 5.25 | Cum | 2,600 ₹13,650 | 2,547 ₹13,371.75 |
| 5.00 | Cement concrete 1:4:8 mix using 40mm HBG Metal including cost and conveyance of all materials and all labour chages etc., complete | 5.64 | Cum | 6,450 ₹36,378 | 6,396 ₹36,073.44 |
| 6.00Brick work in cement mortar 1:5 mix using country bricks including cost and conveyance of all materials to site and all labour charges etc complete. A) Below Basement | |||||
| 7.00 | A) Belowe Basement | 4.65 | Cum | 6,350 ₹29,527.50 | 6,283 ₹29,215.95 |
| 8.00 | B) Above Basement | 6.16 | Cum | 6,400 ₹39,424 | 6,376 ₹39,276.16 |
| 9.00Cement concrete M20 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and providing fixtures like fan clamps in the RCC floor or roof slabs wherever necessary and bearing surfaces of walls , sides and bottom of the slabs, beams etc., shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications. I) upto Basement | |||||
| 10.00 | I)Belowe Basement | 6.98 | Cum | 9,700 ₹67,706 | 9,487 ₹66,219.26 |
Tender Value
₹10 L
Closing Date
18 Feb 2026, 3:00 pmClosed
block deBDO OFFICE MANNARGUDIvelopment officer(BP)
BDO OFFICE MANNARGUDI
CONSTRUCTION OF BUS SHELTER IN ULLIKOTTAI PETROL BUNK NEAR AT ULLIKOTTAI PANCHAYAT
2026_RDTN_655114_3
3497/2025a8dt.09.02.2026
Open Tender
Civil Works - Others
60 days
MANNARGUDI
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
Exempted
BDO OFFICE MANNARGUDI
20 Feb 2026
11 Feb 2026
18 Feb 2026
11 Feb 2026
18 Feb 2026
11 Feb 2026
11 Feb 2026 - 17 Feb 2026
11 Feb 2026
1)Construction of Passenger shelter at Ullikottai Keelatheru petrol bunk Opposite in Ullikottai Panchayat
Earth work excavation depositing on bank with initial lead and lift as per SS 20 B incl cost and conveyance of all charges etc complete
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Supplying and Filling foundation and basement with fillin Cartted Earth not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1:4:8 mix using 40mm HBG Metal including cost and conveyance of all materials and all labour chages etc., complete
Brick work in cement mortar 1:5 mix using country bricks including cost and conveyance of all materials to site and all labour charges etc complete. A) Below Basement
A) Belowe Basement
B) Above Basement
Cement concrete M20 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and providing fixtures like fan clamps in the RCC floor or roof slabs wherever necessary and bearing surfaces of walls , sides and bottom of the slabs, beams etc., shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications. I) upto Basement
I)Belowe Basement
II)Above Basement
Supplying and fabrication of steel including cost and conveyance of steel to site and cost of binding wire including all labour charges for cutting,bending, tying and forming grills for all works
Supplying and errection of centering for sides and soffits with M.S.sheet and country wood props including hire charges for materials and all labour charges etc complete I) Below Basement
I)with struting Ground level
II)coloumn
Weathering Course Roof concrete including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and th.en sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc.,complete complying with standard specifications and as directed by the Departmental Officers. [The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty should be got approved by the Executive Engineer before use on work. (Based on SoR 2024-25)
Finishing the top of the roof with one course of Machine Pressed Tiles of size 23x23x2 cm of approved quality laid in CEMENT MORTAR 1:3(One cement and three sand) 12 mm thick mixed with water proofing compound conforming to ISS by 2% weight of cement used and the joint pointed neatly to full depth of tiles with the same water proofing compound mixed with cement mortar,red oxide, etc., complete complying with standard specification
Providing Granite slab
Providing Granite slab (Double Polished)
Plastering with cement mortar 1:5 mix to 12mm thick including cost and conveyance of all materials to site and all labour charges etc complete.
Plastering with cement mortar 1:3 mix to 12mm thick including cost and conveyance of all materials to site and all labour charges etc complete.
Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and th.en sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc.,complete complying with standard specifications and as directed by the Departmental Officers. [The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty should be got approved by the Executive Engineer before use on work. (Based on SoR 2024-25)
Exterior Emulsion Paint including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and th.en sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc.,complete complying with standard specifications and as directed by the Departmental Officers. [The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty should be got approved by the Executive Engineer before use on work. (Based on SoR 2024-25)
Rainwater Pipe fixing
Wiring with 2x1.5(22/0.3) sqmm PVC unsheathed SC Copper conductor of 1100 V grade in suitable PVC rigid pipe on wall and ceiling with PVC accessories and with T.W. switch box with 5amps F.T. switch in flush with wall covered with hylum sheet of 3mm thick with painting of suitable colour with continuous earth wireconnection of 14 SWG wire for cocealed Light point/fan point (5 points per coil) [ SD No. 24 ]
Wiring with 2x1.5(22/0.3) sqmm PVC unsheathed SC Copper conductor of 1100 V grade in suitable PVC rigid pipe on wall and ceiling with PVC accessories and with T.W. switch box with 5amps F.T. switch in flush with wall covered with hylum sheet of 3mm thick with painting of suitable colour with continuous earth wireconnection of 14 SWG wire for cocealed Light point/fan point (5 points per coil) [ SD No. 25 ]
Supplying and fixing of CFL bulb
Supplying and fixing of Bulket Fitting
Rainwater Harwesting
ss Handrails
Painting and lettering of Name board
Provision for Photo charges
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.69 MB
BOQ_785488.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid