| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹10.7 LAccepted-AOC | 1 | Accepted-AOC lowest tender | |
| 2 | 2₹12.0 L+₹1.3 L (11.8%)Rejected-Finance | 2 | Rejected-Finance 2ND LOWEST | |
| 3 | 3₹12.5 L+₹1.7 L (16.2%)Rejected-Finance | 3 | Rejected-Finance 3RD LOWEST | |
| 4 | Not Admitted-Fee/PreQual/Technical 02 ASPUR DEVSARA NEAR BAJRANG BALI KA MANDIR DAUDPUR PATTI ROAD VILLAGE TOWN DHAURAHARA CITY PATTI PRATAPGARH UTTAR PRADESH 230124 INDIA | PRATAPGARH | UTTAR PRADESH | 230124 | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹12.9 L
EMD Value
₹25,900
Closing Date
9 Oct 2023, 12:00 pmClosed
EE,FWD,PRAYAGRAJ
EE,FWD,PRAYAGRAJ
Construction and Dismantling of 03 Nos Temporary Jetty(10x5)M at Andawa pond Jushi for Durga Murti Visarjan 2023
2023_UPIDC_844618_1
01/EE/2023-24
Open Tender
Civil Works
Item Wise
15 days
ANDAWA, JHUNSHI
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹25,900
Yes
2 Dec 2023
29 Sept 2023
9 Oct 2023
29 Sept 2023
9 Oct 2023
29 Sept 2023
Amount
Earth work in scraping of side slope of pond in all type of soil including all lead & lift etc complete
Supplying ,stacking & spreading of local Ganga sand on approches and platforms as per site requirment and as per direction of engineer-in-charge.
Earth work in slope cutting and for making stairs for approach to jetty with its disposal as per direction of Engineer-in-charge in all types of soil including all leads and lifts, labour and T&P etc.
Providing beldar for removing and proper disposal of sevar including cost of all material, labour, T&P etc. required for proper completion of works all complete as per direction of Engineer-in-charge
Making Balli Khuntas on 125mm (5") dia ballies for piling with all labour and T&P etc. required for proper completion of work as per direction of Engineer-in-charge but excluding cost of ballies.
Balli piling with 125mm (5") dia ballies in grid as per drawing including cost of all material, labour, T&P etc. required for proper completion of works all complete as per direction of Engineer-in-charge but excluding cost of ballies.
Bracing on driven piles with 100mm (4") dia, ballies along and across in rectangular grid with 6" long Mallahi nails of good quality and fixing wooden planks of size 2.00 M. ´ 0.25 M. size, 5 cm. thick over bracing to make platform for Jetty using 4" long good quality Mallahi nails including cost of all material, labour and T&P etc. required for proper completion of work all complete as per direction of Engineer-in-charge but excluding cost of ballies and planks.
Barricading with 100mm-120mm dia balli in two rows including cost of all materials and tying arrangement with all labour T&P. etc. required for proper completion of work as per direction of Engg-in- charge but excluding cost of ballies.
Supplying and filling plastic E.C. bags with local Ganga sand and stacking, placing in position for making stair ,laying over LDEP film etc and at other places with all leads lifts including cost of materials, labour and T&P etc. as per direction of Engineer-in-charge.
Painting two coat of approved superior quality ready mixed synthetic enamel paint on old painted surface on125 mm (5’’) dia balli ,khunta vertical in barricading including cost of all materials and tying arrangement with all labour T&P. etc. required for proper completion of works per R.M.
Painting two coat of approved superior quality ready mixed synthetic enamel paint on old painted surface on100 mm (4") dia balli ,khunta vertical in barricading including cost of all materials and tying arrangement with all labour T&P. etc. required for proper completion of works per R.M.
Providing Beldar for watching of jetty and supervision of constructed J.T. during Durga Murti Viserjan.
Providing Carpentor for watching and Supervision of J.T. during the Durga Murti Visarjan.
Providing boatman with boat for watching balli piling etc. and removal of residue from pond during Durga Murti Visarjan.
Carriage of Stock material from Beni Bundh store to working place and back to store after dismantling.
Making arrangement for removal of residue from the pond after Durga murti visarjan.
Debaricading of ballies 100mm- 120mm in two rows and stacking including all labour T&P etc. as per direciton of Engineer-in-charge.
Deplainking and Debracing in dismantling of jetty and stacking for proper completion of work as per direction of Engineer-in-charge.
Depiling of ballies in dismantling of jetty and stacking for proper completion of work as per direction of Engineer-in-charge.
MAHENDRA KUMAR PANDEY
M/S SUNIL SINGH
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .