| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAdmitted-Finance | ₹1.1 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.2 Cr+₹12.5 L (11.2%)Admitted-Finance | ₹1.2 Cr+₹12.5 L (11.2%) | L2 | Admitted-Finance |
| 3 | L3₹1.3 Cr+₹14.5 L (13.0%)Admitted-Finance | ₹1.3 Cr+₹14.5 L (13.0%) | L3 | Admitted-Finance |
| Sl No | Description | Qty | Unit | TUSHAR TRANSFORMERS L2 | SHRI SAI SARTHAK TRADERS L3 | M/S SUPER ENGINEERING TRADERS L1 |
|---|---|---|---|---|---|---|
| 1.01 | Shifting, dragging and stacking of damaged T/fs to be repaired in the workshop at proper place in cutting yard & pre-checking/ physical inspection, testing of transformer before dismantling i.e. Megger Test (if OK) then HV Test (if OK) then No-Load & Load Losses Tests as per instructions of Junior Engineer in charge.
(i) 10/16 KVA | 50 | No. | 5,000 ₹5,900 | 3,050 ₹3,599 | 2,985 ₹3,522.3 Lowest |
| 1.02 | (ii) 25 KVA | 2,500 | No. | 3,25,000 ₹3,83,500 | 1,90,000 ₹2,24,200 Lowest | 1,90,875 ₹2,25,232.5 |
| 1.03 | (iii) 63 KVA | 1,200 | No. | 1,62,000 ₹1,91,160 | 88,800 ₹1,04,784 Lowest | 1,00,032 ₹1,18,038 |
| 1.04 | (iv) 100 KVA | 1,200 | No. | 1,68,000 ₹1,98,240 | 93,600 ₹1,10,448 Lowest | 1,00,476 ₹1,18,561.2 |
| 1.05 | (v) 160 KVA | 15 | No. | 3,750 ₹4,425 | 2,955 ₹3,486.9 | 2,306.85 ₹2,722.08 Lowest |
| 1.06 | (vi) 250 KVA | 150 | No. | 1,21,500 ₹1,43,370 | 60,300 ₹71,154 | 49,660.5 ₹58,599.45 Lowest |
| 1.07 | (vii) 400 KVA | 80 | No. | 76,000 ₹89,680 | 49,600 ₹58,528 Lowest | 78,492.8 ₹92,621.52 |
| 1.08 | (viii) 630/1000 KVA | 6 | No. | 5,700 ₹6,726 | 2,940 ₹3,469.2 Lowest | 5,794.92 ₹6,838.01 |
| 2.01 | Cutting of sealed T/fs top cover/ opening of nut and bolt of damaged t/f cover plate, de- tanking of core coil assembly dismantling of HV&LV Coils and other accessories, draining of T/f oil in sump well and weighing of scraps and shifting of all scrap to the store of JE in charge.
(i) 10/16 KVA | 50 | No. | 5,000 ₹5,900 | 4,050 ₹4,779 | 2,585 ₹3,050.3 Lowest |
| 2.02 | (ii) 25 KVA | 2,500 | No. | 3,25,000 ₹3,83,500 | 3,55,000 ₹4,18,900 | 1,48,375 ₹1,75,082.5 Lowest |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
2 Jul 2024, 2:00 pmClosed
Superintending Engineer
Superintending Engineer, EWC, PVVNL Meerut
Repairing of Dameged Transformers Capacity 10-1000 KVA at Ghunna Saharanpur Workshop
2024_PVVNL_927181_1
E-Tender No. 01/EWC-MRT/2024-25
Open Tender
Electrical Works
Item Rate
365 days
Ghunna Sharanpur
As Per Tender Document
3 documents required · 3 mandatory
₹5,900
Executive Engineer, Electricity Workshop Division,
₹1.1 L
Yes
23 Jul 2024
10 Jun 2024
2 Jul 2024
10 Jun 2024
2 Jul 2024
10 Jun 2024
Shifting, dragging and stacking of damaged T/fs to be repaired in the workshop at proper place in cutting yard & pre-checking/ physical inspection, testing of transformer before dismantling i.e. Megger Test (if OK) then HV Test (if OK) then No-Load & Load Losses Tests as per instructions of Junior Engineer in charge. (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Cutting of sealed T/fs top cover/ opening of nut and bolt of damaged t/f cover plate, de- tanking of core coil assembly dismantling of HV&LV Coils and other accessories, draining of T/f oil in sump well and weighing of scraps and shifting of all scrap to the store of JE in charge. (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Dismantling of core stamping and its cleaning of dust and dirt. (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Assembly of core coils and fitting of other accessories requiring replacement such as press board support spacers and tapping etc. and also cutting of insulation required for coil assembly. (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Dragging of T/f Tank to washing Zone its cleaning by jet pump and washing by caustic soda shifting to open space for drying Providing primer of red oxide on the inner and outer side of tank and painting inner side of T/fs including core channel and tie rod / core rods with heat proof zinc chromate paint and out side with two coats of synthetic grey enamel paint. The paint should be of Asian/Nerolec/Burger/ Dulux/British make only. Writing of PUC/ Unique No. of transformer readable paint color with the help of stencils design. (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Making of new HV coil from new wire / strip as per design of respective T/F (Complete Job) (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Making of new LV coil from new wire / strip as per design of respective T/F (Complete Job) (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Complete the core and coil assembly(CCA) by fitting HV & LV coils required insulating material and shifting it to oven for de-moisture (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Tanking of the complete core and coil assembly (CCA) in to the painted tank safely, filling of reclaimed / centrifuged/ fresh oil fitting of all accessories. (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Welding/ Tightening of nut and bolts of top cover of repaired T/f by electric welding filling Gap etc. properly including denting of tank if necessary and welding of MS plate 100x50x3 mm thick on the out side of the T/Fs contain unique no., capacity, name of the workshop etc. at proper place . (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
Dragging the Repaired T/f to the testing zone for final testing with necessary record and after testing it should be re dragged / stacked at despatch area. (i) 10/16 KVA
(ii) 25 KVA
(iii) 63 KVA
(iv) 100 KVA
(vi) 250 KVA
(vii) 400 KVA
(viii) 630/1000 KVA
General Cleaning of T&P / Machinery and stacking of material at suitable place
General clearness of store testing room, workshop floor, oven area, generator room, in cutting area, tanking area, assembly area, painting area by wiping, booming and wooden dust properly to keep floor clean by engaging proper man power for cleaning works. As required for cleaning works
TUSHAR TRANSFORMERS
SHRI SAI SARTHAK TRADERS
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.47 MB
Tenderdoc01.pdf
Tender Documents • 0.73 MB
BOQ_1601157.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .