| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | I₹75.3 LAccepted-AOC | ₹75.3 L | I | Accepted-AOC Due to Technical Evaluation |
| 2 | II₹75.7 LRejected-Finance | ₹75.7 L | II | Rejected-Finance Due to Technical Evaluation |
| 3 | Rejected-Technical | - | - | Rejected-Technical Not Responsive |
Tender Value
₹76.1 L
EMD Value
₹1.5 L
Closing Date
2 Apr 2026, 5:00 pmClosed
EXECUTIVE ENGINEER,N.R.E.PGODDA
IST FLOOR RDSPL DIVISION ,OFFICE, GODDA, N.R.E.P GODDA
Construction of Boundary wall IN GOVT HS BHATKHORIYA UNDER BLOCK THAKURGANGTI District Godda
2026_NRGOD_111828_1
N.R.E.P,Godda/13/2025-26
Open Tender
Civil Works
Percentage
180 days
GODDA
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
Yes
₹1.5 L
Yes
16 Sept 2026
19 Mar 2026
4 Apr 2026
19 Mar 2026
2 Apr 2026
19 Mar 2026
19 Mar 2026 - 2 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in excavation in foundation trenches in ordinary soil (vide classfication of soil item - A) and disposal of excavated earth a obtained to a distance up to 50M including all lifts with leveling ramming the foundation trenches removing roots of trees shurbs all complete as per approved design and per building specification and direction of E/I. | 278.6 | CUM | 151.82 | ₹42,296.44 |
| 2 | Earth filling in foundation trenches and plinth in layer not exceeding 150mm thick will watered rammed fully compacted and fine dressed with earth obtained from excavation of foundation trenched with a lead of 50mm and lift of 1.5M all complete as per building specification and direction of E/I. (Mode of measurement compacted volume). | 185.73 | CUM | 55.28 | ₹10,267.21 |
| 3 | Providing coarse clean sand in filling in foundation trenches or in plinth including thick with all leads and watering in layers not exceeding 150mm thick with all leads and lifts including cost of all materials, labour, royalty and taxes all complete as per building specifi cation and direction of E/I. (Mode of measurement compacted voume) | 27.31 | CUM | 589.51 | ₹16,097.75 |
| 4 | Providing designation 75B one brick flat soiling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/I | 358.44 | SQM | 330.34 | ₹1,18,407.73 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 Cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 40 mm nominal size) | 16.39 | CUM | 4,503.43 | ₹73,820.22 |
| 6 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size TPS S.Col (3'6"+1'4")/2 x ( 3'6"+1'9")/2 xH, J.Col (3'6"+2'3")/2 x (3'6"+1'9")/2 x H, G.Col (3'6"+1'9")/2 x (3'6"+1'9")/2 | 123.93 | CUM | 5,218 | ₹6,46,687.61 |
| 7 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size | 40.29 | CUM | 6,082.45 | ₹2,45,037.58 |
| 8 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). | 32.55 | CUM | 6,308.87 | ₹2,05,341.1 |
| 9 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete | 436.28 | SQM | 194.5 | ₹84,856.46 |
| 10 | Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts | 2,309.69 | SQM | 465.38 | ₹10,74,883.07 |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.03 MB
TenderDocument.pdf
Tender Documents • 6.86 MB
BOQ_150982.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .