| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹136.4 CrAccepted-AOC | ₹136.4 Cr | L1 | Accepted-AOC Accepted |
| Sl No | Description | Qty | Unit | DIPANSHU PROMOTER AND BUILDER PVT LTD L1 |
|---|---|---|---|---|
| 1.00PART-A | ||||
| 2.00Design, Engineering, Procurement and Construction on (EPC) basis with required services and utilities including handing over complete as per scope of work mentioned in Tender Documents (Volume 1 to Volume VI) and directions of Engineer In charge: | ||||
| 2.01 | BUNGALOW FOR PROJECT HEAD | 355.88 | Sqm | 52,000 ₹1.9 Cr |
| 2.02 | HOUSING TYPE 2 | 4,168.43 | Sqm | 34,997.7 ₹14.6 Cr |
| 2.03 | HOUSING TYPE 3 | 6,917.83 | Sqm | 34,382.82 ₹23.8 Cr |
| 2.04 | HOUSING TYPE 4 | 2,634.44 | Sqm | 34,537.15 ₹9.1 Cr |
| 2.05 | COMMUNITY BLOCK | 898.27 | Sqm | 65,000 ₹5.8 Cr |
| 2.06 | CLUB & INDOOR SPORTS BLOCK INCLUDING EQUIPMENT AS PER SCOPE OF WORK | 972.19 | Sqm | 64,000 ₹6.2 Cr |
| 2.07 | MINI SHOPPING COMPLEX | 854.84 | Sqm | 65,000 ₹5.6 Cr |
| 2.08 | DISPENSARY INCLUDING EQUIPMENT AS PER SCOPE OF WORK | 282.86 | Sqm | 66,000 ₹1.9 Cr |
Tender Value
₹132.8 Cr
EMD Value
₹1.4 Cr
Closing Date
13 Oct 2025, 3:00 pmClosed
Vice President IDN
HITES, B-14 A Sec-62, Noida-201307
Establishment of Integrated Township, Administrative Office and other allied Infrastructures works at Pachwara South Open cast Project, NUPPL, Dumka, Jharkhand on Engineering, Procurement and Construction (EPC) Basis.
2025_HITE_248469_1
HITES/IDN/NUPPL/EPC/2025-26
Open Tender
Construction Works
546 days
Dumka Jharkhand
As per Tender Document
19 documents required · 19 mandatory
₹1.2 L
Yes
HITES
₹1.4 Cr
HITES Office, Noida
17 Dec 2025
12 Sept 2025
14 Oct 2025
12 Sept 2025
13 Oct 2025
22 Sept 2025
19 Sept 2025
Amount
PART-A
Design, Engineering, Procurement and Construction on (EPC) basis with required services and utilities including handing over complete as per scope of work mentioned in Tender Documents (Volume 1 to Volume VI) and directions of Engineer In charge:
BUNGALOW FOR PROJECT HEAD
HOUSING TYPE 2
HOUSING TYPE 3
HOUSING TYPE 4
COMMUNITY BLOCK
CLUB & INDOOR SPORTS BLOCK INCLUDING EQUIPMENT AS PER SCOPE OF WORK
MINI SHOPPING COMPLEX
DISPENSARY INCLUDING EQUIPMENT AS PER SCOPE OF WORK
GUEST HOUSE CUM HOSTEL
SCHOOL
SERVICE BLOCK
ADMINISTRATION BLOCK
TEMPLE
GUARD ROOMS/SECURITY CABINS
Designing, and Construction on EPC Basis of DEVELOPMENT WORKS–CIVIL : STP/WTP System with Pipe Lines, Bore Well, Underground tanks, Pathways, Parking Landscaping , Internal Roads & Storm Water Drainage System, Rain Water Harvesting, External Water Supply Network, External Sewer System & Boundary Wall Including Main Gate, etc. with support services & allied facilities by incorporating stipulated specifications, all services including handing over complete as per scope of work and directions of Engineer In charge.
Internal Roads, Footpath/Pathways/Roundabouts complete including sub base, kerb stones, joints, Painting etc. complete as per scope of works and directions of Engineer In charge.
Open Path ways / Building approach /drop off including sub-base, kerb stone etc. complete as per scope of works and directions of Engineer In charge.
Open/ Surface Parking including subgrade Kerb Stone etc. complete as per scope of works and directions of Engineer In charge.
Boundary Wall with Entrance Gates complete as per scope of works and directions of Engineer In charge.
Water-Supply System complete as per scope of works and directions of Engineer In charge.
Sewerage System complete as per scope of works and directions of Engineer In charge.
Storm Water Drainage System complete as per scope of works and directions of Engineer In charge.
External Street Lighting System including Cables, Panel etc. complete as per scope of works and directions of Engineer In charge.
Landscaping, Horticulture, Rain water Harvesting System & Irrigation System complete as per scope of works and directions of Engineer In charge.
Children Play Area with Equipment & Fencing etc. complete as per scope of works and directions of Engineer In charge.
Water Treatment Plant complete as per scope of works and directions of Engineer In charge.
Under Ground RCC Tanks complete and other related accessories etc. complete as per scope of works and directions of Engineer In charge.
Sewerage Treatment Plant complete as per scope of works and directions of Engineer In charge.
Designing and Construction on EPC Basis of INFRASTRUCTURE & EXTERNAL DEVELOPMENT – Electrical Works with support services & allied facilities by incorporating stipulated specifications, all services including handing over complete as per scope of work and directions of Engineer In charge.
DG Sets (500- KVA -2NOs) complete with all accessories complete as per scope of works and directions of Engineer In charge.
Transformers 1000 KVA-2Nos complete with all accessories complete as per scope of works and directions of Engineer In charge.
HT Panels, LT Panels, Capacitor Panels and sandwich Bus Ducts complete as per scope of works and directions of Engineer In charge.
HT & LT Cabling work complete as per scope of works and directions of Engineer In charge.
Designing, and Construction on EPC Basis of INFRASTRUCTURE & EXTERNAL DEVELOPMENT – Firefighting System with support services & allied facilities by incorporating stipulated specifications, all services including handing over complete as per scope of work and directions of Engineer In charge.
Fire Fighting System inside fire pump room comprising of Fire Pumps, piping, valves, vessels and accessories etc. including external hydrant ring main system, FHC, fire brigade inlet/ drawout connection etc.complete as per scope of works and directions of Engineer In charge.
Furniture
Designing, and Supply & Installation on EPC Basis of FURNITURE as per stipulated specifications, complete in all respect including handing over complete as per scope of work and directions of Engineer In charge.
PART-B
Providing Operation, Comprehensive Maintenance & Annual Maintenance upto the end of defect liability period for Part-A including deputing the maintenance and operational staff of required experience and trades, complete as per scope of work and directions of Engineer In charge.
Operation, Comprehensive Maintenance & Annual Maintenance for DLP Period of 24 months to be started after the overall completion of project recorded by Engineer-in-charge and obtaining all statutory clearances.
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 0.91 MB
VOL1NIB.pdf
Tender Documents • 0.90 MB
VOL2GCC.pdf
Tender Documents • 1.97 MB
BOQ_284707.xls
BOQ • 0.28 MB
VOL3SCC.pdf
Tender Documents • 1.79 MB
VOL4DBR.pdf
Tender Documents • 9.28 MB
VOL5TECHSPECS.pdf
Tender Documents • 6.11 MB
Download all tender documents and submit your bid