Tender Value
₹1.3 Cr
EMD Value
₹2.7 L
Closing Date
22 Sept 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
Above/Below/Par
WORKS
16 conditions · 4 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or V whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet. As detailed in Para 10.2 of Tender Form (Second sheet) of Part 1 of attached GCC-2022.
The tenderer shall submit certificates regarding status of firm i.e. sole proprietorship, partnership, Company, Society/Trust etc. and should submit supporting documents e.g. notarized affidavit, MOA/AOA, Certificate of Incorporation, Partnership deed, power of attorney etc. (as applicable) to comply Para no. 10, 14, 15, 16 & 18 of Tender Form (Second Sheet) of Part I of attached GCC-2022.
The contractor should have a valid Electrical contractor license issued by Govt. and submit along with tender documents. If tenderer fails to submit a valid electrical contractor license, then offer from the tenderer will be summarily rejected.
14 conditions
Tender document and all the uploaded supporting documents must be digitally signed by the authorized signatory for tender, in token of their acceptance.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
OHE work in c/w proposed extension of L-4 as common long loop at ARNA yard in BKI-JP Section of Jaipur Division.
EL-TRD-JP-2026-27-02~NWR
EL-TRD-JP-2026-27-02
Open
Works - General
12 Months
Jaipur, Rajasthan
₹0
₹2.7 L
22 Sept 2026
31 Aug 2026
8 Sept 2026
94 items across 1 schedule
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 1,32,98,251.72 | ||
| — | 2.00 | — | — | ||
| Preparation of design and drawing for Overhead Equipment and verification and modification in plan. Inspection by : Consignee Inspection charge : None | — | — | — | 40,290.62 | |
| — | 1.00 | — | — | ||
| Preparation and supply of TSWR as per approved sectioning diagram and latest ACTM guidelines. Inspection by : Consignee Inspection charge : None | — | — | — | 10,467.71 | |
| — | 60.00 | — | — | ||
| Fabrication and provision of traction SWR diagram boards of size as per specifications on suitable acrylic FRP sheets framed in teak wood/ metal frame as per approved SWR diagram with colouring as per code of section. Inspection by : Consignee Inspection charge : None | — | — | — | 52,279.8 | |
| — | 5.00 | — | — | ||
| Supply of danger / caution boards Supply of caution boards, unwired turnout boards, engine stop boards, sigma boards etc. and other all similar type of boards. Inspection by : Consignee Inspection charge : None | — | — | — | 9,439.6 | |
| — | 5.00 | — | — | ||
| Erection of danger / caution boards Supply of caution boards, unwired turnout boards, engine stop boards, sigma boards etc. and other all similar type of boards. Inspection by : Consignee Inspection charge : None | — | — | — | 1,057.25 | |
| — | 44.00 | — | — | ||
| Supply of Retro Reflective number plates.Inspection by : ConsigneeInspection charge : None | — | — | — | 55,375.76 | |
| — | 44.00 | — | — | ||
| Erection of Retro Reflective number plates.Inspection by : ConsigneeInspection charge : None | — | — | — | 2,946.24 | |
| — | 204.00 | — | — | ||
| Concrete for foundation and plinth in all typeof soil incl. hard soil and rockInspection by : ConsigneeInspection charge : None | — | — | — | 16,37,958.84 | |
| — | 33.00 | — | — | ||
| Supply of rolled or fabricated and galvanizedsteel for traction mast, TTC, Portals (boom &uprights), AT masts, feeder mast, super-masts,bridge masts, steel gantries, supportingstructures, Drop arm, SPS etcInspection by : RITESInspection charge : Borne by Railway | — | — | — | 42,61,710.75 | |
| — | 33.00 | — | — | ||
| Erection, testing & commissioning of rolled orfabricated and galvanized steel for traction mast, TTC, Portals (boom & uprights), ATmasts, feeder mast, super-masts, bridge masts,steel gantries, supporting structures, Droparm, SPS etcInspection by : ConsigneeInspection charge : None | — | — | — | 3,24,770.82 | |
| — | 12.00 | — | — | ||
| Supply of material for complete Guy rodassembly as per latest RDSO drg., spec &explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 1,38,084.36 | |
| — | 12.00 | — | — | ||
| Erection, testing & commissioning of materialfor complete Guy rod assembly as per latestRDSO drg., spec & explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 20,270.4 | |
| — | 100.00 | — | — | ||
| Supply of material for complete Singlebracket assembly including ST, BT Insulatorsas per latest RDSO drg., spec & explanatorynotesInspection by: Consignee/RITES based on POvalue. Inspection Charges: Borne by Railwayfor RITES & None for Consignee. | — | — | — | 31,81,945 | |
| — | 100.00 | — | — | ||
| Erection, testing & commissioning of materialfor complete Single bracket assemblyincluding ST, BT Insulators as per latest RDSOdrg., spec & explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 2,40,642 | |
| — | 10.00 | — | — | ||
| Supply of material for complete regulatedequipment (3 pulley type) with counterweight assembly for Regulated OHE tension asper latest RDSO drg., spec & explanatory notes.Inspection by: Consignee/RITES based on POvalue. Inspection Charges: Borne by Railwayfor RITES & None for Consignee. | — | — | — | 7,84,777.9 | |
| — | 10.00 | — | — | ||
| Erection, testing & commissioning of materialfor complete regulated equipment (3 pulleytype) with counter weight assembly forRegulated OHE tension as per latest RDSO drg.,spec & explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 70,723.1 | |
| — | 10.00 | — | — | ||
| Supply of material for complete terminationof Single/ Double conductor of overheadequipment with 9-ton insulators as per latestRDSO drg., spec & explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 1,87,115.4 | |
| — | 10.00 | — | — | ||
| Erection, testing & commissioning of materialfor complete termination of Single/ Doubleconductor of overhead equipment with 9-toninsulators as per latest RDSO drg., spec &explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 27,070.3 | |
| — | 150.00 | — | — | ||
| Supply of material of traction bonds as perlatest RDSO drg., spec & explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 1,55,166 | |
| — | 150.00 | — | — | ||
| Erection, testing & commissioning of materialof traction bonds as per latest RDSO drg., spec& explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 23,316 | |
| — | 2.00 | — | — | ||
| Supply of material for complete anti creepwith galvanized steel wire including cut- ininsulators and complete termination as perlatest RDSO drg., spec & explanatory notes.Inspection by : ConsigneeInspection charge : None | — | — | — | 1,10,648.24 | |
| — | 2.00 | — | — | ||
| Erection, testing & commissioning of materialfor complete anti creep with galvanized steelwire including cut-in insulators and completetermination as per latest RDSO drg., spec &explanatory notes.Inspection by : ConsigneeInspection charge : None | — | — | — | 9,222.58 | |
| — | 2.00 | — | — | ||
| Supply of material for overhead equipmentwith complete fitting. (Without supply ofContact & catenary wire)Inspection by : ConsigneeInspection charge : None | — | — | — | 1,20,671.58 | |
| — | 2.00 | — | — | ||
| Erection, testing & commissioning of materialfor overhead equipment with complete fitting.(With Contact & catenary wire)Inspection by : ConsigneeInspection charge : None | — | — | — | 1,13,363.14 | |
| Each Span | 70.00 | — | — | ||
| Supply of material for New dropper and readjustmentof dropperInspection by: Consignee/RITES based on POvalue. Inspection Charges: Borne by Railwayfor RITES & None for Consignee. | — | — | — | 3,01,693 | |
| Each Span | 70.00 | — | — | ||
| Erection, testing & commissioning of materialfor New dropper and re-adjustment of dropperInspection by : ConsigneeInspection charge : None | — | — | — | 37,731.4 | |
| — | 50.00 | — | — | ||
| Supply of material ConsigneeInspection charge : None | — | — | — | 98,191 | |
| — | — | — | 18mm.Inspection | ||
| — | 50.00 | — | — | ||
| Erection, testing & commissioning of materialfor solid copper bus bar 18 mmInspection by : ConsigneeInspection charge : None | — | — | — | 8,203.5 | |
| — | 12.00 | — | — | ||
| Supply of material for solid copper bus barconnectors & Bus terminalInspection by : ConsigneeInspection charge : None | — | — | — | 49,842.84 | |
| — | 12.00 | — | — | ||
| Erection, testing & commissioning of materialfor solid copper bus bar connectors & BusterminalInspection by : ConsigneeInspection charge : None | — | — | — | 739.68 | |
| — | 3.00 | — | — | ||
| Supply of material complete for sectioninsulator assembly as per latest RDSO drg.,spec & explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 2,61,019.2 | |
| — | 3.00 | — | — | ||
| Erection, testing & commissioning of materialcomplete for section insulator assembly asper latest RDSO drg., spec & explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 14,234.55 | |
| — | 2.00 | — | — | ||
| Supply of material complete for single poleisolator without earth assembly with postinsulators as per latest RDSO drg., spec &explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 1,84,125.58 | |
| — | 2.00 | — | — | ||
| Erection, testing & commissioning of materialcomplete for single pole isolator withoutearth assembly with post insulators as perlatest RDSO drg., spec & explanatory notesInspection by : ConsigneeInspection charge : None | — | — | — | 9,355.64 | |
| — | 5.00 | — | — | ||
| Supply of material complete for solid core cutin insulatorInspection by : ConsigneeInspection charge : None | — | — | — | 56,558.6 | |
| — | 5.00 | — | — | ||
| Erection, testing & commissioning of materialcomplete for solid core cut in insulatorInspection by : ConsigneeInspection charge : None | — | — | — | 4,511.3 | |
| — | 1.00 | — | — | ||
| Dismantling of existing complete anti-creepassemblies with anti-creep wire, insulators,adjusters etc. and transportation to TRD DepotInspection by : ConsigneeInspection charge : None | — | — | — | 2,013.63 | |
| — | 34.00 | — | — | ||
| Dismantling of existing cantilever assemblyInspection by : ConsigneeInspection charge : None | — | — | — | 50,977.9 | |
| — | 5.00 | — | — | ||
| Dismantling of ATD (Regulating equipment)with counter weights.Inspection by : ConsigneeInspection charge : None | — | — | — | 38,948.25 | |
| — | 6.00 | — | — | ||
| Dismantling of guy rod with termination.Inspection by : ConsigneeInspection charge : None | — | — | — | 7,585.86 | |
| — | 2.00 | — | — | ||
| Dismantling of Portal, fabricated steel otherthan Mast/UprightInspection by : ConsigneeInspection charge : None | — | — | — | 19,974.36 | |
| — | 21.00 | — | — | ||
| Dismantling of Mast / Upright by gas cuttingInspection by : ConsigneeInspection charge : None | — | — | — | 28,518.63 | |
| — | 1.00 | — | — | ||
| Dismantling & removal of isolator completeInspection by : ConsigneeInspection charge : None | — | — | — | 3,850.76 | |
| — | 10.00 | — | — | ||
| Transportation chargesInspection by : ConsigneeInspection charge : None | — | — | — | 67,276.1 | |
| — | 21.00 | — | — | ||
| Breaking of FoundationInspection by : ConsigneeInspection charge : None | — | — | — | 67,098.57 | |
| for details. | Breakup | — | — | ||
| Power Block Charges - As per Annexure-A | — | — | — | 4,06,487.98 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GCC_April-2022.pdf
ATTACHMENT
CorrectionSlipsupto11-GCCApr2022.pdf
ATTACHMENT
CorrectionSlipNo-12_.pdf
ATTACHMENT
Special Condition of Contract
ATTACHMENT
2026-04-24SpecialconditionofcontractARNAlongloop.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .