| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.0 CrAccepted-AOC ASSAM AS | ₹10.0 Cr | L1 | Accepted-AOC awarded |
| 2 | L2₹10.2 Cr+₹17.9 L (1.79%)Rejected-AOC | ₹10.2 Cr+₹17.9 L (1.79%) | L2 | Rejected-AOC r |
Tender Value
₹10 Cr
EMD Value
₹20 L
Closing Date
5 Feb 2020, 2:00 pmClosed
Chief Engineer, PWD (Roads), Assam
O/o the Chief Engineer, PWD (Roads), Assam, Chandmari, Guwahati, 781003
SOPD_SIG_19_20_89 Improvement and strengthening of Daodhara Hatijan to Doomni road (Khanda Road) under Signature Project of SOPD-G (State Priority Scheme) for the year 2019-20, Chapaguri LAC
2020_PWD_15864_89
CE/DEV/TB/199/2019-20/01
Open Tender
Civil Works
Item Rate
270 days
Chapaguri
Please refer Tender documents.
6 documents required · 6 mandatory
₹10,000
Empowered Officer, ASRB A/C No. 10566991479
₹20 L
Yes
O/o the Chief Engineer, PWD (Roads), Assam
31 Mar 2021
18 Jan 2020
5 Feb 2020
18 Jan 2020
5 Feb 2020
18 Jan 2020
18 Jan 2020 - 1 Feb 2020
18 Jan 2020
Amount
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300mm dia, removal of stumps of trees cut earlier and disposal of serviceable materials to be used or auctioned, upto 1000m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specifications Clause 201. ,(I) By Mannual Means B. In area of thorny jungle
Scarifying existing bituminous surface to a depth of 50 mm by mechanicalmeans (Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres
Dressing & profiling the existing WBM/Granular surface layer of the road from edge to edge of the existing carriage way, filling low spots and ravelled stretches by providing additional materials of same type as that of the existing top surface layer, cambering, watering, rolling with 8-10 tonne roller to obtain specified compaction, etc to obtain a uniform formation surface with cross fall from the road centre line to the outer edges of the existing embankment. Works to be carried out in accordance with MORT&H specifivation section 300 and as directed by the deptt. (rate considered as per SOR for road bridge and culvert works for all divisions inder PWD Assam 2009-10, at sections where the top level of the subgrade of the existing road surface is not proposed to be raised by more than 100mm.
Dismantelling of structure ( Dismantalling of existing structure like culverts, bridges, retaining wallsand other structure comprising of massonary,cement concrete ,wood works, steel works including T&P and scaffolding wherever necessary,sorting the dismantling,disposable of unserviceable material and stacking thr serviceable materials with all lift and lead of 1000 m
Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirment of table 300-2 ( including compensation of earth.)( Including cost of testing of materials at site and laboratory as directed by the deptt.) (a) From private land
Construction of Subgrade and Earthen shoulders with approved materials obtained from borrowpits, with all leads and lifts, transporting to site, spreading, grading to required slope and compacting to meet requirement of Table 300-2 (including land compensation of earth) as per drawing and Technical Specifications Clause 305. As per Annexure I
Excavation in Soil by Manual Means. (a)(Excavation for roadway in soil using manual means including loading in truck for carrying of cut earth to embankment site with all lifts and lead upto1000 metres.)
Granular Sub Base in paves shoulder with Coarse Graded Material (Table 400-2) ( Construction of granular sub base by providing coarse raded material, spreading in uniform layer with motorgrader on prepared surface, mixing by mix in place method with rotovator at OMC and co,acting with vibratory roller to achieve the desired density, complete as per cl. 401. Including extra lead beyond 5.00 km for carriage of materials from quarry to middle of the road. (ii) for grading II Material
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sb-base/base course on well prepared surface and compacting with vibratory roller to achieve the desired density ( Including extra lead beyond 5.00 km for carriage of materials from quarry toplant site and exrtra lead beyond 10.00Km from Plant site to Laying site.)
Prime coat Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 1.00 kg/sqm using mechanical means.)( Including cost of testing of materials at site and laboratory as directed by the deptt.) A. with bitumen emalsion-CSS- 1h
Tack Coat :- Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20kg per sqm on the prepared bituminous/ grannula surface cleaned with mechanical broom ( Including cost of testing of materials at site and laboratory as directed by the Deptt.) ii) With bitumen emulsion- CSS-1 (IS- 8887-2004 ) (b) dry & hungry bituminous surface
Dense Graded Bituminous Macadam (Providing and laying Dense Graded bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixedwith bituminous binder transporting to site ,laid over a primix (including carriage of mixed materials up to 10.0 km initial lead from mixing plant) ( including cost of testing of materials at site and laboratory as directed by the deptt.) (a)'with VG-30 grade bitumen (ii) for grading-I ) (40 mm nominal size) As per Annexure I
Bituminious concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous [email protected] to 5 % of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel andalignment, rollingwith smooth wheeled,vibratoryand tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.508. complete in all respect. ( Including carriage of mixed upto 10.0 km initial lead from mixing plant) (including cost of testing of materials at site and leboratory as directed by the deptt,) (a)'with 60/70 or VG-30 grade bitumen (ii) for grading-II )13mm nominal size)
Retro reflectorised Traffic sign: Providing and erecting of Retro-Reflectrorised cautionary, mandatory & informatory sign as per IRC: 67 made of high intensity encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick fixed on an angle iron of 25x25x4mm supported on a mild steel angle iron post 75mm x 75mm x 6mm firmly fixed to the ground by means of properly design foundation with M-15 grade Cement concrete 45cm x 45cm x 60cm, 60cm below ground level as per approved drawing and sign. ( All the Steel work must be Tata/Sail/or any other approved brand),(i) 60cm equilateral traingle
Retro reflectorised Traffic sign: Providing and erecting of Retro-Reflectrorised cautionary, mandatory & informatory sign as per IRC: 67 made of high intensity encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick fixed on an angle iron of 25x25x4mm supported on a mild steel angle iron post 75mm x 75mm x 6mm firmly fixed to the ground by means of properly design foundation with M-15 grade Cement concrete 45cm x 45cm x 60cm, 60cm below ground level as per approved drawing and sign. ( All the Steel work must be Tata/Sail/or any other approved brand(ii) 60cm circular
Providing reflective pavement marker with a provision of spike at the bottom with Micro prismatic lens in both direction having thermoplastic body adhering to the specification and guidelines of MoSRTH & H's fixed to the road surface using the adhesives and the procedures recommended by the manufacturers with three months replacement warranty and free maintenance.
Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes.
Planting of Trees and their Maintenance for one Year (Planting of trees by the road side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge mannure, planting the saplings, backfilling the trenches, watering , fixing the tree guatrd and maintaining the plants for one year.
(Earth work in excavation of foundation of structures as per drawing and technical specification, includingsetting out, construction of shoring and bracing, removal of stumpsand other deleterious matter, dressing of sides and bottom andbackfilling with approved material.
(Construction of granular sub-base by providingclose graded Material, mixing in a mechanical mix plant at OMC,carriage of mixed Material to work site, spreading in uniform layerswith motor grader on prepared surface and compacting withvibratory power roller to achieve the desired density,completeas percl. 401( Including cost of testing ofmaterials at site and laboratory as directed by the deptt.)
Foundation(Plain cement concrete 1:3:6 nominalmixin open foundation with crushed stone aggregate 40 mm nominal sizemechanically mixed, placed in foundation and compacted byvibration including curing for 14 days.), with plasticiser, PCC M-15
Plain/Reinforcedcement concrete, in sub structure complete as perdrawing and technical specification and steel shuttering formwork, WITH PLASTISER,RCCM20 Grade, Ht. upto 5.00 m
Supplying, fitting and placing TMT bar reinforcement in substructurecomplete as per drawing and technical specifications
Backfilling behind apartment wing wall and return wall complete as per drawing complete
Providing and laying Cement concrete wearing coat M-30 gradeincluding reinforcement complete as per drawing and Technical Specifications
Providing and laying boulders apron on river bed for protectionagainst scour with stone boulders weighing not less than 40 kg each complete as per drawing and Technical specification
Construction of embankment with approved material obtainedfrom borrow pits with all lifts and leads, transporting to site,spreading, grading to required slope and compacting to meet requirment of table 300-2( Including cost of testing of materials at site and laboratory as directed by the deptt.)
Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC,and compacting with vibratory roller to achieve the desired density,complete as per cl. 401( with an initial lead of 5 Km.)
Labour for laying Reinforced cement concrete pipe NP4/NP3/prestressed concrete pipe for culverts on first class bedding of granular material /cc M-15 in single row including fixingcollar with cement mortar 1:2,and cost of granular bedding but excluding excavation, protection works, backfilling, concrete andmasonry work in head wall and parapet,cost of pipe and cost of CC bedding. (I) With 1st class
(Culvert : 3.00 mx3.00 m)(Earth work in excavation of foundation of structures as per drawing and technical specification, includingsetting out, construction of shoring and bracing, removal of stumpsand other deleterious matter, dressing of sides and bottom andbackfilling with approved material.
(Construction of granular sub-base by providingclose graded Material, mixing in a mechanical mix plant at OMC,carriage of mixed Material to work site, spreading in uniform layerswith motor grader on prepared surface and compacting withvibratory power roller to achieve the desired density,completeas percl. 401( Including cost of testing ofmaterials at site and laboratory as directed by the deptt.)
Foundation(Plain cement concrete 1:3:6 nominalmixin foundation with crushed stone aggregate 40 mm nominal sizemechanically mixed, placed in foundation and compacted byvibration including curing for 14 days.)
Plain/Reinforcedcement concrete, in sub structure complete as perdrawing and technical specification and steel shuttering formwork
Supplying, fitting and placing TMT bar reinforcement in substructurecomplete as per drawing and technical specifications
Backfilling behind apartment wing wall and return wall complete as per drawing complete
Cont. of RCC Railing of M-30 gradeincluding reinforcement complete as per drawing and Technical Specifications
Providing and laying cement concrete wearing coat M-30 GRADE INCL. REINFORCEMENT omplete as per drawing and Technical specification
Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not less than 40 kg each complete as per drawing and Technical specification
Construction of embankment with approved material obtainedfrom borrow pits with all lifts and leads, transporting to site,spreading, grading to required slope and compacting to meet requirment of table 300-2( Including cost of testing of materials at site and laboratory as directed by the deptt.)
Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC,and compacting with vibratory roller to achieve the desired density,complete as per cl. 401( with an initial lead of 5 Km.)
Labour for laying Reinforced cement concrete pipe NP4/NP3/prestressed concrete pipe for culverts on first class bedding of granular material /cc M-15 in single row including fixingcollar with cement mortar 1:2,and cost of granular bedding but excluding excavation, protection works, backfilling, concrete andmasonry work in head wall and parapet,cost of pipe and cost of CC bedding. (I) With 1st class
H.P.Culvert:- (Earth work in excavation of foundation of structures as per drawing and technical specification, includingsetting out, construction of shoring and bracing, removal of stumpsand other deleterious matter, dressing of sides and bottom andbackfilling with approved material.
Foundation(Plain cement concrete 1:3:6 nominalmix in open foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Bedding for pipe:Laying concrete cradle bedding with M-15 Grade cement concrete as per clause 1105(i)
Plain/Reinforcedcement concrete, in sub structure complete as per drawing and technical specification and steel shuttering formwork
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical specifications
Cost of Hume pipe 1000mm dia
Labour for laying Reinforced cement concrete pipe NP4/NP3/prestressed concrete pipe for culverts on first class bedding of granular material /cc M-15 in single row including fixingcollar with cement mortar 1:2,and cost of granular bedding but excluding excavation, protection works, backfilling, concrete andmasonry work in head wall and parapet,cost of pipe and cost of CC bedding. (I) With 1st class
kamalchgoyary
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .