| 1 | L1₹1.2 CrAccepted-AOC | ₹1.2 Cr | L1 | Accepted-AOC Accepted |
| 2 | L2₹1.2 Cr+₹1.1 L (0.93%)Rejected-Finance 18 CORPORATION ROAD DEVAKOTTAI | SIVAGANGA | TAMIL NADU | 630001 | ₹1.2 Cr+₹1.1 L (0.93%) | L2 | Rejected-Finance Rejected |
Tender Value
₹1.2 Cr
EMD Value
₹1.2 L
Closing Date
3 May 2023, 3:00 pmClosed
Additional Collector DRDA Coimbatore
DRDA,Coimbatore
Strengthening and renewal of 2 roads in SSKulam Block, Coimbatore district under MGSMT 22-23
2023_RDTN_306851_1
DIPR/2018/Tender/2023 Dated 05.04.2023
Open Tender
Civil Works - Roads
Item Wise
210 days
Coimbatore
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹1.2 L
Yes
7 Jun 2023
26 Apr 2023
3 May 2023
26 Apr 2023
3 May 2023
26 Apr 2023
Amount
1.Renewal of the road from Kalipalayam to onnipalayam road Km 0/0-2/400
Clearing the scrub jungle by uprooting including all cutting charges and disposing of the products and clearing as directed by departmental officers including all incidental charges etc. complete.
Providing 25 mm advance BT patches using 13.2mm HBG IRC metal using 44Kg of bitumen 80/100 grade including cost and conveyance of all labour charges etc., complete Km 0/0-1/0
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal
Excavation in soil using Hydraulic Excavator and Tippers with disposal upto 1000m Excavation for road work in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers. Trimming bottom and side slopes , in accordance with requirements of lines grades and cross - section , and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m asb per Technical specification clause 302.3
Embankment Formation Using Filling Road Way Cutting Earth
Borrow Pit Earth Filling
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in Subbase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.7 kg/sqm using mechanical means as per Technical Specification Clause 502
For 50 mm Patches
Applying TACK COAT over Primed WBM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
For 50 mm Patches
Applying tack coat over BT surface (not treated with primer) using 3Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for powerroller, watersprinkler and all other incidental charges such as traffic barricading and providing dangerlights etc. comp for side berms km 0/0-1/0
Supplying and fixing Guard stones including painting and lettering as directed by the departmental officers etc., complete
Provision for Kilometre stones
Provision for Hecta Metre stones
Provision for Supplying and erection of Scheme Name board Cum Citizen Board
Providing and erecting of Retro - reflectorized cautionary , Mandatory and Informatory signs (without definition board) made out of High Intensity Prismatic Grade Sheeting confirming to Type - IV standards of IRC - 67: 2012 and ASTM D -09, Specification and fixed over 2mm thick Aluminium sheet fixed over a black supporting frame of25MMx25mmx3mm Mild steel angle and supported on a mild steel angle post 75x75x6 mm with a clear height of not less than 2.10m from the ground level to the bottom of the sign board and 0.60m below ground level. The sign post should be painted as per IRC 67-2012 and firmly fixed to the ground by means of properly designed foundadation with M15 grade cement concrete 45cmx45cmx60cm size including cost and conveyance of all materials , equipment , Machinary and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. Higj intensity Retro Reflectro sheet shall consist of minimum coefficient of Retro - reflection as per Table 6.6 of IRC 67-2012. The retro - reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC 67 - 2012 ( as per MORTH Specification No 801)
Stop Sighn Board
Rumble Strips Ahead
Provision of 1 nos. rumble strips covered with premix bituminous carpet, 15-20 mm high at centre, 250 mm wide placed at 1 m centre-to-centre at approved locations to control speed, marked with white strips of road marking paint.
Rumble Strips
Providing and erecting of Retro - reflectorized cautionary , Mandatory and Informatory signs (without definition board) made out of High Intensity Prismatic Grade Sheeting confirming to Type - IV standards of IRC - 67: 2012 and ASTM D -09, Specification and fixed over 2mm thick Aluminium sheet fixed over a black supporting frame of25MMx25mmx3mm Mild steel angle and supported on a mild steel angle post 75x75x6 mm with a clear height of not less than 2.10m from the ground level to the bottom of the sign board and 0.60m below ground level. The sign post should be painted as per IRC 67-2012 and firmly fixed to the ground by means of properly designed foundadation with M15 grade cement concrete 45cmx45cmx60cm size including cost and conveyance of all materials , equipment , Machinary and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. Higj intensity Retro Reflectro sheet shall consist of minimum coefficient of Retro - reflection as per Table 6.6 of IRC 67-2012. The retro - reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC 67 - 2012 ( as per MORTH Specification No 801)
Major Road Head
Providing and Fixing reflective road studs of category A raised pavement markers made out of Poly carbonate / methyl methercrylate / ABS moulded body confirming to ASTM D 788 and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face with retro reflectance and chromically values conforming to ASTM D428. The reflective raised pavement markers shall also confirm to the MORTH circular No RW/NH. 33023/10*97- DO .III dt 11.06.97.The height, width and length shall not be less than 15 mm , 90 mm and 100 mm and with minimum re4flective area of 13 sq.cm on each side and the slope to the base shall be 35+/-5 degree . Each reflector shall have a CIL not less than values specified in Table 2 of sais MORTH circular . The strength of detachment of the integrated cylindrical shanks, ( of diameter not less than 19+/-2 mm and height not less than 30+/-2 mm) from the body is to be a minimum value of 500Kgf . Fixing will be by drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturers recommandation and complete as directed by the engineer. The marker shall support a load of 13635 Kg tested in accordance with ASTM D4280 and confirming to IRC 35-2015 guidelines and MORTH specification 804 etc complete
Reflecting Studs
Providing and Fixing reflective road studs of category A raised pavement markers made out of Poly carbonate / methyl methercrylate / ABS moulded body confirming to ASTM D 788 and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face with retro reflectance and chromically values conforming to ASTM D428. The reflective raised pavement markers shall also confirm to the MORTH circular No RW/NH. 33023/10*97- DO .III dt 11.06.97.The height, width and length shall not be less than 15 mm , 90 mm and 100 mm and with minimum re4flective area of 13 sq.cm on each side and the slope to the base shall be 35+/-5 degree . Each reflector shall have a CIL not less than values specified in Table 2 of sais MORTH circular . The strength of detachment of the integrated cylindrical shanks, ( of diameter not less than 19+/-2 mm and height not less than 30+/-2 mm) from the body is to be a minimum value of 500Kgf . Fixing will be by drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturers recommandation and complete as directed by the engineer. The marker shall support a load of 13635 Kg tested in accordance with ASTM D4280 and confirming to IRC 35-2015 guidelines and MORTH specification 804 etc complete
Reflecting Studs
Road Marking by providing and laying of hot applied Thermoplastic Compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5mm exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes.
Towards the charges for routline maintenance of the road work executed under PMGSY including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP- 20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
2.Strengthening Of Road From Samanaickenpalayam to Athipalayam Road at Samanaickenpalayam H/O Vellamadai Panchayat.(R-82) KM 2/2 - 3/2.
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc complete
Picking the existing mettaled surface and sectioning including all labour charges etc, complete.
Excavation in soil using Hydraulic Excavator and Tippers with disposal upto 1000m Excavation for road work in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers. Trimming bottom and side slopes , in accordance with requirements of lines grades and cross - section , and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m asb per Technical specification clause 302.3
Embankment Formation Using Filling Road Way Cutting Earth
Borrow Pit Earth Filling
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in Subbase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete
Bituminous macadam of 50 mm thick shall consist of Construction in a single couse of compacted crushed aggregates premixed with bituminous binder of 80/100 grade at the rate of 3.5 % by weight of total mix to serve as base / binder course in accordance with MORTH rev IV cl.504 specification and in confirmity with drawing.
Providing and laying Bituminious concrete which shall consists of construction of a single course binder /wearing corse on a previosly prepared Bituminous base to the requirements of the specification using 60/70 grade bitumen as per MorRTH specificaton CI.508.
Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for powerroller, watersprinkler and all other incidental charges such as traffic barricading and providing dangerlights etc. comp for side berms Km 0/0-1/0
Supplying and fixing Kilometer Metre stones including painting and lettering as directed by the departmental officers etc., complete
Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete
Supplying and fixing Guard stones including painting and lettering as directed by the departmental officers etc., complete
Construction of Hardbed Ch 2900m.
Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days,using curing compound (where specified ) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501
Construction of Protection Wall CH :2500m
Earth work excavating and depositing on bank with initial lead of 10m and initial lead of 2m in hard stiff clay, stiff black cotton soil, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders (SS20B) etc., complete in all respects as directed by the departmental officers.
Plain Cement concrete 1:4:8 (One of cement, four of sand and eight of hard broken stone) using 40mm size hard broken stone for foundation inclusive of shoring, strutting, bailing out water, ramming, curing etc., complete in all respects as directed by the departmental officers..
Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Retro - Reflectorised Traffic Signs (with definition board) Type - IV - Providing and erecting of Retro - reflectorized cautionary , Mandatory and Informatory signs (without definition board) made out of High Intensity Prismatic Grade Sheeting confirming to Type - IV standards of IRC - 67: 2012 and ASTM D -09, Specification and fixed over 2mm thick Aluminium sheet fixed over a black supporting frame of25MMx25mmx3mm Mild steel angle and supported on a mild steel angle post 75x75x6 mm with a clear height of not less than 2.10m from the ground level to the bottom of the sign board and 0.60m below ground level. The sign post should be painted as per IRC 67-2012 and firmly fixed to the ground by means of properly designed foundadation with M15 grade cement concrete 45cmx45cmx60cm size including cost and conveyance of all materials , equipment , Machinary and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. Higj intensity Retro Reflectro sheet shall consist of minimum coefficient of Retro - reflection as per Table 6.6 of IRC 67-2012. The retro - reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC 67 - 2012 ( as per MORTH Specification No 801)
Stop Sighn Board
Rumble Strips Ahead
Retro - Reflectorised Traffic Signs (with out definition board) Type - IV - Providing and erecting of Retro - reflectorized cautionary , Mandatory and Informatory signs (without definition board) made out of High Intensity Prismatic Grade Sheeting confirming to Type - IV standards of IRC - 67: 2012 and ASTM D -09, Specification and fixed over 2mm thick Aluminium sheet fixed over a black supporting frame of25MMx25mmx3mm Mild steel angle and supported on a mild steel angle post 75x75x6 mm with a clear height of not less than 2.10m from the ground level to the bottom of the sign board and 0.60m below ground level. The sign post should be painted as per IRC 67-2012 and firmly fixed to the ground by means of properly designed foundadation with M15 grade cement concrete 45cmx45cmx60cm size including cost and conveyance of all materials , equipment , Machinary and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. Higj intensity Retro Reflectro sheet shall consist of minimum coefficient of Retro - reflection as per Table 6.6 of IRC 67-2012. The retro - reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC 67 - 2012 ( as per MORTH Specification No 801)
Major Road Head
60 cm Equilateral Triangle
Providing and Fixing reflective road studs of category A raised pavement markers made out of Poly carbonate / methyl methercrylate / ABS moulded body confirming to ASTM D 788 and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face with retro reflectance and chromically values conforming to ASTM D428. The reflective raised pavement markers shall also confirm to the MORTH circular No RW/NH. 33023/10*97- DO .III dt 11.06.97.The height, width and length shall not be less than 15 mm , 90 mm and 100 mm and with minimum re4flective area of 13 sq.cm on each side and the slope to the base shall be 35+/-5 degree . Each reflector shall have a CIL not less than values specified in Table 2 of sais MORTH circular . The strength of detachment of the integrated cylindrical shanks, ( of diameter not less than 19+/-2 mm and height not less than 30+/-2 mm) from the body is to be a minimum value of 500Kgf . Fixing will be by drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturers recommandation and complete as directed by the engineer. The marker shall support a load of 13635 Kg tested in accordance with ASTM D4280 and confirming to IRC 35-2015 guidelines and MORTH specification 804 etc complete
Reflecting Studs
Road Marking by providing and laying of hot applied Thermoplastic Compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5mm exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes.
Provision of 1 nos. rumble strips covered with premix bituminous carpet, 15-20 mm high at centre, 250 mm wide placed at 1 m centre-to-centre at approved locations to control speed, marked with white strips of road marking paint.
Rumble Strips
Towards the charges for routline maintenance of the road work executed under PMGSY including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP- 20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
V MEENAL AND CO
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .