Loading…
Loading…
Tender Value
₹2.7 Cr
EMD Value
₹2.9 L
Closing Date
13 Apr 2026, 2:45 pmClosed
25 KV Electrification work in connection with Construction of Block station at ROI in BSB division of N. E. Railway.
SrDEE-TRD-BSB-2025-26-T18~NER
SrDEE-TRD-BSB-2025-26-T18
Open
Works - General
9 Months
Varanasi, Uttar Pradesh
₹0
₹2.9 L
13 Apr 2026
20 Mar 2026
30 Mar 2026
2-Non-Schedule Items (Not available in SOR)
Item Breakup - 1-SOR Items
SOR Item No.1(a)- Preparation of designs and Per Track drawings for over head equipment KM VARANASI DIVISION-ELECTRICAL/NORTH EASTERN RLY
SOR Item No. 5(a) (i)- Supply without Insulator Each of mounting arrangment for span wire.
SOR Item No. 5(a) (i)- Erection with Insulator Each mounting arrangment for span wire.
SOR Item No. 8(a) (xii)- Marking/Painting of Each temperature & 'Y' measurement of OHE mast at BWA locations.
SOR Item No. 8(b)(i)- Supply without insulator of Each material for termination of Single conductor of Over head equipment or terminating wire.
SOR Item No. 8(b)(i)- Erection with of material Each for termination of Single conductor of Over head equipment or terminating wire.
SOR Item No.9(dz)- Supply without insulator of Each anti-creep with cadmium copper catenary wire in polluted area.
SOR Item No.9(dz)- Erection with insulator of Each anti-creep with cadmium copper catenary wire in polluted area.
SOR Item No.11(a)(i)- Supply without insulator Each of cut-in (9Tonne) Insulator.
SOR Item No.11(a)(i) (9Tonne) Insulator.
SOR Item No. 11(b)- Supply without insulator of Each 25kV Post Insulator.
SOR Item No. 11(b)- Erection of 25 kV Post Each Insulator.
SOR embedment of earth electrode.
SOR Item No.27(a) - Supply, o i l - filtration, Each testing and commissioning of L.T. supply transformers (10kVA).
SOR Item No.27(a) - Erection, oil- filtration, Each testing and commissioning of L.T. supply transformers (10kVA).
SOR Item No.27(c)- Supply, oil- filtration, testing Each and commissioning of L.T. supply transformers (25 kVA).
SOR Item No.27(c) - Erection, oil- filtration, Each testing and commissioning of L.T. supply transformers (25 kVA).
SOR Item No.27(d)- Supply, oil- filtration, Each testing and commissioning of L.T. supply transformers (50 kVA).
SOR Item No.27(d)- Erection, oil- filtration, Each testing and commissioning of L.T. supply transformers (50 kVA).
SOR Item No.28 - Supply without Insulator of 25 Each kV D.O. fuse switch.
SOR Item No.28 -Erection with Insulator of 25 Each kV D.O. fuse switch.
SOR Item No.31(a) - Transfer of equipment from Each one mast or support to another.(Supply)
SOR Item No.31(a) - Transfer of equipment from Each one mast or support to another.(Erection)
SOR Item No.31(d)- Dismantling of overhead Kilometre equipment.
SOR Item No.31(f)- Splicing & extension of an Each anchored OHE.
SOR Item No.31(gz)- Dismantling of a Section Each Insulator Assembly (Supply)
SOR Item No.31(gz)- Dismantling of a Section Each Insulator Assembly (Erection)
SOR Item No.31(i)- Dismantling of an Isolator. VARANASI DIVISION-ELECTRICAL/NORTH EASTERN RLY
SOR Post/Pedestal Insulator.
SOR Item No.36(a)-Unloading of all type steel MT structure.
SOR Item No. 36(b)- Loading of all type steel MT structure.
SOR Item No. 37(a)- Unloading of all type of MT Copper & Aluminium conductors.
SOR Item No. 37(b)- loading of all type of MT Copper & Aluminium conductors.
SOR Item No. 32- Extra on Erection rate of 5(a) Each (i) for work under power block.
SOR Item No. 32- Extra on Erection rate of 8(b) Each (i) for work under power block.
SOR Item No. 32-Extra on Erection rate of 9(dz) Each for work under power block
SOR Item No. 32-Extra on Erection rate of 11(a) Each (i) for work under power block.
SOR Item No. 32 - Extra on Erection rate of Each 31(a) for work under power block.
SOR Item No. 32- Extra on Erection rate of 31(d) Kilometre for work under power block.
SOR Item No. 32- Extra on Erection rate of 31(f) Each for work under power block.
SOR Item No. 32- Extra on Erection rate of Each 31(gz) for work under power block.
SOR Item No. 32- Extra on Erection rate of 31(i) Each for work under power block.
SOR Item No. 32- Extra on Erection rate of 31(j) Each for work under power block. Total 498043.00 Item- 2 Section -2 (Concrete) S No. Item Description of Item Unit Qty Rate Amount No
SOR Item No. 2(a) (ii)- Concrete for foundation cum and plinth in rocky soil. (Supply)
SOR Item No. 2(a) (ii)- Concrete for foundation cum and plinth in rocky soil. (Erection)
SOR Item No. 2(b)- Concrete for foundation and cum plinth in other than hard and rock soil.(Supply)
SOR Item No. 2(b)- Concrete for foundation and cum plinth in other than hard and rock soil.(Erection)
SOR Item No. 34(d)- Brick work in foundation cum plinth, retaining walls and drainage.
SOR Item No. 34(i)- Plastering of retaining wall Sqm with 1:4 cement & sand mortar.
SOR Item No. 34(f)(i) - Earth work in excavation cum and filling including compaction In normal soil Total 969160.00 Item- 3 Section -3 (Ferrous) S No. Item Description of Item Unit Qty Rate Amount No
SOR Item No. 3(b)(i)- Supply of fabricated and MT galvanised structures (O,N & R type portals) with all necessary components other than masts.
SOR Item No. 3(b)(i)- Erection of fabricated and MT galvanised structures (O,N & R type portals) with all necessary components other than masts.
SOR Item No. 3(b)(ii)- Supply of Structure steel MT (traction masts) fabricated and galvanised of all Type : B - series Mast. VARANASI DIVISION-ELECTRICAL/NORTH EASTERN RLY
SOR Item No. 3(b)(ii)- Erection of Structure steel MT (traction masts) fabricated and galvanised of all Type : B - series Mast.
SOR Item No. 3(b)(iii)- Supply of special MT fabricated and galvanised steel structures other than Portals & traction- Masts not covered under items 3(b)(i) & 3(b)(ii).
SOR fabricated and galvanised steel structures other than Portals & traction- Masts not covered under items 3(b)(i) & 3(b)(ii).
SOR Item No. 3(c)- Supply only of fabricated MT steel other than masts.
SOR Item No. 3(e)(i)- Supply of a Guy Rod Each assembly.
SOR Item No. 3(e)(i)- Erection of a Guy Rod Each assembly.
SOR Item No. 3 (i)- Supply of 25KV Caution Each board/ Plates.
SOR Item No. 3 (i)- Erection of 25KV Caution Each board/ Plates.
SOR Item No. 4(a)(i)- Supply without Insulator of Each Single bracket assembly.
SOR Item No. 4(a)(i)- Erection with Insulator of Each Single bracket assembly.
SOR Item No. 4(a)(ii)- Extra of 4(a)(i) above, for Each supporting two OHE's.(Supply)
SOR Item No. 4(a)(ii)- Extra of 4(a)(i) above, for Each supporting two OHE's.(Erection)
SOR Item No. 8(a)(v)- Supply of Regulating Each Equipment (3-Pulley type) with counter weight assembly for conventional/ composite OHE.
SOR Item No. 8(a)(v)- Erection of Regulating Each Equipment (3-Pulley type) with counter weight assembly for conventional/composite OHE.
SOR Item No. 8(b)(ii)- Supply without Insulator Each of materials for termination of double conductor.
SOR Item No. 8(b)(ii)- Erection with Insulator of Each materials for termination of double conductor.
SOR Item No.16(a)(i)- Supply of a structure Each bond.
SOR Item No. 16(a)(i)- Erection of a structure Each bond.
SOR Item No. 16(b)- Supply of a longitudinal Each bond.
SOR Item No. 16(b)- Erection of a longitudinal Each bond.
SOR Item No. 16(c)- Supply of a transverse and Each special bond.
SOR Item No. 16(c)- Erection of a transverse Each and special bond.
SOR Item No. 17(a)- Supply of a single earth Each electrode.
SOR Item No. 17(a)- Erection of a single earth Each electrode.
SOR Item No. 30(b)(iii)- Supply of anticlimbing Each device for L.T. Supply Transformer Stations.
SOR Item No. 30(b) (iii)- Erection of anticlimbing Each device for L.T. Supply Transformer Stations.
SOR Item No 32.- Extra on Erection rate of 3(b) MT (i) for work under power block.
SOR Item No. 32. - Extra on Erection rate of 3(b) MT (ii) for work under power block. VARANASI DIVISION-ELECTRICAL/NORTH EASTERN RLY
SOR Item No 32. - Extra on Erection rate of 3(b) MT (iii) for work under power block.
SOR Item No 32. - Extra on Erection rate of 3(e) Each (i) for work under power block.
SOR Item No. 32 - Extra on Erection rate of 4(a) Each (i) for work under power block.
SOR Item No. 32- Extra on Erection rate of 4(a) Each (ii) for work under power block.
SOR Item No. 32 - Extra on Erection rate of 8(a) Each (v) for work under power block.
SOR Item No. 32 - Extra on Erection rate of 8(b) Each (ii) for work under power block.
SOR Item No. 33(b)- Extra on on Erection rate of MT 3(b)(i) for manual steel work.
SOR Item No. 33(b)- Extra on Erection rate of MT 3(b)(ii) for manual steel work.
SOR Item No. 33(b)- Extra on Erection rate of MT 3(b)(iii) for manual steel work. Total 5797237.00 Item- 4 Section -4 (Non- Ferrous) S No. Item Description of Item Unit Qty Rate Amount No
SOR Item No. 5(az)(ii)- Supply of span wire.
SOR Item No. 5(az)(ii)- Erection of span wire.
SOR equipment only.
SOR Item No. equipment only.
SOR Item No. 10(az) - Extra on item 6(a) for Each supply of additional fittings at a turn-out, diamond crossing or overlap.
SOR Item No. 10(az) - Extra on item 6(a) for Each erection of additional fittings at a turn-out, diamond crossing or overlap.
SOR Item No. 12(az)- Supply without insulator Each of a section insulator assembly.
SOR Item No. 12(az)- Erection with insulator of Each a section insulator assembly.
SOR Item No. 13 (a)- Supply without insulator of Each a 25 kv single pole isolator without earth contact assembly
SOR Item No. 13 (a)- Erection with insulator of a Each 25 kv single pole isolator without earth contact assembly.
SOR Item No. 13(d)- Extra for supply of an earth Each contact assembly in an isolator.
SOR Item No. 13(d)- Extra for erection of an Each earth contact assembly in an isolator.
SOR Item No.15(a)(i)- Supply of large copper Each jumper.
SOR Item No.15(a)(i)- Erection of large copper Each jumper.
SOR Item No. 15(a)(ii)- Supply of small copper Each jumper.
SOR Item No.15(a)(ii)- Erection of small copper Each jumper.
SOR Item No. 15(a)(iv)- Supply of a copper Each jumper (5mm dia droper wire).
SOR Item No. 15(a)(iv)- Erection of a copper Each jumper (5mm dia droper wire).
SOR Item No. 15(c)- Supply of insulated Each catenary cable in the span under over-line structures. VARANASI DIVISION-ELECTRICAL/NORTH EASTERN RLY
SOR Item No. 15(c)- Erection of insulated Each catenary cable in the span under over-line structures.
SOR Items No. 15 (e)- Supply of materials Large Each copper jumper 160 Sq. mm between cross feeder and OHE.
SOR Items No.15 (e)- Erection of Large copper Each jumper 160 Sq. mm between cross feeder and OHE.
SOR Items No. 26(a)(ii)- Supply of solid copper Metre bus bar 18 mm
SOR Items No. 26(a)(ii)- Erection of solid copper Metre bus bar 18 mm.
SOR Items No. 26(b)(i)- Supply of Aluminum Each bus-bar connectors:- Bus terminal (6480)
SOR Items No. 26(b)(i)- Erection of Aluminum Each bus-bar connectors:- Bus terminal (6480)
SOR Items No. 26(b)(ii)- Supply of Aluminum Each bus-bar connectors:- Bus splice (6490)
SOR Items No. 26(b)(ii)- Erection of Aluminum Each bus-bar connectors:- Bus splice (6490).
SOR Items No. 26(b)(iii)- Supply of Aluminum Each bus-bar connectors:- Bus tee connector (6500).
SOR Items No. 26(b)(iii)- Erection of Aluminum Each bus-bar connectors:- Bus tee connector (6500).
SOR Items No. 26(b)(iv)- Supply of Aluminum Each bus-bar connectors:- Terminal connector 36/20 (6530).
SOR Items No. 26(b)(iv)- Erection of Aluminum Each bus-bar connectors:- Terminal connector 36/20 (6530)
SOR Items No. 26(b)(v)- Supply of Aluminum Each bus-bar connectors:- Tap connector (6520).
SOR Items No. 26(b)(v)- Erection of Aluminum Each bus-bar connectors:- Tap connector (6520)
SOR Items No. 26(b)(vi)- Supply of Aluminum Each bus-bar connectors:- Flexible bus splice (6550).
SOR Items No. 26(b)(vi)- Erection of Aluminum Each bus-bar connectors:- Flexible bus splice (6550).
SOR Items No. 26(b)(vii)- Supply of Aluminum Each bus-bar connectors:- Terminal connector Bolted Type (6830-1).
SOR Items No. 26(b)(vii)- Erection of Aluminum Each bus-bar connectors:- Terminal connector Bolted Type (6830-1)
SOR Items No. 26(c)(i)- Supply of solid copper Each bus-bar connectors: Bus terminal (6310).
SOR Items No. 26(c)(i)- Erection of solid copper Each bus-bar connectors: Bus terminal (6310).
SOR Items No. 26(c)(ii)- Supply of solid copper Each bus-bar connectors: Bus splice (6320)
SOR Items No. 26(c)(ii)- Erection of solid copper Each bus-bar connectors: Bus splice (6320)
SOR Items No. 26(c)(iii)- Supply of solid copper Each bus-bar connectors: Bus tee joint (6330)
SOR Items No. 26(c)(iii)- Erection of solid Each copper bus-bar connectors: Bus tee joint (6330)
SOR Items No. 26(c)(iv)- Supply of solid copper Each bus-bar connectors: Bus terminating tee (6351).
SOR Items No. 26(c)(iv)- Erection of solid Each copper bus-bar connectors: Bus terminating tee (6351).
SOR Item No. 32- Extra on Erection rate of 5(az) Metre (ii) for work under power block. VARANASI DIVISION-ELECTRICAL/NORTH EASTERN RLY
SOR Item No. 32- Extra on Erection rate of 6(az) Kilometre for work under power block.
SOR Item No. 32- Extra on Erection rate of Each 10(az) for work under power block.
SOR Item No. 32 - Extra on Erection rate of Each 12(az) for work under power block.
SOR Item No. 32- Extra on Erection rate of 13(a) Each for work under power block.
SOR Item No. 32- Extra on Erection rate of 15(a) Each (i) for work under power block.
SOR Item No. 32- Extra on Erection rate of 15(a) Each (ii) for work under power block.
SOR Item No. 32 - Extra on Erection rate of Each 15(e) for work under power block.
SOR Item No. 32- Extra on Erection rate of 26(a) Metre (ii) for work under power block. Total 1109965.00 Item- 5 Section 5 (Insulators) S No. Item Description of Item Unit Qty Rate Amount No
SOR Item No. 4(ax)(i)- Supply of Stay Arm Each Porcelain insulator (CD-1050 mm).
SOR Item No.4(ax)(iv)- Supply of Bracket Arm Each Porcelain insulator (CD-1050 mm).
SOR Item No.5(ax)(i) - Supply of 9-Tonne Set Porcelain insulators (CD-1050 mm)
SOR Item No.8(bx)(i)- Supply of Porcelain insulators (CD-1050 mm).
SOR Item No. 9(ax)(i)- Supply of 9 Tonne Set Porcelain insulator (CD-1050 mm).
SOR Item No.11(ax)(i)- Supply of 9 Tonne Each Porcelain insulator (CD-1050 mm) for 11(a)(i).
SOR Item No.11(bx) - Supply of 25 Kv post Each insulator for item no.11(b)
SOR Item No. 12(ax)(i)- Supply of Porcelain 9- Set Tonne (CD-1050 mm) and Sectioning Insulator for item 12(ax)(i).
SOR Item No.13(ax)- Supply of Post & Operating Set rod insulators for item 13(a).
SOR Item No. 28(x)- Supply of Post insulators Set for item 28. Total 519802.61
Item Breakup - 2-Non-Schedule Items (Not available in SOR)
NS-1-Cutting and removal of released OHE Numbers masts/portals
NS-2-Dismantling of released cantilever.
NS-3-Dismantling of Anti-Creep Anchor/BWA
NS-4-Dismantling modification i.e. Eye rod, three pulley and counter weight etc.
NS-5-Dismantling of small parts steel. VARANASI DIVISION-ELECTRICAL/NORTH EASTERN RLY
NS-6-Construction of traction SWR diagram as Numbers per approved sectioning diagram and ACTM guidelines. The diagram prepared in AUTOCAD and operation rules annexure shall be prepared in Microsoft Word and submitted for approval. After approval, supply 18 set of hard copy of drawing with colouring and operation rules annexure with cover and one tracing, one soft copy in CD shall be submitted. Work shall be done as per scope of work.
NS-7-Fabrication, & supply of traction SWR Numbers diagram boards of size approx 4'x3' or 6'x4' on suitable acrylic/FRP sheets framed in teak wood/metal frame as per approved SWR diagram with colouring as per code of section.
NS-8-Supply & erection of OHE sectioning Numbers diagram board of section.
NS-9-Erection of structure bonds on platform Numbers including drillings of holes including cutting of platform surface upto depth of 100 mm placing of bond and making good surface with PCC.
Square NS-10-Modification in TWR Foot
NS-11-Provision of Painting & Marking of Numbers 2000.00 implantation, emergency phone socket direction, rail level, Km's number of Structures, OHE height and ATD's temperature marking on ATD structures.
NS-12-Provision of painting of balance weight of Numbers 2000.00 ATD by Aluminium paint (Double Coat) (Rate inclusive of required material cost i.e Paint, brush etc.)
NS-13-Provision of Bond painting & dressing Numbers (Rate inclusive of required material cost i.e Paint, brush etc.)
NS-14-Provision of white washing of Muff (Rate Numbers 2000.00 inclusive of required material cost)
NS-15-Supply of 25 KV DO Fuse Link, 1 Amp as Numbers per RDSO spec no. ETI/PSI/14(1/86) Rev 1 (Apr- 87) or Latest.
NS-16- Supply of 25 KV DO Fuse Barrel Numbers assembly only 53 cm long as per RDSO spec no. ETI/PSI/14(1/86) Rev.1 (Apr-87) or latest.
NS-17-Supply Of Executive Table with Executive Numbers Return unit.
NS-18- Supply Of In charge Supervisors Table Numbers with CPU Hanger.
NS-19- Supply Of In charge supervisors - Numbers Revolving chair Mild Black.
NS-20- Supply Of Visitor Chair with Arm.
NS-21- Supply Of Computer Table.
NS-22- Supply Of Steel Almirah/Book Case.
Extra on erection rate for work under power Numbers block NS - 1.
Extra on erection rate for work under power Each block NS - 2.
Extra on erection rate for work under power Each block NS - 3
Extra on erection rate for work under power Each block NS - 4.
Extra on erection rate for work under power MT block NS - 5. Total 1522470.18
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
TenderDocument.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].