Tender Value
₹27.3 Cr
EMD Value
₹54.7 L
Closing Date
25 Aug 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
120 days
Expenditure
Capital (Works)
CPM/KOL 2
8 conditions · 2 needing a document upload
The rates and prices to be tendered in the Pricing Schedule are for completed and finished items of work and complete in all respects. It will be deemed to have included all construction plants, tools, machinery, labour, supervision, materials, fuel, oil, consumables, electical power, water, transportation, all leads and lifts, dewatering, all temporary works and false works, construction of temporary stores and buildings, fencing, watering, lighting, erection, maintenance, night working, inspection facilities, safety measures at work sites casting yard for workmen and road users, preparation of design and drawings pertaining to the casting yard, staging, shuttering/sacrificial steel shuttering, form work, stacking yard etc., establishment and overhead charges, labour camps, insurance costs for labour and works, contractor's profit, all taxes, royalties, duties, cess, octroi, and other levies and other charges together with all general risks, liabilities and obligations set out or implied in the contract and including remedy of any defects during the Defect Liability Period, unless otherwise provided in Pricing schedule.
The bidder has to quote rates only through electronic mode in the IREPS portal only. The rates must not be quoted elsewhere, i.e. the quoted rates must appear only during the opening of financial bid.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Item no. 35 to 88 of Schedule-A5 are related to auditorium, conference hall etc. and these items shall be executed as per specifications laid down in GFC drawings and as per direction of the Engineer-in-Charge.
"Construction of Metro Railway Training Academy at Noapara Carshed (Phase-1)."
RVNL_KOL2_METRO_MRTA_PH1~RVNL
RVNL_KOL2_METRO_MRTA_PH1
Special Limited
Works - General
18 Months
Kolkata, West Bengal
₹0
₹54.7 L
25 Aug 2026
11 Aug 2026
19 Aug 2026
161 items across 7 schedules · ₹27,06,18,890.41 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | "Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-incharge. All kinds of soil". | cum | 3600.00 | 177.5 | 6,39,000 |
| 2 | "Excavating trenches in all kinds of soil by mechanical / manual means of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, for all depth, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 mPipes, cables etc, not exceeding 80 mm dia." | Metre | 700.00 | 215.6 | 1,50,920 |
| 3 | "Excavating trenches in all kinds of soil by mechanical / manual means of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, for all depth, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50m. Pipes, cables etc. exceeding 80 mm dia. but not exceeding 300 mm dia | Metre | 1400.00 | 352.15 | 4,93,010 |
| 4 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. | cum | 1400.00 | 196 | 2,74,400 |
| 5 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | cum | 900.00 | 2,123.75 | 19,11,375 |
| Schedule total | ₹34,68,705 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
BidDocumentMRTA_Noapara_1.pdf Bid Document Vol I
ATTACHMENT
BidDocumentVol.II_1.pdf
ATTACHMENT
BidDocumentMRTA_Noapara_1.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .