| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹93.4 LAccepted-AOC GRAM NAURANGABAD THANA DHAMPUR DISTRICT BIJNOR UTTAR PRADESH | NAURANGABAD | BIJNOR | UTTAR PRADESH | ₹93.4 L | L1 | Accepted-AOC L1 |
| 2 | L2₹1.1 CrRejected-AOC | ₹1.1 Cr | L2 | Rejected-AOC L2 |
Tender Value
₹1.1 Cr
EMD Value
₹7.7 L
Closing Date
5 May 2026, 12:00 pmClosed
Superintending Engineer
Office of The Superintending Engineer Rampur Circle PWD Rampur
Construction of 4 x 4 Mtr. span 5 cell box culvert and approach road at Sherkot Harewali road to Kopa
2026_CEMBD_1143259_1
2006/E-Nivida-R.Circle/26-27 Dt. 29.03.2026
Open Tender
Civil Works - Bridges
365 days
Bijnor
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,354
₹7.7 L
Yes
Rampur
25 May 2026
30 Apr 2026
5 May 2026
30 Apr 2026
5 May 2026
30 Apr 2026
1 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. as per MORT&H specification 304 Sr. No. 15.01. (Including labour cess but excluding GST) | - | Cum | 135 | - | BI01010001010000000000000515BI0100001113 |
| 2 | Flexible Apron : Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less than 40 kg beyond curtain wall. As per MORTH 2507.2, Sr. No. 16.11. (Including royalty, labour cess but excluding GST) | 500 | Cum | 2,620 | ₹13,10,000 | BI01010001010000000000000515BI0100001113 |
| 3 | Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical specification. As per MORTH Specification 2504 Sr. No. 16.05. (Including royalty, labour cess but excluding GST) | 87 | Cum | 2,810 | ₹2,44,470 | BI01010001010000000000000515BI0100001113 |
| 4 | (PCC M-15) Plain Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. As per MORTH 1500, 1700 & 2100, Sr. No. 12.08A Case I. (Including Royalty, labour cess but excluding GST) | 63 | Cum | 5,770 | ₹3,63,510 | BI01010001010000000000000515BI0100001113 |
| 5 | RCC Grade M-20 Reinforced Cement Concrete in open foundation complete as per drawing and technical specification. RCC Grade M25 using batching plant transit mixer & concrete pump. As per MORTH Specification clause 1500, 1700 & 2100 Sr. No. 12.08G. (Including Royalty, labour cess but excluding GST) | 510 | Cum | 6,830 | ₹34,83,300 | BI01010001010000000000000515BI0100001113 |
| 6 | Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications complete as per MORTH Specification 1600 Sr. No. 15.13 (Including labour cess but excluding GST) | 41 | MT | 77,900 | ₹31,93,900 | BI01010001010000000000000515BI0100001113 |
| 7 | Supplying & Fixing PVC pipe for bridge work of pressure 6 kg/cm² of 100mm internal dia including cost of all materials, labour and T&P etc. required for proper completion of work as per item no. 24, ch. 1 of PWD S.O.R.(for weep hole) (Including labour cess but excluding GST) | 66 | Rm | 135 | ₹8,910 | BI01010001010000000000000515BI0100001113 |
| 8 | Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 sqm. As per MORTH Specification Clause 800 Sr. No 14.16. (Including labour cess but excluding GST) | 125 | Sqm | 178 | ₹22,250 | BI01010001010000000000000515BI0100001113 |
| 9 | Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1 Sr. No. 3.14. (Including labour cess but excluding GST) | 3,360 | Cum | 205 | ₹6,88,800 | BI01010001010000000000000515BI0100001113 |
| 10 | Construction of Granular Sub-Base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density complete. As per MORTH Specification Clause 401 Sr. No. 4.01 B. (Including labour cess, royalty but excluding GST) | 109 | Cum | 3,270 | ₹3,56,430 | BI01010001010000000000000515BI0100001113 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.31 MB
t2.pdf
Tender Documents • 1.63 MB
BOQ_2135392.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid