Tender Value
₹2.7 Cr
EMD Value
₹1.5 L
Closing Date
23 Aug 2023, 11:00 amClosed
executive officer
arulmigu ekambaranathar temple kanchipuram
conservation works in third and fourth praharam thirumadhil
2023_HRCE_348141_1
7809/2023/G1
Open Tender
Civil Works - Others
Lump-sum
360 days
arulmigu ekambaranathar temple premises
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹1.5 L
Yes
17 Nov 2023
24 Jul 2023
23 Aug 2023
24 Jul 2023
23 Aug 2023
24 Jul 2023
Amount
Dismantling clearing away and carefully stacking materials useful for reuse for any thickness of walls. Brick work in cement mortar
Earth work open excavation in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the excavated earth with a lead of 10 mts. within the compound in places shown by the departmental officers and clearing and levelling the site, etc., complete complying with standard specification.
Supplying and filling in foundation, basement, etc with filling crushed stone sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers.
Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and curing etc. complete complying with standard specification
Providing Two legged Scaffolding using 15cm Dia blue Gum post or Best quality Bamboo / casurina post of 4m overall length (3m ht + 0.5m Projection + 0.50m into the Ground) the Distance between the Two rows being 1.25m and the spacing of post being 2m in both the rows with two horizontal posts with 0.5m . overlap on either side and braces at 2m.c/c including logitudinal and transverse middle braces to step up and providing a platform with country wood planks of 40mm thick and 1m width etc,in a complete form using coir and nails.
Removing the stone walls, stone columns, stone beams and stone slabs from Third and Fourth Thirumadhil and stocking it for refixing including cost and conveyance labour, handling and etc., all complete. a)Stone wall
Removing the stone walls, stone columns, stone beams and stone slabs from Third and Fourth Thirumadhil and stocking it for refixing including cost and conveyance labour, handling and etc., all complete.b)Stone beam and columns
Cleaning the stone surfaces by water washing including cost of tools and plants,scaffolding and labour charges etc,
Brick work in Lime Mortar 1:2 (one part of lime and two part of sand) using special bricks of size 8" x 4" x 2" including curing, etc., complete complying with standard specifiction. ground floor super structure
Brick work in following Lime Mortar 1:2 (one part of lime and two part of sand) using best quality of country bricks of size 8-3/4" x 4-1/4" x 2-3/4" for foundation and basement including curing, etc., complete complying with standard specifiction.
Refixing the stone walls, pillars, uthiram and roof slab including labour charges for fixing, handling and pointing with in lime mortar 1:1.5(one part of lime and one point five part of sand) etc., all complete
Pointing the Cut stone masonry work with Lime mortar 1:1.5 (one part of lime and one and half part of sand), including all labour charges, scaffolding etc complete with standard specifications.
Supplying & fixing Teak wood temple type door including all materials, labour charges for manufacturing and fixing in position including all furniture fittings etc complete with std. Specifications
Supplying and fixing mild steel grill Gate including cost conveyance of all materials etc complete with standard specification.
Plastering with Lime Mortar 1:1.5(one part of lime and one and half part of sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers
Plastering with Lime Mortar 1:1.5 (One part of lime and one and half part of sand), 20mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Painting new wood work with two coats of synthetic enamel paint of approved quality and colour over one coat of priming coat in all floors including the cost of primer etc., complete complying with standard specification.
Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with two coats of best approved first quality and colour of synthetic enamel paint over one coat of zinc chromite yellow primer in all floorsetc., complete complying with standard specification.
Painting two coats of newly plastered wall surface with water based emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification.
Flooring with SS flooring stone slab of size 600mmX600mm and other sizes suitable for site requirement not less than 100mm thick with machine cut edges and top surface dressed as directed by the departmental officers including cost and conveyance of materials to site and labour charges for paving and Pointing with lime mortar 1:2 (one lime and two sand) etc complete.
Sub Total
SHRI ABHIRAMI CONSTRUCTION
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_414918.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .