| Sl No | Description | Qty | Unit | Mahasamy Sakthivel L1 | SOLAIAPPAN CONSTRUCTIONS L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for Narrow Pipe Line Cutting in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete | 422 | M3 | 77 ₹32,494 Lowest | 78 ₹32,916 |
| 2.00 | Providing and laying ,spreading and compacting graded stone aggregate to wet mix macadam (WMM) soecification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications. | 282 | M3 | 2,150 ₹6,06,300 Lowest | 2,250 ₹6,34,500 |
| 3.00 | Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev V Specifications | 2,812 | M3 | 78 ₹2,19,336 Lowest | 78 ₹2,19,336 Lowest |
| 4.00 | Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM/ surface treated with binder using 2.5 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications | 2,812 | M2 | 18 ₹50,616 | 17 ₹47,804 Lowest |
| 5.00 | Providing and laying tack coat of 2.0 kgs/10 sqm over the B.T surface treated with binder using 2.0 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications | 24,907 | M2 | 26 ₹6,47,582 Lowest | 26 ₹6,47,582 Lowest |
| 6.00 | Patch repairs with bitumen premixed chips and metal upto 50mm thick using 4kg of bitumen as tack coat per 10 sq.m using 2/3 qty. of 37.50mm IRC metal and 1/3 Qty. of 11.20mm chips and premixed chips with 44kgs of bitumen per cum including bitumen mixing laying and tamping etc., including cost of bitumen and cost of metal etc., complete | 142 | M3 | 4,000 ₹5,68,000 Lowest | 4,200 ₹5,96,400 |
| 7.00 | Providing and laying Bituminous Concrete to 30mm thick using 0.13 cum of 19.00 - 9.50mm, 0.17cum of 9.50 -2.36mm and 0.26cum of 2.36 and below with 45.27kgs of VG30 / VG40 bitumen and 5.03Kg of plastic waste (50.30*10%=5.03Kg) for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform | 832 | M3 | 9,700 ₹80,70,400 Lowest | 10,400 ₹86,52,800 |
| 7.01 | thickness of 30mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10tonne Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification. | 422 | M3 | 80 ₹33,760 Lowest | 82 ₹34,604 |
| 8.00Conveyance of excess excavated and surpluse earth to low laying areas upto 5 km lead including loading and unloading charges and all labours charges etc complete | |||||
Tender Value
₹1.3 Cr
EMD Value
₹1.3 L
Closing Date
30 Jun 2023, 3:00 pmClosed
THE COMMISSIONER,ERODE CITY MUNICIPAL CORPORATION
246,MEENAKHISUNDARANAR SALAI,ERODE-638001
RESTORATION OF B.T SURFACE DAMAGED DUE TO URATCHIKOTTAI WATER SUPPLY SCHEME AND UGSS AT PKKS STREET - 2 056060R4670 ,BALADANDAYUDAM STREET 056060R4672 ,MOLAGOUNDANPALAYAM CROSS ROAD - 7 056060R4660 ,LIC NAGAR OPP ROAD 056058R4169 ,DOLLARS C
2023_MAWS_331704_1
E1-0846-2023-5-ERODE CITY MUNICIPAL CORPORATION
Open Tender
Civil Works - Roads
Works
180 days
ERODE CITY MUNICIPAL CORPORATION
Please refer Tender documents.
17 documents required · 17 mandatory
₹0
₹1.3 L
ERODE CITY MUNICIPAL CORPORATION
5 Jul 2023
24 Jun 2023
30 Jun 2023
24 Jun 2023
30 Jun 2023
24 Jun 2023
26 Jun 2023
Amount
Earth work excavation for Narrow Pipe Line Cutting in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete
Providing and laying ,spreading and compacting graded stone aggregate to wet mix macadam (WMM) soecification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications.
Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev V Specifications
Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM/ surface treated with binder using 2.5 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications
Providing and laying tack coat of 2.0 kgs/10 sqm over the B.T surface treated with binder using 2.0 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications
Patch repairs with bitumen premixed chips and metal upto 50mm thick using 4kg of bitumen as tack coat per 10 sq.m using 2/3 qty. of 37.50mm IRC metal and 1/3 Qty. of 11.20mm chips and premixed chips with 44kgs of bitumen per cum including bitumen mixing laying and tamping etc., including cost of bitumen and cost of metal etc., complete
Providing and laying Bituminous Concrete to 30mm thick using 0.13 cum of 19.00 - 9.50mm, 0.17cum of 9.50 -2.36mm and 0.26cum of 2.36 and below with 45.27kgs of VG30 / VG40 bitumen and 5.03Kg of plastic waste (50.30*10%=5.03Kg) for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform
thickness of 30mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10tonne Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification.
Conveyance of excess excavated and surpluse earth to low laying areas upto 5 km lead including loading and unloading charges and all labours charges etc complete
SOLAIAPPAN CONSTRUCTIONS
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.61 MB
BOQ_393567.xls
BOQ • 0.28 MB
CONDITIONS_5.pdf
Additional Documents • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .