Tender Value
₹4.1 L
EMD Value
₹5,200
Closing Date
1 Mar 2024, 6:00 pmClosed
SO EM BHATGAON AREA
OFFICE OF THE SO EM BHATGAON AREA
Erection of 3.3 kV Overhead Line from Incline No. 1 2 Substation to mouth of Incline No. 1 and connection and transportation of PVC armoured cable from Incline mouth to 2L 36R LPP Substation of Bhatgaon Colliery and Erection of 3.3 kV Overhead Line
2024_SECL_301401_1
GM/Bhat/EM/e-open tender/2023-24/80 dtd 13.02.2024
Open Tender
Electrical and Maintenance Works
Item Rate
30 days
SECL BHATGAON AREA
As per NIT
9 documents required · 9 mandatory
₹5,200
25 Oct 2024
14 Feb 2024
2 Mar 2024
14 Feb 2024
1 Mar 2024
14 Feb 2024
14 Feb 2024 - 19 Feb 2024
Amount
Item Description/ Heading
Labour Part
A Single Poles (Total Single Poles - 02)
Pit Digging
Stay Pit Digging
Transportation of pole from road side to pole pit for a lead of 1 km (poles will be provided by SECL)
Shifting of material to pole pits
Cross arm fixing complete with top clamp
Pole erection complete
Stay erection complete
Concreting of poles @0.6 cmt per pole and 0.05 cmt per pole for base pading (1:3:6)(for Rail Pole)
Insulator fixing at each location
Painting and numbering etc including steel support
Stringing of line for all 3 phases (Conductors shall be provided by SECL)
Carpet Guarding
Twisting of jointing sleeves
B Double Pole (Total DP - 03)
Pit Digging
Stay Pit Digging
Shifting of material to pole pits
Transportation of pole from road side to pole pit for a lead of 1 km (pole will be provided by SECL)
Cross arm fixing complete including insulators etc.
Pole erection complete (including earthing)
Concreting of stay @0.3 cmt/stay and poles
Stay erection complete
Painting of cross arm and numbering of poles etc.
C Triple Pole (Total TP - 01)
Pit Digging
Stay Pit Digging
Transportation of pole from road side to pole pit for a lead of 1 km (pole will be provided by SECL)
Shifting of material to pole pits
Cross arm fixing complete with top clamp
Pole erection complete
Concreting of poles @0.6 cmt per pole and 0.05 cmt per pole for base pading (1:3:6)(for Rail Pole)
Stay erection complete
Insulator fixing at each location
Painting and numbering etc including steel support
Stringing of line for all 3 phases (Conductors shall be provided by SECL)
Carpet Guarding
Twisting of jointing sleeves
D Installation of AB Switch (02 No.)
Fixing of AB switch complete with handle isolator
Stringing of conductor with fixing of terminal clamps
Fixing of T-clamps for jumpers and bimetallic clamps
Jumpering of AB Switch and fixing of terminal clamps
E Running Earth
Providing and fixing 6 SWG dia G.I. wire on surface or in recess for loop earthing as required (Running Earth)
F HV Cable Jointing and End Termination - 70 Sq. mm
HV Cable Jointing and End Termination for 3 core 70 Sq. mm
G HV Cable Jointing and End Termination - 120 Sq. mm
HV Cable Jointing and End Termination for 3 core 120 Sq. mm
I Transportation & laying of 120 Sq. mm PVC Armoured cable from Incline No. 1 mouth to 2L/36R LPP Substation
Manpower required- 16 unskilled labours for 3 days
Material Part
Earthing coil per pole (coil of 115 turns of 50mm dis and 2.5 mtrs lead of 4mm GI Wire)
Barbed Wire @2kg/pole
Back Clamp for Pole
MS Nut and Bolt 16x160mm
11 kV "V" Cross Arm Channel type 75x40 mm
Stay Set 20mm
Stay Wire 7/8 SWG @8.5Kg/stay
Stay Clamp
Stay Insulator
DC Cross Arm 5' center 100x50mm MS Channel
Bracing Set 5' center DP
MS Nut and Bolt 16x40mm
MS Nut and Bolt 16x200mm
11KV Disc Insulator
11KV Pin Insulator
11 kV Guarding Channel 100x50mm
GI Wire 6 SWG (Guarding)
GI Wire 8 SWG (Guarding)
Tension / anchoring Clamp with tracking protection IPC
Lightning Arrestor
Running Earth
HV Cable Jointing and End Termination- Outdoor cable jointing kit with cast resin compound with lugs for 11 KV grade XLPE cable for 3 core 70 sq. mm.
HV Cable Jointing and End Termination- Outdoor cable jointing kit with cast resin compound with lugs for 11 KV grade XLPE cable for 3 core 120 sq. mm.
AB Switch (11 kV) with complete fitting
Overhead Charges (market fluctuation, contractor's profit on material cost)
Total impact of GST for the purpose of CTC
Mahamaya Electircals
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_312231.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .