Tender Value
₹7.6 Cr
EMD Value
₹5.3 L
Closing Date
24 Feb 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
TENDER
15 conditions · 4 needing a document upload
Financial Eligibility Criteria : The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
Electrical License: The individual/firm should have valid "B" grade electrical license and should be on their own name/firm name issued by the competent Authority. A copy of license should be uploaded through IREPS with their offer, failing which the tender WILL BE REJECTED.
Similar nature of work: - "Supply, installation, testing and commissioning of solar power generating system at least 5 KWp capacity"." Note: This is minimum capacity of either grid connected or off grid systems (Ref: Hqrs Lr.No:E.29/P/Similar nature of works Dt: 30.12.2014.)
Technical Eligibility Criteria: (a)The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i)Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii)Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii)One similar work costing not less than the amount equal to 60% of advertised value of the tender. (b) (1)In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i)Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or (ii)Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or (iii)One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender.
37 conditions · 4 needing a document upload
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
The General Conditions of Contract governing the performance of the works covered by this tender are the Indian Railway Standard General Conditions of Contract as amended from time to time up to date. A soft copy of the Indian Railway Standard General conditions of Contract is uploaded in the annexed documents to the tender. Hard copy may be perused in the office of the Senior Divisional Electrical Engineer/Maintenance/ Secunderabad Division/ South Central Railway / Secunderabad - 500025. In submitting the tender it would be deemed that the tenderer has kept himself fully Informed of the provision of the Indian Railways Standard General Conditions of Contract including all corrections and Amendments issued upto date and claim that he is not aware of any amendment or correction slip to the IRSGCC shall not be entertained.(As per IRGCC April 2022 or latest with amendments).
STUDY OF DRAWINGS AND LOCAL CONDITIONS: The drawings for the works can be seen in the office of the Senior Divisional Electrical Engineer/Maintenance/ Secunderabad Division/ South Central Railway/ Secunderabad - 500025. It should be noted that these drawings are meant for general guidance only and Railway may suitably modify them during the execution of work according to the circumstances without making the Railways liable for any claims on account of such changes. If there is any variation between the description in the tender and the detailed plans, the Engineer-in-Charge will operate the correct description and his decision is final and binding on the tenderer/ Contractor. The Tenderer/Contractor is required to inspect the sites of works and acquaint himself with the site conditions, availability of approaches for transporting of men and materials, space and other factors relating to the works, availability of labour, electricity and water, etc., before quoting his rates. The extent of lead and lift involved in the execution of works and any difficulties involved in the execution of work should also be examined before formulating the rates for complete items of works described in the schedule. The Tender submitted will be deemed to have been made after such inspection.(As per IRGCC April 2022 or latest with amendments).
DRAWINGS FOR WORKS: The percentage rates for the schedule items and itemized rates for the non-scheduled items quoted by the tenderer as may be accepted by the railways will, hold good irrespective of any changes, modifications, alterations, additions, omissions in the locations of structures and detailed drawings, specifications and/or the manner of executing the work. It should be specifically noted that some of the detailed drawings may not have been finalised by the Railway and will, therefore, be supplied to the contractor as and when they are finalised on demand. No compensation whatsoever on this account shall be payable by the Railway Administration. No claim whatsoever will be entertained by the Railway on account of any delay or hold up of the works arising out of delay in approval of drawings, changes, modifications, alterations, additions, omission and the site layout plans or detailed drawings and design and/or late supply of such material as are required to be arranged by the Railway or due to any other factor on Railway Accounts.(As per IRGCC April 2022 or latest with amendments).
Manual tenders sent by Post/FAX/Courier or in Person SHALL NOT BE ACCEPTED (As per IRGCC April 2022 or latest with amendments).
If the Bid of a Tenderer is seriously unbalanced in relation to the Engineer's estimate of the cost of work to be performed under the contract, the Railways may require the tenderer to produce detailed price analysis for any or all items of the Tender Schedule, to demonstrate the internal consistency of those prices with the construction methods and schedule proposed. (As per IRGCC April 2022 or latest with amendments).
CORRIGENDUM NOTICE ON IREPS: [I] Railway may modify the tender document by issuing online corrigendum through www.ireps.gov.in [II] Prospective Bidders shall keep watch for CORRIGENDUM upto 15 days prior to the deadline for submission of bids. For the purpose of CORRIGENDUM in the tender, NIT period is splitted as under: (a) ADVERTISEMENT PERIOD: The time during which all information pertaining to tender shall be available but offers cannot be submitted (b) OFFER SUBMISSION PERIOD: 15 days prior to closing of tender, during which tenderers can submit their offer. [III] To give prospective bidders a reasonable time on account of CORRIGENDUM in preparing their bids, the Railways may at their discretion extend as necessary, the deadline for submission of Tender document. Railways decision will be final and no correspondence will be entertained from prospective bidders. (As per IRGCC April 2022 or latest with amendments).
E-Tender shall be rejected if it is not accompanied by the prescribed: [1] Cost of tender document [2] EMD [3] Certificate(s) in support of technical eligibility criteria [4] Certificate(s) in support of financial eligibility criteria [5] Copy of documents in support of Proprietary concern/ Partnership firm / Pvt.Ltd.company / Limited Company / JV firm / Valid MOU for JV firms as detailed in COMMERCIAL COMPLIANCE. (As per IRGCC April 2022 or latest with amendments).
The bidders/tenderers should ensure that they are GST compliant. Quoted rates are inclusive of applicable GST as per GST ACT -2017 amended from time to time and as detailed in Special Conditions - General (under TAXES clause). (As per IRGCC April 2022 or latest with amendments).
The tenderer[s] may also upload the following documents alongwith his/their tender: The tenderer may upload method statement, which shall contain organizational set up and working systems to be adopted by the successful tenderers during the operation of the contract. It shall contain the details of man power and machineries in the prescribed format and details of methodology for planning, execution, monitoring and completion of the project. The methodology so adopted shall suit to the nature of work and shall also comply fully with best practice and current regulations. A comprehensive detailing for each activity like setting-up organization, safety plan, execution plan, quality assurance plan, sequence of work to achieve the mile stones, ensure targeted progress and quality and inturn deployment of resources, risk analysis and its mitigation strategy shall be given communication arrangement within his organization and with the railways for decisions, progress or any other matter connected with this project to ensure full information about the project including progress of work at different time scale shall also be furnished. (As per IRGCC April 2022 or latest with amendments).
Tenderer shall adhere to the time frame as mentioned in mile stone chart prescribed in the tender. (As per IRGCC April 2022 or latest with amendments).
Tenderer shall engage the personnel with requisite qualification as per Special Conditions of Contract. (As per IRGCC April 2022 or latest with amendments).
Tenderer shall deploy adequate number of plant and equipment for the execution of subject contract works to achieve progress as per mile stone chart. (As per IRGCC April 2022 or latest with amendments).
List of works completed in the last seven financial years giving description of work, organization for whom executed, approximate value of contract at the time of award, date of award and date of scheduled completion of work. Date of actual start, actual completion and final value of contract should also be given. (As per IRGCC April 2022 or latest with amendments).
List of works on hand indicating description of work, contract value, and approximate value of balance work yet to be done and date of award. (As per IRGCC April 2022 or latest with amendments).
Supportive documents/certificates from the organizations with whom they worked/are working as list of works completed and list of works on hand should be enclosed. (As per IRGCC April 2022 or latest with amendments).
[1] I/We have read the various conditions of the tender attached hereto and hereby agree to abide by the said conditions. I/We also agree to keep this tender open for acceptance for the period mentioned in the tender document [NIT HEADER] from the date fixed for opening the same and in default thereof, I/We will be liable for forfeiture of my/our Earnest Money Deposit submitted. [2] I/We offer to do the work at the percentage rates quoted by me/us in the attached schedule and bind myself/ourselves to complete the work within the period of completion given in this tender document [NIT HEADER] from the date of issue of letter of acceptance of this tender. I/We also hereby agree to abide by the IRS GCC and Special Conditions of contract in carryingout the works laid down by South Central Railway for the present contract. [3] The full value of the earnest money paid shall stand forfeited without prejudice to any other rights or remedies of the railway if [a]I/We do not execute the contract document within seven days after receipt of notice issued by the Railway that such documents are ready: OR [b] I/We do not commence the work within fifteen days after receipt of orders to that effect. [4] Until a formal agreement is prepared and executed, acceptance of this tender shall constitute a binding contract between us subject to modifications, as may be mutually agreed to between us and indicated in the letter of acceptance of my/our offer for this work. (As per IRGCC April 2022 or latest with amendments).
I/We fail to submit the requisite Performance Guarantee [P.G] in the prescribed format within the time limit as prescribed in GCC (as amended from time to time) from the date of issue of Letter of Acceptance, we are aware that the contract shall be terminated duly forfeiting EMD and other dues, if any payable against the contract. Also, I/We shall be debarred from participating in the retender for the work. (As per IRGCC April 2022 or latest with amendments).
I/We understand that no post-tender correspondence will be entertained, however, if any clarification is required by the Railway, the same will be sought from the tenderer. Also, I/We are aware that any Certificate/ Documents offered after the tender opening shall not be given any credit and shall not be considered. (As per IRGCC April 2022 or latest with amendments).
I/we do hereby solemnly affirm and state on behalf of the tenderer including its constituents as under: (As per IRGCC April 2022 or latest with amendments).
[i] I/We the tenderer(s) am/are signing this document after carefully reading the contents. [ii] I/We declare and certify that I/We have not made any misleading or false representation in the documents, forms, statements attached in proof of the qualification requirements. [iii] I/We also understand that my/our offer will be evaluated based on the documents/credentials uploaded alongwith the offer and the same shall be binding upon me/us. [iv] I/We declare that the information and the documents attached alongwith the tender by me/us are correct and I/We are fully responsible for the correctness of the information and the documents submitted by us. (As per IRGCC April 2022 or latest with amendments).
[i] I/We do hereby undertake that, if any of the certificates regarding eligibility criteria submitted by us are found to be forged/false/incorrect at any time during the process of evaluation of the tenders, it shall lead to forfeiture of the tender EMD. Further, I/We and all my/our constituents understand that my/our offer shall be summarily rejected. [ii] I/We also understand that, if the certificates submitted by us are found to be false/forged/ incorrect at any time after the award of the contract, it will lead to termination of the contract besides suspending of business for 5 years, with the tenderer and with all the partners in case of partnership firm and with all the members of a JV in case of a Joint Venture, forfeiture of EMD/SD and Performance Guarantee and any other action provided in the contract. (As per IRGCC April 2022 or latest with amendments).
It is certified that I/We have not been blacklisted or debarred by railways or any other ministry/ department/public sector undertaking of the government of India/State Government from participation in tenders/contract on the date of tender opening of bids, either in individual capacity or as a member of JV firm in which I/We were/are members. (As per IRGCC April 2022 or latest with amendments).
I/We indemnify and save harmless the Railway from and against all actions, suit proceedings losses, costs, damages, charges, claims and demands of every nature and description brought or recovered against the Railways by reason of any act or omission of the Contractor, his agents or employees, in the execution of the works or in his guarding of the same. All sums payable by way of compensation under any of these conditions shall be considered as reasonable compensation to be applied to the actual loss or damage sustained, and whether or not any damage shall have been sustained. (As per IRGCC April 2022 or latest with amendments).
The prices are inclusive of GST
Secunderabad Division Electrical Maintenance Department - Schedule -A - Provision of rooftop solar plants of different capacities along with cleaning accessories on Station buildings, Cover over platforms, Service buildings , residential buildings over SC division. Schedule - B - Provision of Solar geyser, solar street lights, Solar pumps, and Occupancy sensors, energy saver for welding transformer to meet HQ action plan targets for the year of 2025-26 - Electrical arrangements.
E-M-SC-39-OT-2025-26~SCR
E-M-SC-39-OT-2025-26
Open
Works - General
6 Months
Hyderabad, Telangana
₹0
₹5.3 L
24 Feb 2026
2 Feb 2026
10 Feb 2026
200 items across 2 schedules
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 6,50,01,724 | ||
| — | 3.00 | — | — | ||
| Design, Supply and fixing of 100 KWp rooftop on-grid solar plant with MPPT technology with Mono PERC Bifacial solar modules of 535wp or above, Module Mounting Structure,Power Conditioning Unit (PCU) consisting of Maximum Power Point Tracker (MPPT),Inverter ( inverters may be planned as per site feasibility from 10-100KW output puresine wave inverter with RMS ), and Controls and Protections, interconnect cables and switches ,all complete as per the standard specifications as per the direction of site Engineer, | — | — | — | 1,43,13,000 | |
| — | 5.00 | — | — | ||
| Design, Supply and fixing of 50 KWp rooftop on-grid solar plant with MPPTtechnology w ith Mono PERC Bifacial solar modules of 535wp or above, Module Mounting Structure,Power Conditioning Unit (PCU) consisting of Maximum Power Point Tracker (MPPT),Inverter ( inverters may be planned as per site feasibility from 10-50KW output pure sine wave inverters with RMS ), and Controls and Protections, interconnect cables and switches ,all complete as per the standard specifications as per the direction of site Engineer, | — | — | — | 1,19,27,500 | |
| — | 2.00 | — | — | ||
| Design, Supply and fixing of 40 KWp rooftop ongrid solar plant with , MPPT technology with Mono - PERC Bifacial solar modules of 535wp or above, Module Mounting Structure, Power Conditioning Unit (PCU)consisting of Maximum Power Point Tracker(MPPT), Inverter ( inverters may be planned as per site feasibility from 10-40KW output pure sine wave inverters with RMS), and Controls and Protections, interconnect cables and switches including net meter ,all complete as per the standard specifications as per the direction of site Engineer. | — | — | — | 38,16,800 | |
| — | 2.00 | — | — | ||
| Design, Supply and fixing of 30 KWp rooftop on-grid solar plant with MPPTtechnology with Mono PERC Bifacial solar modules of 535wp or above, Module Mounting Structure, Power ConditioningUnit (PCU) consisting of Maximum Power Point Tracker (MPPT),Inverter ( inverters may be planned as per site feasibility from 10-30KW output pure sine wave inverters with RMS), a and Controls and Protections, interconnect cables and switches including net meter ,all complete as per the standard specifications as per the direction of site Enginee. | — | — | — | 28,62,600 | |
| — | 7.00 | — | — | ||
| Design, Supply and fixing of 20KWp rooftop ongrid solar plant with , MPPTtechnology with Mono PERC Bifacial solar modules of 535wp or above, Module Mounting Structure, Power Conditioning Unit (PCU)consisting of Maximum Power Point Tracker(MPPT), Inverter( inverters may be planned as per site feasibility from 10-20KW output pure sine wave inverters with RMS), and Controls and Protections, interconnect cables and switches ,all complete as per the standard specifications as per the direction of site Engineer. | — | — | — | 66,79,400 | |
| — | 9.00 | — | — | ||
| Design, Supply, erection, fixing and commissioning of 10 KWp rooftop on-grid solar plant with MPPTtechnology with Mono PERC Bifacial solar modules of 535wp or above,ModuleMounting Structure, Power Conditioning Unit (PCU) consisting of Maximum Power Point Tracker (MPPT),Inverter (10KW output puresine wave inverterwith RMS), and Controls and Protections, interconnect cables and switches ,all complete as per the standard specifications as per the direction of site Engineer. | — | — | — | 42,93,900 | |
| — | 1.00 | — | — | ||
| Design, Supply, Installation, Testing & Commissioning of 50 kWp Building Integrated Roof Solar Photo Voltaic (BIPV) On Grid Solar plant including connecting to the existing grid/local supply through suitably designed inverter complete set consists of Solar panels (Mono- PERC) with MPPT technology, Module Mounting Structure- HDGI Structure for BIPV Solar Modules, Power Conditioning Unit (PCU) consisting of Maximum Power Point Tracker (MPPT), Inverter ( inverters may be planned as per feasibility from 10-50KW output pure sine wave inverter with RMS ), SIlicon sealant material, Aluminum T Profile and controls and Protections, interconnect cables and switches all complete & as per enclosed specifications with all associated Civil works & hardware items for installation of BIPV System with necessary accessories. | — | — | — | 41,27,950 | |
| — | 300.00 | — | — | ||
| Supply and erection of 4 core x150 Sqmm LTUG XLPE Aluminum armored cable as per BIS specification IS 7098 Part I or (latest amendments ) along with end terminations | — | — | — | 2,67,300 | |
| — | 100.00 | — | — | ||
| Supply and erection of 4 core x120 Sqmm LTUG XLPE Aluminum armored cable as per BIS specification IS 7098 Part I or (latest amendments ) along with end terminations | — | — | — | 87,500 | |
| — | 100.00 | — | — | ||
| Supply and erection of 4 core 95 qmm LTUG XLPE aluminium armoured cable as per BIS specification IS 7098 Part I or(latest amendments ) along with end terminations | — | — | — | 70,700 | |
| — | 800.00 | — | — | ||
| Supply and erection of 4 core x70 Sqmm LTUG XLPE Aluminum armored cable as per BISspecification No.IS 7098.Part-I or (latestamendments ) along withend terminations | — | — | — | 4,44,800 | |
| — | 200.00 | — | — | ||
| Supply and erection of 4 core 50 qmm LTUG XLPE aluminium armoured cable as per BIS specification IS 7098 Part I or(latest amendments ) along with end terminations | — | — | — | 79,600 | |
| — | 1600.00 | — | — | ||
| Supply and erection of 4 core x35 Sqmm LTUG XLPE Aluminum armored cable as per BISspecification No.IS 7098.Part-Ior (latestamendments ) along withend terminations | — | — | — | 5,20,000 | |
| — | 500.00 | — | — | ||
| Supply and erection of 8SWG GI wire | — | — | — | 5,000 | |
| — | 100.00 | — | — | ||
| Horizontal drilling of bores for HT/LT cables of suitable size as per the guideline of Site Engineer | — | — | — | 2,15,700 | |
| — | 1500.00 | — | — | ||
| Excavation of cable trench in all types of soils for LT cable as per the directions of engineer at site making good after laying the cable | — | — | — | 1,95,000 | |
| — | 200.00 | — | — | ||
| Excavation of cable trench in cement concrete bed flooring as per the Rly specification No:C/E/UGC/1/92& Drg No:SC/A3/STD/1288 | — | — | — | 81,000 | |
| — | 100.00 | — | — | ||
| Excavation of cable trench across No:C/E/UGC/1/92& Drg No:SC/A3/STD/1288 Alt-I | — | — | — | 26,500 | |
| — | — | — | Rly | ||
| — | — | — | specification | ||
| — | 60.00 | — | — | ||
| Supply and erection of earthing arrangements (as per RDSO specification No.TI_LKO (PSI@47&47@2020 dt.23.05.21 or latest) | — | — | — | 2,09,880 | |
| — | 60.00 | — | — | ||
| Supply and Erection Provision of RCC earth pit hollow box of size 300 mm x 300 mm x 300mm with 50 mm wall thickness by using M20 Grade precast RCC. It includes fixing of earth pits at various locations (All the required men, material and transportation are to be arranged by contractor) Drawings to be collected in the office of Sr.DEE/M/SC. | — | — | — | 44,160 | |
| — | 60.00 | — | — | ||
| Supply and Erection of RCC precast slabs with hook to cover Earth pits of dimensions as per drawings. All the required materials for this work i.e. stones, cement, iron and sand etc. are to be supplied by contractor.) Drawings to be collected in the office of Sr.DEE/M/SC. | — | — | — | 9,360 | |
| — | 400.00 | — | — | ||
| Supply and erection of 50mm of HDPE pipes of Grade PE-100, PN 6 (6Kg/Cm2 Capacity) with accessories as per IS 4984 - 2016 (SDR-21) | — | — | — | 36,400 | |
| — | 400.00 | — | — | ||
| Supply and erection of 63 mm HDPE pipes of Grade PE-100,PN 6 (6Kg/Cm2 Capacity) with accessories as per IS 4984 - 1995 | — | — | — | 53,200 | |
| — | 100.00 | — | — | ||
| Supply and erection of 110 mm HDPE pipes of Grade PE-100, PN 6 (6Kg/Cm2 Capacity) with accessories as per IS 4984 - 1995 | — | — | — | 41,900 | |
| — | 3.00 | — | — | ||
| Supply and erection of 250A 4 pole MCCB with 36KA breaking capacity with LSIG Micro processor based release with extended ROH , spereder links(4 nos-02 sets) and phase barriers | — | — | — | 89,094 | |
| — | 2.00 | — | — | ||
| Supply and erection of 160A 4 pole MCCB with 36 KA breaking capacity with LSIG Micro processor based release with extended ROH , spereder links(4 nos-02 sets) and phase barriers | — | — | — | 54,618 | |
| — | 8.00 | — | — | ||
| Supply and erection of 100A 4 pole MCCB with 25KA breaking capacity with Adjustable thermal magnetic release with extended ROH , spereder links(4 nos-02 sets) and phase barriers | — | — | — | 49,512 | |
| — | 9.00 | — | — | ||
| Supply and erection of 63A 4 pole MCCBs with 16 KA breaking capacity with Adjustable thermal magnetic release with extended ROH , spreader links(4 nos-02 sets) and phase barriers | — | — | — | 36,315 | |
| — | 9.00 | — | — | ||
| Supply and erection of 32A 4 pole MCCBs with 16 KA breaking capacity with Adjustable thermal magnetic release with extended ROH , spreader links(4 nos-02 sets) and phase barriers | — | — | — | 36,315 | |
| — | 10.00 | — | — | ||
| Supply and erection of MCCB enclosure for suitable above MCCBs | — | — | — | 20,480 | |
| — | 47.00 | — | — | ||
| lumpsum provision for payment to the discom authorities towards net metering arrangement including metering cost and other statutory clearances, liaisoning and coordinating with discom for obtain NOC for net metering & agreement etc. | — | — | — | 18,80,000 | |
| — | 170.00 | — | — | ||
| Design, supply,Installation,testing and commissioning of online monitoring system of solar power plant with 5 years validity and access to web portal, including server charges and connected accessories etc.as per thedirection of Engineer at site | — | — | — | 23,73,030 | |
| — | 5.00 | — | — | ||
| Supply and fabrication of Ladders with handrails & Canopy for power plants including painting transportation and civil work | — | — | — | 4,05,210 | |
| — | 500.00 | — | — | ||
| Supply and fixing of FRP Walkway forsolar plant with Specification (L-4000mmxW- 300mmXH-30 mm) | — | — | — | 21,50,000 | |
| Supply of automatic PV module cleaning system for solar power plants and existing solar plants over SC divison | — | 2000.00 | — | — |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
2_GCC_April-2022_withcorrectionslips.pdf
ATTACHMENT
Specifications_for_solar_Street_Lights.pdf
ATTACHMENT
1_Tender_Booklet_E_M_SC_39_OEW_OT_2025_26_Corrigendum.pdf
ATTACHMENT
Specifications_for_VVVF_Drives_1.pdf
ATTACHMENT
Specifications_for_VVVF_Drives_1.pdf
CORRIGENDUM
Specifications_for_solar_Street_Lights.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .