| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹97.6 LAccepted-AOC AT PO KALAMUCHHIN PS COLLIERY TALCHER DIST ANGUL PIN 759103 ODISHA | TALCHER | ANGUL | ODISHA | 759103 | ₹97.6 L Quoted ₹85.9 L | L-1 | Accepted-AOC techno-commercially eligible L-1 bidder. |
| 2 | L-2₹94.7 LRejected-Finance AT BRAHMAN SASAN TALCHER DIST ANGUL PIN 759100 ODISHA | ANUGUL | ODISHA | 759100 | ₹94.7 L | L-2 | Rejected-Finance Rejected due to not becoming techno-commercially eligible L-1 bidder. |
| Sl No | Description | Qty | Unit | SIVA SHEKHAR SAHOO L2 | TRISHAKTI ENGINEERING L1 |
|---|---|---|---|---|---|
| 1.00HT RELATED WORKS | |||||
| 1.01 | Erection of metallic pole of following length in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) foundation including excavation and refilling etc. as required.
Above 10.00 metre and upto 12.00 metre | 20 | each | 6,233.92 ₹1.2 L | 3,800 ₹76,000 |
| 1.02 | Supplying and erection of galvanised stay set for 11 KV over head lines complete with 19/ 20 mm dia X 1.8 metres long stay rod, anchor plate of size 45 cm X 45 cm X 7.5 mm thick, thimble, stay clamps, turn buckle ( 20 mm X 600 mm ), 7/ 4.00 mm dia G.I. stay wire and 11 KV strain insulator etc in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size ) foundation including excavation and refilling etc. as required. | 20 | set | 4,817.12 ₹96,342.40 | 3,400 ₹68,000 |
| 1.03 | Supplying of channel iron 75 mm X 40 mm X 6 mm (7.14 kg per metre) pole top bracket/ cross arm for single 11 KV over head line conductor complete with 50 mm X 6mm flat iron clamp, bolts, nuts and washers including drilling holes for insulator pins, bolts and nuts etc and painting with primer and finish paint as required . | 20 | each | 442.52 ₹8,850.40 | 220 ₹4,400 |
| 1.04 | Supplying of channel iron 75 mm X 40 mm X 6 mm (7.14 kg per metre) V shape cross arm for two 11 KV over head line conductors complete with 50 mm X 6mm M.S. flat iron clamps, bolts and
nuts including drilling holes for insulator pins, bolts, nuts and washers etc (as per drawing) and painting with primer and finish paint as required. | 20 | each | 1,555.72 ₹31,114.40 | 1,350 ₹27,000 |
| 1.05 | Erection of pole top/ straight two wire/ V shape two wire, angle iron/ channel iron, cross arm on steel tubular/ rail/ PCC pole for 11/22/33 KV as required. | 20 | set | 356.04 ₹7,120.80 | 90 ₹1,800 |
| 1.06 | Supplying of two lengths of channel iron 75 mm X 40 mm X 6 mm (7.14 kg per metre) double pole cross arm for three wire 11KV over head line conductors complete with through bolts and
nuts for clamping to the poles, 50 mm X 6 mm M.S. flats welded on one side to the channel iron and with bolts and nuts on the other side for tying the cross arms together, including drilling holes for insulator pins/ fittings, bolts, nuts and washers etc (as per drawing) and painting with primer and finish paint as required . | 10 | set | 4,119.76 ₹41,197.60 | 3,600 ₹36,000 |
| 1.07 | Erection of double pole 3 wire cross arm for 11KV/ 22KV/ 33 KV over head lines as required. | 5 | each | 805.92 ₹4,029.60 | 300 ₹1,500 |
| 1.08 | Supplying and erection of 11 KV pin insulator complete with large steel head G.I. pin, nuts, washers etc. as required. | 30 | set | 238.28 ₹7,148.40 | 270 ₹8,100 |
| 1.09 | Supplying and erection of 11 KV disc insulator for 11 KV over head lines with galvanised insulator fittings, ball and socket type and complete with galvanised strain clamps, bolts, nuts, washers
etc. as required. | 30 | set | 927.36 ₹27,820.80 | 850 ₹25,500 |
Updated dates
Tender Value
₹1.0 Cr
EMD Value
₹1.3 L
Closing Date
17 Feb 2026, 5:00 pmClosed
Staff Officer(EnM), Jagannath Area, MCL
Deenabandhu Sethi, Staff Officer(EnM), Jagannath Area, MCL PH 06760-269717, 06670-269751(Extn)2023 Fax 06760-269527 E-mail so-enm-jaga.mcl(at)coalindia.in
Day to day maintenance, dismantling and erection of power line of 11KV/3.3KV/440V grade of different feeders along with maintenance of lighting circuit under Balanda Colony of Jagannath OCP for a period of Two years on as and when required basis
2026_MCL_351896_1
GM(JA)/EnM/e-Tender/ 25-26/E-813/078 DTD. 27/01/2026
Open Tender
Electrical and Maintenance Works
730 days
Talcher
AS PER NIT
6 documents required · 6 mandatory
₹1.3 L
4 Jun 2026
27 Jan 2026
20 Feb 2026
28 Jan 2026
17 Feb 2026
28 Jan 2026
28 Jan 2026 - 6 Feb 2026
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 1.00 MB
Tendernotice_2.pdf
PDF • 1.58 MB
BOQ_364668.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid