| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹43,837Admitted-Finance | ₹43,837 | L1 | Admitted-Finance |
| 2 | L2₹45,884.30Admitted-Finance | ₹45,884.30 | L2 | Admitted-Finance |
| 3 | L3₹47,990.60Admitted-Finance | ₹47,990.60 | L3 | Admitted-Finance |
| Sl No | Description | Qty | Unit | KHAN ENTERPRISES L1 | M/s Lucky Enterprises L2 | SYED TANZEEL L3 |
|---|---|---|---|---|---|---|
| 1.00Safe carriage of following materials from Store centre or any other place to the respective site of work through the Kachha/Pacca road including loading, unloading at the respective ends and erection of same including the work of dragging as per site requirement, jumphering of Transformer with 11 KV line through LT ABC cable, Weasal conductor etc. Cost of labour, T&P carrier etc. required for proper completion of work as per RESPO Norms is included in the work. | ||||||
| 1.01 | 09Mtr. STP Pole | 25 | No | - | - | - |
| 1.02 | 11Mtr. STP Pole | 143 | No | - | - | - |
| 1.03 | 11 KV D.O. Fuse Set | 4 | No | - | - | - |
| 1.04 | 11 KV Fuse Set | 3 | No | - | - | - |
| 1.05 | 11KV TPMO Complete | 12 | No | - | - | - |
| 1.06 | Stay Set Complete | 28 | No | - | - | - |
| 1.07 | 11 KV Pin Insulator with Pin | 408 | No | - | - | - |
| 1.08 | 11 KV Disc Insulator with Fitting 45KN | 72 | No | - | - | - |
| 1.09 | 11 KV Disc Insulator | 42 | No | - | - | - |
Tender Value
₹27 L
EMD Value
₹35,000
Closing Date
4 Feb 2026, 10:00 amClosed
SE
EUDC ALIGARH
SHIFTING OF 11KV AND LT LINE from Kotwali to Aligarh City boundary against sanctioned package No. 02 under Deposit Head for Aligarh-Ramghat Road widening MDR-105 ON SEMI TURNKEY BASIS
2026_DVVNL_1109223_1
EUDCA-47/2025-26
Open Tender
Electrical Works
90 days
EUTD-II
Please refer Tender documents.
2 documents required · 2 mandatory
₹3,540
DVVNL
₹35,000
26 Feb 2026
25 Jan 2026
4 Feb 2026
25 Jan 2026
4 Feb 2026
25 Jan 2026
Safe carriage of following materials from Store centre or any other place to the respective site of work through the Kachha/Pacca road including loading, unloading at the respective ends and erection of same including the work of dragging as per site requirement, jumphering of Transformer with 11 KV line through LT ABC cable, Weasal conductor etc. Cost of labour, T&P carrier etc. required for proper completion of work as per RESPO Norms is included in the work.
09Mtr. STP Pole
11Mtr. STP Pole
11 KV D.O. Fuse Set
11 KV Fuse Set
11KV TPMO Complete
Stay Set Complete
11 KV Pin Insulator with Pin
11 KV Disc Insulator with Fitting 45KN
11 KV Disc Insulator
11 KV Disc Fitting
V- Type Cross Arm
Earthing Complete
L.T. PVC Alu. Cable 3.5x240sq.mm.
L.T. PVC Alu. Cable 3.5x70sq.mm.
L.T. XLPE Alu. Cable 3.5x150sq.mm.
L.T. A.B. Cable 3x120sq.mm.
ACSR Dog Conductor
Distribution Box with clamps
Supply, fixing and erection of following materials as per site requirement as per RESPO Norms:-
Top Channel size 125x65x2240 mm. with Clamp, Nut, Bolt & Washers
Dropper Channel size 100x50x2028 mm. with Clamp, Nut, Bolt & Washers
M.S. Angle (T/F Base)
Cross Bracing MS Angle
L.T. Incoming Panel with metering equipment & fixing arrangements
Barbed wire
Stone Pad 300x300x75mm.
Holding clamp with nut & bolt
PG Clamp with nut & bolt
Danger Board with Clamp, Nut & Bolt
Number Plate with Clamp, Nut & Bolt
F-Clamp
Al. Winding wire
Alluminium Paint
Red Oxide Paint
Al. Lug long barrel off-size
ABC Connector 3x120sq.mm.
Dead End Clamp with I-hook
Suspension Clamp with I-hook
Concreting of Stay
Concreting of Support
After dismentling of 25 KVA & 63 KVA Distribution Transformer from old site, safe carriage to the respective site of work including loading & unloading at the respective ends and mounting/placement on double pole/plinth including proper jumpering from 11 KV line to the transformer and also connecting the LT site cables as per RESSPO Manual.
After dismentling of 100 KVA & above Distribution Transformer from old site, safe carriage to the respective site of work including loading & unloading at the respective ends and mounting/placement on double pole/plinth including proper jumpering from 11 KV line to the transformer and also connecting the LT site cables as per RESSPO Manual.
Earthing for Distibution Transformer installed at various places by digging of pit upto water level depth and then inserting 1-¼” dia GI pipe of ‘A’ grade, conforming to the requirement of IS specification and then connecting the top of the inserted pipe and transformer body through GI strip of size 40x6 mm with the help of nut and bolt or through gas welding, as per direction of supervising engineer. It includes the cost of all material labour, T&P, carrier etc. required for proper completion of work. The aforesaid work shall be carried out as per RESSPO norms.
Dismantling and removal of following material from the existing line and then stacking in the respective JE’s (Store) as per direction of Supervising Engineer. It includes the work of cartage, cost of labour, T&P carrier etc. required for proper completion of work.
Dismentling of old & used ST Pole
Dismentling of Iron Scrap
Dismentling of Damaged Dog & Weasel Conductor
Dismentling of Damaged L.T. AB Cable
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.23 MB
EUDCA_47_2025-26.rar
Tender Documents • 8.53 MB
BOQ_2048267.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid