Tender Value
Refer Docs
EMD Value
₹57.5 L
Closing Date
27 Aug 2026, 3:00 pm
Yes (up to 5 members)
Two Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
90 days
Expenditure
Capital Works)
24 conditions · 9 needing a document upload
Financial Eligibility Criteria - The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure - VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet. (Page-21, Para 10.2, Part-I of GCC April 2022). Attached Performa as per Annexure VIB - in Tender Document).
Electrical Contractors License: The contractor or the sub-contractor appointed by him must have valid Electrical Contractors License issued by any State Government in their own name or in the name of the firm, as per IE Rule 1956 clause No. 45 or as amended from time to time. A copy of the license shall be uploaded along with the tender offer failing which the offer shall be summarily rejected.The license must be valid as on the date of opening of the tender. If the Electrical Contractors License has expired as on the date of opening of tender, the license renewal documents must be uploaded along with the copy of the license.The contractor or the sub- contractor appointed by him shall possess valid Electrical Contractor License throughout the currency of the contract. The contractor shall ensure timely renewal of license.
License for escalators erection, service/ maintenance, if required/obligatory by any State Government. (Maharashtra, Gujrat)
Similar Nature Work - "Supply, erection/ installation, testing and commissioning of escalator OR Construction of buildings / FOBs in Railways / Metro Railways / Airports / Central/State Government building or PSU Establishment. If the tenderer is not an escalators manufacturer or authorised dealer of escalator manufacturer, he shall enter into a MoU with escalator manufacturer for the supply, erection, warranty & maintenance etc. of the required escalator and submit a copy of MoU along with his offer. MoU should be signed on a non-judicial stamp paper of minimum 500/- duly notarised and should be legally enforceable." Format of the Memorandum Of Understanding (MOU) between the Tenderer/ Contractor and an OEM of the Escalator/ Escalator manufacturer is enclosed herewith. Non submission of MOU will lead to summarily rejection of the offer.
If the tenderer is not an approved escalators manufacturer or authorized dealer of an approved escalator manufacturer, the bidder shall enter into a MoU with a suitable approved escalator manufacturer for the supply, erection, warranty, etc. of the required escalators and submit a copy of the MoU along with his offer. The MoU should be signed on a non-judicial stamp paper duly notarized and should be legally enforceable. The provision of Comprehensive AMC of escalators has to be carried out byOriginal Equipment Manufacturer (OEM). Assurance of OEM for 05 years CAMC has to be taken in written by tenderer and has to be enclosed by him along with his tender offer. OEM has to support the contractor during the defect liability warranty period of 02 years as well, and accepting the responsibilities to depute their engineers to rectify the escalator at site in the event of any odd situation arising during the maintenance of the installed escalator. Format of the Memorandum Of Understanding (MOU)between the Tenderer/ Contractor and an OEM of the Escalator/ Escalator manufacturer is enclosed herewith. Non submission of MOU will lead to summarily rejection of the offer.
27 conditions · 9 needing a document upload
1) The tenderer shall be required to submit the Bid Security with the tender for the due performance with the stipulation to keep the offer open till such date as specified in the tender, under the conditions of tender. 2) The Bid Security shall be deposited either in cash through e-payment gateway or submitted as Bank Guarantee bond from a scheduled commercial bank of India or as mentioned in tender documents. The Bank Guarantee bond shall be as per Annexure- VIA and shall be valid for a period of 90 days beyond the bid validity period. (3) In case, submission of Bid Security in the form of Bank Guarantee,following shall be ensured: i. A scanned copy of the Bank Guarantee shall be uploaded on e-Procurement Portal (IREPS) while applying to the tender. ii. The original Bank Guarantee should be delivered in person to the official nominated as indicated in the tender document before closing date for submission of bids (i.e. excluding the last date of submission of bids). (ACS-11 Dated 13.03.2026). iii. Non submission of scanned copy of Bank Guarantee with the bid on e-tendering portal (IREPS) and/or non-submission of original Bank Guarantee within thespecified period shall lead to summary rejection of bid. iv. The Tender Security shall remain valid for a period of 90 days beyond the validity period for the Tender. v. The details of the BG, physically submitted should match with the details available in the scanned copy and the data entered during bid submission time, failing which the bid will be rejected. vi. The Bank Guarantee shall be placed in an envelope, which shall be sealed. The envelope shall clearly bear the identification "Bid for the ***** Project" and shall clearly indicate the name and address of the Bidder. In addition, the Bid Due Date should be indicated on the right hand top corner of the envelope. vii. The envelope shallbe addressed to the officer and address as mentioned in the tender document.viii. If the envelope is not sealed and marked as instructed above, the Railway assumes no responsibility for the misplacement or premature opening of the contents of the Bid submitted and consequent losses, if any, suffered by the Bidder. (As per Clause 5, Page -4,5,6 Part I GCC April 2022 with ACS-2 Dated 13.12.2022)
Subject to exemptions provided under para 5(1) (a) of Part-1 (ITT) of GCC April 2022, the tender must be accompanied by a Bid Security as mentioned in tender documents, failing which the tender shall be summarily rejected. (Clause 6 (a) Annex -I, Page-11, Part-I of GCC April 2022)
Note: i) Any firm recognized by Department of Industrial Policy and Promotion (DIPP as 'Startups' shall be exempted from payment of Bid Security subject to submission of Registration Certificate issued by appropriate authority. ii) Labour Cooperative Societies shall submit only 50% of Bid Security shall also additionally submit Registration Certificate. (As per Clause 5 , Page-5, Part-I of GCC April 2022)
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
If a tender is accepted on the quoted rates of bidder which is below the advertised tender value, an additional performance security shall be submitted by the bidder as below: (Railway Board Letter No. 2022/CE-I/CT/GCC-2022/POLICY/Pt.I (E-3320424) New Delhi, Dated 13.03.2026). Bid quoted Below 0 - 5% (inclusive) of advertised cost - Additional Performance Guarantee Nil. Bid quoted Below 5% of advertised cost - Additional Performance Guarantee - 5%
Tenderer Credentials: Documents testifying tenderer previous experience and financial status should be produced along with the tender. (Clause 11, Page-16-17, Part-I of GCC April 2022)
(i) Certificates and testimonials regarding contracting experience for the type of job for which tender is invited with list of works carried out in the past.
(ii) Audited Balance Sheet duly certified by the Chartered Accountant regarding contractual payments received in the past. The documentary proof whether the Balance sheets of each year are audited or not must be submitted. Audited Balance sheet with UDIN shall be submitted to established authenticity of the submitted documents.
(iii) The list of personnel / organization on hand and proposed to be engaged for the tendered work.
List of Plant & Machinery available on hand and proposed to be inducted and hired for the tendered work.
(iv) A copy of certificate stating that they are not liable to be disqualified and all their statements / documents submitted along with bid are true and factual. Standard format of the certificate to be submitted by the bidder is enclosed as Annexure-V. Non submission of a copy of certificate by the bidder shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent upon the tenderer to identify, state and submit the supporting documents duly self-attested / digitally signed by which they/he are/is qualifying the Qualifying Criteria mentioned in the Tender Document.
(v) The Railway reserves the right to verify all statements, information and documents submitted by the bidder in his tender offer, and the bidder shall, when so required by the Railway, make available all such information, evidence and documents as may be necessary for such verification. Any such verification or lack of such verification, by the Railway shall not relieve the bidder of its obligations or liabilities hereunder nor will it affect any rights of the Railway there under.
(vi) (a) In case of any information submitted by tenderer is found to be false, forged or incorrect at any time during process for evaluation of tenders, it shall lead to forfeiture of the tender Bid Security besides banning of business for a period of upto two years. (b) In case of any information submitted by tenderer is found to be false, forged or incorrect after the award of contract, the contract shall be terminated. Bid Security, Performance Guarantee and Security Deposit available with the railway shall be forfeited. In addition, other dues of the contractor, if any, under this contract shall be forfeited and agency shall be banned for doing business for a period of upto two years.
Non-compliance with any of the conditions set forth therein above is liable to result in the tender being rejected.
This tender complies with Public Procurement Policy (Make in India) Order, 2017 - Revision dated 16/09/2020, issued by Department of Industrial Promotion and Policy, Ministry of Commerce, circulated vide Railway Board letter no. 2020/RS(G)/779/2/Pt.1 dated 25/09/2020 and amendments / revisions thereof." The full details of the order can be seen at http://dipp.nic.in/whats-new/publicprocurement- preference-make-india-order- 2017. (Authority Railway Boards L. No. 2020/RS(G)/779/2/Pt.1 dated 25-09- 2020)
Contractor is to abide by the provisions of various labour laws in terms of above clause 54, 55, 55-A and 55-B of the Standard General Conditions of Contract. In order to ensure the same, an application has been developed and hosted on website ''www.shramikkalyan.indianrailways.gov.in'. Contractor shall register his firm/ company etc. and upload requisite details of labour and their payment in this portal. These details shall be available in public domain. (Page- 86-89, Part-II of GCC-April 2022)
Mumbai Division (Suburban Section) - Provision of Escalators (18 Nos) at Lower Parel (1), Prabhadevi (1), Santacruz (2), Vile Parle (1), Andheri (3), Jogeshwari (1), Borivali (2), Dahisar (1), Vasai Terminal (4) and Vasai Road (2). (Composite tender for Electrical and Civil work)
EL-166-170-WA-46
EL-166-170-WA-46
Open
Works - General
24 Months
Mumbai, Maharashtra
₹0
₹57.5 L
31 Jul 2026
31 Jul 2026
13 Aug 2026
57 items across 11 schedules · ₹19,65,94,868.7 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| EARTH WORK | — | — | — | — | |
| General | — | — | — | — | |
| Earth work by mechanical / manual means in rough excavation, banking excavated earth in layers not exceeding 20cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up embankments for roads, flood banks, marginal banks and guide banks or filling up ground depressions, lead upto 50 m and for lift. | or in all | — | — | — | |
| 1 | All kinds of soil | cum | 2880 | 395.3 | 11,38,464 |
| Schedule total | ₹11,38,464 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GCC-April-2022.pdf
ATTACHMENT
BankGuaranteeFormat.pdf
ATTACHMENT
AnnexureVclarificationforonlinesubmissiondated14.05.2024.pdf
ATTACHMENT
2026_03_13IndianRailwaysStandardGeneralConditionsofContractApril2022AdvanceCorrectionSlipNo_111.pdf
ATTACHMENT
AnnexureVIBAnnualContractualTurnoverGCC2022.pdf
ATTACHMENT
InsuranceSuretyBondforPerformanceSecurity.pdf
ATTACHMENT
SinageGuidelines_11zon.pdf
ATTACHMENT
NoRelativeFormatEmployeeofWesternRailway-Annexure-II.pdf
ATTACHMENT
NORETIREDRAILWAYEMPLOYEEGCC2022-Annexure-III.pdf
ATTACHMENT
ESCALATORCoveringCanopydrawingbyEnggDept.pdf
ATTACHMENT
JPOforinvitingCompositetendersforLiftsandEscalatorsHQletterdtd16-04-2024.pdf
ATTACHMENT
MOUbetweentheEscalatorContractorandtheOEM-Format.pdf
ATTACHMENT
RDSOEscalatorSpecification16-01-2026.pdf
ATTACHMENT
Barricade-Drwing.pdf
ATTACHMENT
SpecialTechnicalconditions_1.pdf
ATTACHMENT
EL-166-170-WA-462026-2027.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].