| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹9.5 LAccepted-AOC | L-1 | Accepted-AOC Work allotted after financial approval from committee | |
| 2 | L-2₹11.8 L+₹2.4 L (24.9%)Rejected-AOC | L-2 | Rejected-AOC Work not allotted | |
| 3 | Rejected-Technical KANPUR NAGAR | UTTAR PRADESH | 209402 | - | Rejected-Technical All conditions not fulfill |
| Sl No | Description | Qty | Unit | M/s Shri Balaji Traders L2 | HS Associates L1 |
|---|---|---|---|---|---|
| 1.0005 MVA T/F at various 33/11 KV S/s under EDD, Kiraoli. | |||||
| 1.01 | Opening of all connections of 05 MVA Power TF as per direction of supervising Engineer. | 9 | Job | 4,130 ₹37,170 | 3,304 ₹29,736 Lowest |
| 1.02 | Drain out of TFs Oil and store in drum for replacement of damaged packing of 05 MVA Power TF. | 8 | Job | 11,800 ₹94,400 | 9,003.4 ₹72,027.2 Lowest |
| 1.03 | Opening of 33 KV, 11 KV busing rod very carefully and removal of damage packing and replacement of packing and fixing of 33 KV, 11 KV busing rod complete. | 7 | Job | 4,130 ₹28,910 | 3,256.8 ₹22,797.6 Lowest |
| 1.04 | Replacement of damaged inspection cover packing with new packing and fixing. | 4 | Job | 2,950 ₹11,800 | 2,206.6 ₹8,826.4 Lowest |
| 1.05 | Replacement of LT side Rod 02 No (Required material provided by contractor at his own cost). | 8 | Job | 5,723 ₹45,784 | 3,540 ₹28,320 Lowest |
| 1.06 | Radiator air release and balb Seal Replacement. | 6 | Job | 4,130 ₹24,780 | 3,304 ₹19,824 Lowest |
| 1.07 | Opening of radiator and removal of damage packing fixing packing of radiator and fitting of radiator of 05 MVA Power T/Fs by help of craine and as per direction of supervising Engineer. | 22 | Job | 4,484 ₹98,648 | 3,776 ₹83,072 Lowest |
| 1.08 | Equaliser pipe remove damage packing and dry foum fixing new packing. | 4 | Job | 4,484 ₹17,936 | 3,504.6 ₹14,018.4 Lowest |
| 1.09 | Replacement of WTI. (Required material provided by contractor at his own cost) | 7 | Set | 5,015 ₹35,105 | 4,012 ₹28,084 Lowest |
Tender Value
₹9.5 L
EMD Value
₹10,000
Closing Date
30 Jul 2025, 1:00 pmClosed
SE
EDC, B 690, Kamla Nagar, Agra
Work of Overhauling, Replacement of Packaging and Other associated works on 05-10 MVA Power TFs situated at Various Sub Station under EDD, Kiraoli, Agra
2025_DVVNL_1051642_2
04/EDCA/2025-26
Open Tender
Electrical Works
Piece-work
180 days
EDC, B 690, Kamla Nagar
As per tender specification
2 documents required · 2 mandatory
₹1,180
www.dvvnl.org
₹10,000
14 Jan 2026
1 Jul 2025
30 Jul 2025
1 Jul 2025
30 Jul 2025
1 Jul 2025
05 MVA T/F at various 33/11 KV S/s under EDD, Kiraoli.
Opening of all connections of 05 MVA Power TF as per direction of supervising Engineer.
Drain out of TFs Oil and store in drum for replacement of damaged packing of 05 MVA Power TF.
Opening of 33 KV, 11 KV busing rod very carefully and removal of damage packing and replacement of packing and fixing of 33 KV, 11 KV busing rod complete.
Replacement of damaged inspection cover packing with new packing and fixing.
Replacement of LT side Rod 02 No (Required material provided by contractor at his own cost).
Radiator air release and balb Seal Replacement.
Opening of radiator and removal of damage packing fixing packing of radiator and fitting of radiator of 05 MVA Power T/Fs by help of craine and as per direction of supervising Engineer.
Equaliser pipe remove damage packing and dry foum fixing new packing.
Replacement of WTI. (Required material provided by contractor at his own cost)
Replacement of OTI. (Required material provided by contractor at his own cost)
Filling of Transformer Oil in ther power T/F after replacement of all required packing as per direction of supervising Engineer.
Making of all connections of 05 MVA Power T/Fs as per direction of supervising Engineer.
All packing set complete made of cork sheet for 05 MVA Power T/Fs (Required material provided by contractor at his own cost).
Centrifuging of power TF oil of 05 MVA.
Opening of conservator tank by the help of craine removal of damaged packing. Cleaning of surface fixing of packing and fitting of conservator tank.
HV Mounting Bushing fixing arrengement.
Breather Complete with Silica Gel 3 Kg, each. (Required material provided by contractor at his own cost)
Fixing of Arching Horn. (Required material provided by contractor at his own cost)
Bushing Fixing Clamp 630 Amp. (Required material provided by contractor at his own cost)
Magnetic oil level gauge. (Required material provided by contractor at his own cost)
Lifting of Top Cover by the help fo craine for replacement of damaged packing of top cover including removal of damaged packing and surface including tightining of nut & bolt.
Cleaning of Power TF by the castic soda/required chemical poweder for removal of dust/oily surface.
10 MVA T/F at 33/11 KV S/s Kiraoli Rural.
Opening of all connections of 10 MVA Power TF as per direction of supervising Engineer.
Drain out of TFs Oil and store in drum for replacement of damaged packing of 10 MVA Power TF.
Opening of 33 KV, 11 KV busing rod very carefully and removal of damage packing and replacement of packing and fixing of 33 KV, 11 KV busing rod complete.
Replacement of damaged inspection cover packing with new packing and fixing.
Radiator air release and balb Seal Replacement.
Opening of radiator and removal of damage packing fixing packing of radiator and fitting of radiator of 10 MVA Power T/Fs by help of craine and as per direction of supervising Engineer.
Equaliser pipe remove damage packing and dry foum fixing new packing.
Replacement of oil level gauge damage glass and packing. (Required material provided by contractor at his own cost).
Filling of Transformer Oil in ther power T/F after replacement of all required packing as per direction of supervising Engineer.
Making of all connections of 10 MVA Power T/Fs as per direction of supervising Engineer.
Replacement of MOG. (Required material provided by contractor at his own cost)
Replacement of WTI. (Required material provided by contractor at his own cost)
Replacement of OTI. (Required material provided by contractor at his own cost)
Fixing of Arching Horn and Bushing. (Required material provided by contractor at his own cost)
All packing set complete made of cork sheet for 10 MVA Power T/Fs. (Required material provided by contractor at his own cost)
Cleaning of Power TF by the castic soda/required chemical poweder for removal of dust/oily surface.
M/s Shri Balaji Traders (BID ID -5389208)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .