| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.1 LAccepted-AOC | L1 | Accepted-AOC Accepted | |
| 2 | L2₹7.5 L+₹37,435.74 (5.26%)Rejected-Finance SHOP NO 5 WARD NO 12 132041 | KARNAL | KARNAL | HARYANA | 132041 | L2 | Rejected-Finance Reject | |
| 3 | L3₹7.7 L+₹62,190.23 (8.73%)Rejected-Finance S O PREM KUMAR SUNDER NAGAR 132117 | KARNAL | HARYANA | 132117 | L3 | Rejected-Finance Reject | |
| 4 | L4₹7.9 L+₹78,345.79 (11.0%)Rejected-Finance 949 GALI NO 9A NEW KARNAL ROAD AMARGARH GAMRI KAITHAL 136027 | KAITHAL | HARYANA | 136027 | L4 | Rejected-Finance Reject | |
| 5 | L5₹8.4 L+₹1.3 L (18.1%)Rejected-Finance NIL | L5 | Rejected-Finance Reject |
Tender Value
₹8.7 L
EMD Value
₹16,000
Closing Date
14 Jan 2026, 5:00 pmClosed
Raj Kumar
Municipal Committee Taraori
Construction and repairing of street and drain from Tower in Sadhu vihar ward no.13MC TARAORI
2026_HRY_495144_1
2026D6E647A0 3099 4E42 B8CE A0D1C4918603310ULB
Open Tender
Civil Works
Works
90 days
Taraori
Construction and repairing of street and drain from Tower in Sadhu vihar ward no.13MC TARAORI
2 documents required · 2 mandatory
₹1,000
₹16,000
Yes
6 Feb 2026
7 Jan 2026
15 Jan 2026
7 Jan 2026
14 Jan 2026
7 Jan 2026
7 Jan 2026 - 9 Jan 2026
[17.13]Granular Sub-Base (Mix in place) Construction of granular sub-base by providing Material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per technical clause 401 of MORT&H technical specifications [Through Rate]
[17.69.2]Interlocking Concrete Block Pavement 2. Providing and Laying 80 mm thick ISI marked Interlocking Paver Blocks conforming to IS 15658:2006/IRC SP 63: 2004 of all shapes and colours in design mix cement M 40 over the bed of 30 mm thick fine sand complete in all respect. [Through Rate]
[17.70]Removal of existing IPB by manual means and disposal of dismantled material with all lead and lift as per technical specification clause 202.3. [Through Rate]
[17.71]Relaying of available (removed and stacked) Interlocking Paver Block Pavement having thickness 100mm/80 mm/ 60 mm (average = 80mm) as per drawings and Technical Specification Clause 1504 [Through Rate]
[21.53]Constructing standard drain type I drain moulded and laid over lime concrete foundation rendered and finished smooth with 6 mm thick rendering concrete to be of 1.3.6 parts by volume of cement sand stone bajri and rendering to be 1:1 cement sand mortar [Through Rate]
[3.1.1]By Mechanical Transport including loading, unloading and stacking 1. Lime, moorum, building rubbish [5km]
[5.23.2]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) [Through Rate]
[6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.33.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more [Through Rate]
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.73 MB
BOQ_573606.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .