| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAccepted-AOC KARUR | ₹1.2 Cr | L1 | Accepted-AOC Admitted |
| 2 | L2₹1.2 Cr+₹2,768.27 (0.02%)Rejected-AOC | ₹1.2 Cr+₹2,768.27 (0.02%) | L2 | Rejected-AOC Rejected |
Tender Value
₹1.2 Cr
EMD Value
₹1.3 L
Closing Date
16 May 2023, 3:00 pmClosed
Addl. Collector (Dev.) / Project Director DRDA
DRDA Krishnagiri
Krishnagiri DT Bargur Block Under MGSMT 2022-2023 strengthening of the 4 Roads Package No TN 04 KRI 11
2023_RDTN_300843_1
RocNo_1433_2023_R3_06_04_23
Open Tender
Civil Works - Roads
Item Rate
180 days
Bargur
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹1.3 L
DRDA Krishnagiri
3 Jul 2023
11 Apr 2023
16 May 2023
11 Apr 2023
16 May 2023
11 Apr 2023
10 May 2023
Amount
1. Strengthening of the Road from Madhepalli PUM School to NH 46 (via) Sanitary Complex Km 0/0-0/470 (R 178) Rs. 12.98Lakhs (Using plastic waste)
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking Existing BT Surface 5cm to 10 Cm Deep Surface and Sectioning including all charges etc., complete
Providing and Laying Gravel to 100mm Compacted thick including cost & conveyance of Gravel From Approved sources to work site including labour for Spreading, watering and comp-acting by power roller to achieve the required proctor density at 100 % compaction.
Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for TOP LAYER
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying Premix Carpet with Seal Coat Type -A to 20mm thick using 0.18cum of 13.2mm, 0.09 cum of 11.20mm and .09cum of 6.70mm with 23.232 Kgs of VG 30 Bitumen for premixing per 10sqm including cost and conveyance of all materials to site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in Central Hot Mix Plant 20-30T capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 20mm with mechanical paver to the specified grades and cross section and consolidated by 8-10T vibratory/pneumatic roller to the required density etc., including labour for attending to paver to site, hire & fuel charges for 20-30T CMP with bitumen boiler, tipper trucks, paver finisher, vibratory/pneumatic roller and all other tools and plants required, including fuel and other incidental charges etc., complete .(using plastic Waste)
Road Marking with hot applied thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface
Provision of 15 nos. rumble strips covered with premium bituminous carpet, 15-20mm high at centre at approved locations to control speed, marked with white strips of road marking paint
Provision for HM Stone
Provision for Name Board cum Citizen Information Board
Provision forEquilateral triangle cautionary Sign Board
Provision forGaurd stones
MAINTANANCE
For 1st year maintenance
For 2nd year maintenance
For 3rd year maintenance
For 4th year maintenance
For 5th year maintenance
2.Strengthening ofT the Road From Krishnagiri - Kandhikuppam Road to Belavarthy Gunttur Km 0/0-1/280 (R 33) Rs. 39.89 Lakhs
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking Existing BT Surface 5cm to 10 Cm Deep Surface and Sectioning including all charges etc., complete
Providing and Laying Gravel to 100mm Compacted thick including cost & conveyance of Gravel From Approved sources to work site including labour for Spreading, watering and comp-acting by power roller to achieve the required proctor density at 100 % compaction.
Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for TOP LAYER
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
BITUMINOUS CONCRETE 25MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Road Marking with hot applied thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface
Construction of Retaining Wall From Ch 873 to 913 Mt
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete.
Construction of Well Prodection From Ch 913 to 933 Mt
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete.
Provision of 15 nos. rumble strips covered with premium bituminous carpet, 15-20mm high at centre at approved locations to control speed, marked with white strips of road marking paint
Provision for HM Stone
Provision for KM Stone
Provision for Name Board cum Citizen Information Board
Provision for 60cm Equilateral Triangle cautionary sign Board
MAINTANANCE
For 1st year maintenance
For 2nd year maintenance
For 3rd year maintenance
For 4th year maintenance
For 5th year maintenance
3.Strengthening ofT the Road From NH 46 to Pulikuttai Km 0/0-1/230 H/o Orappam (R 399) Rs. 38.28 Lakhs
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
collection and supply of carted earth from approved quarry an average lead 1km including cost and conveyance of all materials to site anf labour charges etc.
Picking Existing BT Surface 5cm to 10 Cm Deep Surface and Sectioning including all charges etc., complete
Providing and Laying Gravel to 100mm Compacted thick including cost & conveyance of Gravel From Approved sources to work site including labour for Spreading, watering and comp-acting by power roller to achieve the required proctor density at 100 % compaction.
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and laying 75mm compacted thick WBM Grade II using 1 cum of 75mm to 22.4mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for BOTTOM LAYER
Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for TOP LAYER
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
BITUMINOUS CONCRETE 25 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Road Marking with hot applied thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface
Provision of 15 nos. rumble strips covered with premium bituminous carpet, 15-20mm high at centre at approved locations to control speed, marked with white strips of road marking paint
Providing Hard Bed From 790 to 827
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse an
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete.
Provision for HM Stone
Provision for KM Stone
Provision for Name Board cum Citizen Information Board
Provision for 60cm Equilateral triangle cautionary Sign Board
MAINTANANCE
For 1st year maintenance
For 2nd year maintenance
For 3rd year maintenance
For 4th year maintenance
For 5th year maintenance
4.Strengthening of the Road from Krishnagiri-Ranipet Road to Melkottai Km 0/0-1/05 H/o Oppathavadi (R 196) Rs. 33.62 Lakhs
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking Existing BT Surface 5cm to 10 Cm Deep Surface and Sectioning including all charges etc., complete
Providing and Laying Gravel to 100mm Compacted thick including cost & conveyance of Gravel From Approved sources to work site including labour for Spreading, watering and comp-acting by power roller to achieve the required proctor density at 100 % compaction.
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and laying 75mm compacted thick WBM Grade II using 1 cum of 75mm to 22.4mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for BOTTOM LAYER
Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for TOP LAYER
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
BITUMINOUS CONCRETE 25 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Road Marking with hot applied thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface
Provision of 15 nos. rumble strips covered with premium bituminous carpet, 15-20mm high at centre at approved locations to control speed, marked with white strips of road marking paint
Construction of Retaining Wall Ch 470-500M
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete.
Provision for HM Stone
Provision for KM Stone
Provision for Name Board cum Citizen Information Board
MAINTANANCE
For 1st year maintenance
For 2nd year maintenance
For 3rd year maintenance
For 4th year maintenance
For 5th year maintenance
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
K Sundaramoorthy
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .