| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹6.9 CrAccepted-AOC | ₹6.9 Cr | 1 | Accepted-AOC Accepted by COT chennai |
| 2 | 2₹7.1 CrRejected-Finance 18 CORPORATION ROAD DEVAKOTTAI | SIVAGANGA | TAMIL NADU | 630001 | ₹7.1 Cr | 2 | Rejected-Finance L2 Tenderer |
| 3 | 3₹7.1 CrRejected-Finance MADURAI ROAD SEKKANOORANI MADURAI | MADURAI | TAMIL NADU | 625001 | ₹7.1 Cr | 3 | Rejected-Finance L3 Tenderer |
Tender Value
₹6.9 Cr
EMD Value
₹3.5 L
Closing Date
22 Jan 2026, 12:15 pmClosed
Thiru.R.K.Ramesh
O/o the Superintending Engineer Highways Projects Circle Alagarkovil Main Road Madurai 2
Providing Junction Improvements at km 7/6 and 10/8 in the main work of Forming of Bypass to Sivagangai town branching from Km 129/2 of Thanjavur - Manamadurai road SHU (Sivagangai urban stretch) and merging with Thanjavur Manamadurai road NH226
2026_HWAY_640390_1
TN No 14 2025 26 SDO Dated 30.12.2025
Open Tender
Civil Works - Highways
180 days
Sivagangai
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹3.5 L
O/o the Superintending Engineer Highways Projects
4 Mar 2026
8 Jan 2026
22 Jan 2026
8 Jan 2026
22 Jan 2026
8 Jan 2026
8 Jan 2026 - 20 Jan 2026
12 Jan 2026
Picking the existing BT surface to 90mm deep including levelling and sectioning in hard granite, gneiss, quartz etc., complete as directed by the departmental officers. Junction At km 7/6 & 10/8
Earth work excavation and disposal of excavated earth by transfer with a lead of 5 km away from work site as directed by the departmental officers for disposal as per Standard Specifications and all other incidental charges etc., complete. Junction At km 7/6 & 10/8
Forming embankment using carted earth having a minimum CBR of 95% with an average lead of 17 km, including laying and spreading in layers of 250 mm loose thick each, sectioning, watering and compacting by Power roller to achieve the required density at 95% Proctor Density at optimum moisture content as determined in occurence with IS 2720(Part VII) for sub grade including finishing the surface to the required camber and longitudinal profile including all leads for water and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete as per Clause 301 - 305 of MoRT&H - V Revision for - Carted Earth for filling Junction At km 7/6 & 10/8
Forming embankment using carted earth having a minimum 8 CBR of 97% with an average lead of 11 km, including laying and spreading in layers of 250 mm loose thick each, sectioning, watering and compacting by Power roller to achieve the required density at 97% Proctor Density at optimum moisture content as determined in occurence with IS 2720(Part VII) for sub grade including finishing the surface to the required camber and longitudinal profile including all leads for water and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete as per Clause 301 - 305 of MoRT&H - V Revision for - Carted Earth for filling Junction At km 7/6 & 10/8
Providing and laying Granular Sub Base (GSB) Grade - V to required thickness on the prepared minimum CBR value 30 grading conforming to Table 400-1 of MoRT&H, Revision - V with sand, gravel crushed stone or quarry fines or any other granular material or combination to given CBR of 30 on prepared sub grade in accordance with the requirements of the specifications including cost of materials, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 401 of MoRT&H -V to the work site spreading in uniform layers with motor grader on prepared surface and compacting with vibratory roller to achieve the desired complete as per clause 401 of MoRT&H V Revision Junction At km 7/6 & 10/8
Providing and laying Granular Sub Base (GSB) Grade - III to required thickness on the prepared minimum CBR value 30 grading conforming to Table 400-1 of MoRT&H, Revision V with sand, gravel, crushed stone or quarry fines or any other granular material or combination to given CBR of 30 on prepared sub grade in accordance with the requirements of the specifications including cost of materials, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 401 of MoRT&H -V to the work site spreading in uniform layers with motor grader on prepared surface and compacting with vibratory roller to achieve the desired complete as per Clause 401 of MoRT&H V Revision Junction At km 7/6 & 10/8
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 250mm thick specification including premixing the materials with water at OMC in mechanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base / Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 406 of MoRT&H V Revision Junction At km 7/6 & 10/8
Providing and laying Prime Coat over WMM surface using 7Kg of Emulsion Bitumen (SS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MoRT&H V Revision Junction At km 7/6 & 10/8
Proivding and laying of Tack Coat over WMM surface (treated with primer) using 2.5 Kg Bitumen Emulsion (RS1) per 10sqm for preparatary to another bitumious costruction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MoRT&H V Revision Junction At km 7/6 & 10/8
Providing and laying Tack Coat over Concrete surface using 2.50kg of Bitument Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MoRT&H V Revision Junction At km 7/6 & 10/8
E_5Providing and laying 65mm consolidated thick Dense Bituminous Macadam using 0.24 cum of
氠慯景ㄠ㘳㔳欠整瑳摥椠捡潣摲湡散眠瑩十䵔䐠㈴〸愠摮挠湯楦浲湩潴䤠䍒㌠ⴵ〲㔱朠極敤楬敮湡潍呒⁈灳捥晩捩瑡潩〸‴瑥潣灭敬整䨊湵瑣潩瑁欠†⼷‶…〱㠯†††††,ՉեԒЈ倀潲楶楤杮†湡攠敲瑣湩删瑥潲爭晥敬瑣牯獩摥†䠠穡牡慍歲牥吠慲晦捩匠杩洠摡畯⁴景䠠杩湉整獮瑩⁹楍牣牐獩慭楴片摡桳敥楴杮挠湯楦浲湩潴吠灹䤭⁖瑳湡慤摲景䤠䍒㘭㨷〲㈱愠摮䄠呓⁍⁄㤴㘵〭ⰹ猠数楣楦慣楴湯愠摮映硩摥†′浭琠楨正䄠畬業畮桳敥⁴楦數癯牥愠戠捡畳灰牯楴杮映慲敭㈠洵硭㔲浭㍸浭䴠汩瑳敥湡汧湡畳灰牯整湯愠洠汩瑳敥湡汧物湯瀠獯⁴㔷浭砠㜠洵㙸浭†楷桴愠挠敬牡栠楥桧⁴景渠瑯氠獥桴湡㈠ㄮ洰映潲桴牧畯摮氠癥汥琠桴潢瑴浯漠楳浧戠慯摲愠摮〠㘮洰戠汥睯朠潲湵敬敶吠敨猠杩潰瑳猠潨汵敢瀠楡瑮摥愠数剉⁃㜶㈭′湡楦浲祬†楦數潴琠敨朠潲湵祢洠慥獮漠牰灯牥祬搠獥杩敮潦湵慤楴湯眠瑩ㅍ‵牧摡散敭瑮挠湯牣瑥㔴浣砠㐠挵⁸〶挠楳敺椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污ⱳ煥極浰湥ⱴ慭档湩牥⁹湡慬潢牵眠瑩污敬摡愠摮氠晩獴潬摡湩档牡敧敮散獳牡⁹潦慳楴晳捡潴祲挠浯汰瑥潩景琠敨眠牯獡搠物捥整祢琠敨攠杮湩敥湩挠慨杲楈桧椠瑮湥楳祴删瑥潲刭晥敬瑣潲猠敨瑥猠慨汬挠湯楳瑳漠業楮畭潣晥楦楣湥⁴景删瑥潲爭晥敬瑣潩獡瀠牥琠扡敬㘠㘮漠剉⁃㜶㈭⸲吠敨爠瑥潲爭晥敬瑣癩桳敥楴杮猠慨汬戠潣敶敲湵敤‷敹牡眠牡慲瑮⁹獩畳摥映牯映敩摬瀠牥潦浲湡散愠摮愠挠牥楴楦摥挠灯⁹景琠牨敥礠慥獲漠瑵潤牯攠灸獯牵敲潰瑲猠慨汬戠扯慴湩摥愠数剉⁃㜶㈭⸲愨数位呒䠦猠数楣楦慣楴湯丠〸⤱††††††††䨊湵瑣潩瑁欠†⼷‶…〱㠯 Ԁ㸀Ԅᄀ伀ࠅ牐癯摩湩愠摮†牥捥楴杮†敒牴ⵯ敲汦捥潴楲敳†慃瑵潩慮祲慍摮瑡牯⁹湡湉潦浲瑡牯⁹匠杩獮⠠楷桴畯⁴敤楦楮楴湯戠慯摲 †慭敤漠瑵漠楈桧䤠瑮湥楳祴䴠捩潲倠楲浳瑡捩䜠慲敤猠敨瑥湩潣普物業杮琠祔数ⴠ噉猠慴摮牡獤漠剉ⵃ㜶㈺′湡十䵔䐠㐠㔹ⴶ㤰灳捥晩捩瑡潩湡楦數㈠洠桴捩汁浵湩浵猠敨瑥映硩摥漠敶慢正猠灵潰瑲湩牦浡㔲浭㉸洵硭洳楍摬猠整汥愠杮敬愠摮猠灵潰瑲摥漠業摬猠整汥愠杮敬椠潲潰瑳㜠洵⁸㔷浭砠洶眠瑩汣慥敨杩瑨漠潮⁴敬獳琠慨⸲〱牦浯琠敨朠潲湵敬敶潴琠敨戠瑯潴景猠杩潢牡湡⸰〶敢潬⁷牧畯摮氠癥汥桔楳湧瀠獯⁴桳畯摬戠慰湩整獡瀠牥䤠䍒㘠ⴷ〲㈱愠摮映物汭⁹映硩摥琠桴牧畯摮戠⁹敭湡景瀠潲数汲⁹敤楳湧摥映畯摮瑡潩楷桴䴠㔱朠慲敤挠浥湥⁴潣据敲整㐠挵⁸㔴浣砠㘠‰浣猠穩湩汣摵湩潣瑳愠摮挠湯敶慹据景愠汬洠瑡牥慩獬攬畱灩敭瑮洬捡楨敮祲愠摮氠扡畯楷桴愠汬氠慥湡楬瑦ⱳ氠慯楤杮挠慨杲獥渠捥獥慳祲映牯猠瑡獩慦瑣牯⁹潣灭敬楴湯漠桴潷歲愠楤敲瑣摥戠⁹桴湥楧敮牥椠档牡敧䠮杩湩整獮瑩⁹敒牴ⵯ敒汦捥牴桳敥⁴桳污潣獮獩⁴景洠湩浩浵挠敯晦捩敩瑮漠敒牴ⵯ敲汦捥楴湯愠数慴汢⸶‶景䤠䍒㘠ⴷ〲㈱桔敲牴ⵯ敲汦捥楴敶猠敨瑥湩桳污敢挠癯牥摥甠摮牥㜠礠慥慷牲湡祴椠獳敵潦楦汥数晲牯慭据湡散瑲晩敩潣祰漠桴敲敹牡畯摴潯硥潰畳敲爠灥牯⁴桳污敢漠瑢楡敮獡瀠牥䤠䍒㘠ⴷ〲㈱⠮獡瀠牥䴠副♔⁈灳捥晩捩瑡潩潎㠮⸩攊畱汩瑡牥污琠楲湡汧䨊湵瑣潩瑁欠†⼷‶…〱㠯†††††礠ሀԅ㨀捏潴潧慮††††ਠ畊据楴湯䄠⁴浫†㜠㘯☠ㄠ⼰‸†††††ƵЈ匀灵汰楹杮愠摮椠獮慴汬瑡潩景搠汥湩慥潴獲爨慯慷⁹湩楤慣潴獲慨慺摲洠歡牥ⱳ漠橢捥⁴慭敫獲Ⱙ㠠ⴰ〱‰浣栠楥桧愠潢敶朠潲湵敬敶ⱬ瀠楡瑮摥戠慬正愠摮眠楨整椠㔱挠楷敤猠牴灩ⱳ映瑩整楷桴㠠砰〱洰敲瑣湡畧慬牯㜠洵楤楣捲汵牡爠晥敬瑣牯獩摥瀠湡汥瑡琠敨琠灯戠牵敩牯瀠敲獳摥椠瑮桴牧畯摮愠摮挠湯潦浲湩潴䤠䍒㨠㜠‹攠瑣⸮挬浯汰瑥獡瀠牥䴠副♔⁈灳捥晩捩瑡潩潎㠮㘰†††ਠ畊据楴湯䄠⁴浫†㜠㘯☠ㄠ⼰‸††††††††††††††^ŽƘơŴЈ倀楡瑮湩䍃猠牵慦散眠瑩湯潣瑡漠牰浩湡睴潣瑡景猠湹桴瑥捩攠慮敭慰湩⁴景愠灰潲敶畱污瑩⁹湡潣潬牵椠据畬楤杮琠牨畯桧猠牣灡湩Ⱨ挠敬湡爠浥癯污漠楤瑲攠捴挠浯汰瑥潣灭祬湩楷桴猠慴摮牡灳捥晩慩瑣潩獮愠摮愠楤敲瑣摥戠⁹桴湥楧敮牥湩档牡敧††䨊湵瑣潩瑁欠†⼷‶…〱㠯††††††††††††††††††††††††††††††††††††††††匠ࠀԁ␀㘀ԁᘀ楍潮牂摩敧愠⁴浫㜠㘯䈀硯䌠汵敶瑲愠⁴浫㜠㘯ȃ؈匀灵汰楹杮愠摮䘠硩湩景匠汯牡删䑅圯䥈䕔䈯啌⁅䕌⁄求湩敫獲眠瑩′潎景㐠搢慩㌠浭琠楨正䌠湡楴敬敶⁌祴数瀠汯ⱥ㐠潎景㌠•楤⸲洵桴捩摁慶据潰敬〬丠獯漠敒⽤桷瑩⽥求敵䠠杩牦煥敵据⁹汦獡楨杮氠杩瑨″敳⁴‶潎景㌠〰浭搠慩删摥戠楬歮牥氠杩瑨㘬潎䕌⁄敄楬慮潴獲删摥圯楨整䈯畬ⱥ串獯漠楨桧映敲畱湥祣挠物畣瑩戠硯㐬潎景ㄠ〰䡁䔠䥘䕄匠䙍戠瑡整祲眠瑩慢瑴牥⁹潢⁸湡慰敮瑳畲瑣牵慥档㈠渠獯††ਠ畊据楴湯䄠⁴浫†㜠㘯☠ㄠ⼰‸††††††††††††††††††††††††††††††††††††††††EƒƖƗƳDžǠ̈匀灵汰⁹湡牥捥楴湯漠洷映敲瑳湡楤杮搠畯汢牁牂捡敫⁴‸楳敤捯潴潧慮汬⁹潣瑮湩畯汳⁹慴数敲瑳畲瑣摥瀠汯楷桴戠獡汰瑡景猠穩㔲‰⁸㔲‰⁸㈱浭愠数卉㠠㔷眠瑩潦汬睯湩灳捥晩捩瑡潩䈊瑯潴潰敬搠慩ⴠㄠ〴浭吊灯瀠汯楄〷浭吊楨正敮獳漠潰敬ⴠ㌠浭吊敨瀠汯桳畯摬戠潨⁴楤⁰慧癬湡穩摥挠湯楦浲湩潴䈠卅⁎卉⁏㐱ㄶ眠瑩桴捩湫獥景㘠‵楍牣湯䠊杩浨獡⁴㘱楷桴㠠丠獯ㄠ〵⁗䕌⁄楦瑴湩੧湉汣摵湩潦湵慤楴湯†䨊湵瑣潩瑁欠†⼷‶…〱㠯†††††††††††††⼠ꨀԁ턀㜀ࠁ潃獮牴捵楴湯漠楍潮牂摩敧愠⁴档†㐷〸䐠獩慭瑮楬杮琠敨攠楸瑳湩慐慲数⁴慷汬漠敶畃癬牥⁴湡楤灳獯桴敤潭楬桳摥洠瑡牥慩湩汣摵湩污瑯敨湩楣敤瑮污挠慨杲獥攠捴楷桴愠氠晩⁴灵潴㌠湡敬摡甠瑰‱浫愠数灳捥晩捩瑡潩湡獡瀠牥搠物捥楴湯景䐠灥牡浴湥慴景楦散獲映牯䐠獩慭瑮楬杮漠牃獡慂牲敩rက⤀Ԁ尀ᬀԁ椀ࠂ慅瑲睨牯硥慣慶楴湯椠污汣獡敳景猠楯硥散瑰栠牡潲正爠煥極楲杮戠慬瑳湩湡敤潰楳楴杮漠慢歮眠瑩污敬摡湡楬瑦獡瀠牥匠㉓䈰湩汣摵湩潣瑳漠污慬潢牵煥極浰湥獴愠摮愠汬椠据摩湥慴档牡敧畳档愠慢楬杮漠牵眠瑡牥牰癯摩湩湡慭湩慴湩湩敮散獳牡⁹潣晦牥慤獭桳敥楴杮桳牯湩牢捡湩湡桴楥畳獢煥敵瑮爠浥癯污敲潭慶景愠汬氠杯ⱳ猠畴灭ⱳ朠畲獢愠摮漠桴牥搠汥瑥牥潩獵洠瑡整湡扯瑳畲瑣潩獮牴浩業杮戠瑯潴景攠捸癡瑡潩慢正楦汬湩Ⱨ愠摮挠敬牡湩桴楳整愠摮搠獩潰慳景愠汬猠牵汰獵洠瑡牥慩獬攠捴Ⱞ挠浯汰瑥獡瀠牥爠汥癥湡⁴瑳湡慤摲猠数楣楦慣楴湯映牯䐠䕒卓义⁇䡔⁅䕂⁄偕吠⁏䥓䱌䰠噅䱅㴮䔀Ԃ�ࠂ慅瑲睨牯硥慣慶楴湯椠愠汬挠慬獳獥漠潳汩攠捸灥⁴潳瑦搠獥湩整牧瑡摥爠捯硥散瑰䬠湡慫 匠景⁴楤楳瑮来慲整潲正渠瑯爠煥極楲杮戠慬瑳湩愠摮栠牡潲正爠煥極楲杮戠慬瑳湩湡敤潰楳楴杮漠慢歮眠瑩污敬摡湡楬瑦獡瀠牥匠㉓䈰湩汣摵湩潣瑳漠污慬潢牵煥極浰湥獴愠摮愠汬椠据摩湥慴档牡敧畳档愠慢楬杮漠牵眠瑡牥牰癯摩湩湡慭湩慴湩湩敮散獳牡⁹潣晦牥慤獭桳敥楴杮桳牯湩牢捡湩湡桴楥畳獢煥敵瑮爠浥癯污敲潭慶景愠汬氠杯ⱳ猠畴灭ⱳ朠畲獢愠摮漠桴牥搠汥瑥牥潩獵洠瑡整湡扯瑳畲瑣潩獮牴浩業杮戠瑯潴景攠捸癡瑡潩慢正楦汬湩Ⱨ愠摮挠敬牡湩桴楳整愠摮搠獩潰慳景愠汬猠牵汰獵洠瑡牥慩獬攠捴Ⱞ挠浯汰瑥獡瀠牥爠汥癥湡⁴瑳湡慤摲猠数楣楦慣楴湯映牯䘠問䑎呁佉⁎䙏䄠啂䵔久協䥐剅⁓乁⁄䥗䝎⹓唊瑰洲䠠楥桧畴ꐀԂ∀灕潴㈠效杩瑨†潆敒慴湩湩慷汬ǴȈ倀慬湩挠浥湥⁴潣据敲整漠牧摡ㅍ‵潎業慮楍⁸㨱㨲‴獵湩〴浭䤠卓䠠䝂洠瑥污椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污潴猠瑩湡散敭瑮愠⁴楳整椠据畬楤杮挠獯⁴景映牯睭牯Ⱬ猠景⁴慷整Ⱳ慬潢牵挠慨杲獥映牯洠硩湩Ⱨ琠慲獮潰瑲湩Ⱨ氠祡湩湡畣楲杮挠湯牣瑥ⱥ眠牯楫杮愠⁴敤瑰獨听潯獬愠摮倠慬瑮湡湩楣敤瑮污挠慨杲獥猠捵獡洠楡瑮楡楮杮漠牰瑯捥楴敶戠湵獤潣晦牥慤獭桳牯湩Ⱨ猠牴瑵楴杮攠捴※潣灭敬整愠数敲敬慶瑮猠慴摮牡灳捥晩捩瑡潩潦䅂䕓䌠問卒⁅但⁒但乕䅄䥔乏传⁆䉁呕䕍呎䄠䑎圠义⁇䅗䱌䴮븀ԁༀ潆潂⁸畃癬牥ቴ潆敒慴湩湩慷汬ǾȈ嘀扩慲整䌠浥湥⁴潃据敲整漠牧摡㉍‰潎業慮楍⁸獵湩〴浭䤠卓猠穩䉈⁇牧摡摥洠瑥污椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污潴猠瑩湩汣摵湩潣瑳漠散敭瑮†瑡猠瑩椠据畬楤杮挠獯⁴景映牯睭牯Ⱬ猠景⁴慷整Ⱳ氠扡畯档牡敧潦業楸杮牴湡灳牯楴杮慬楹杮†湡畣楲杮挠湯牣瑥潷歲湩瑡搠灥桴潴汯湡汰湡獴愠摮洠楡瑮楡楮杮漠牰瑯捥楴敶戠湵獤潣晦牥慤獭桳牯湩Ⱨ猠牴瑵楴杮攠捴Ⱞ挠浯汰瑥獡瀠牥爠汥癥湡⁴瑳湡慤摲猠数楣楦慣楴湯ⱳ映牯䘠住䥔䝎⁓䙏䄠啂䵔久ⱔ倠䕉卒䄠䑎圠义升䈠䱅坏匠䱉⁌䕌䕖⹌㌠였ԁ︀ࠁ楖牢瑡摥†敃敭瑮䌠湯牣瑥景朠慲敤䴠〲丠浯湩污䴠硩甠楳杮㐠洰卉⁓楳敺䠠䝂朠慲敤敭慴湩汣摵湩潣瑳愠摮挠湯敶慹据景愠汬洠瑡牥慩獬琠楳整椠据畬楤杮挠獯⁴景挠浥湥⁴愠⁴楳整†湩汣摵湩潣瑳漠潦浲潷歲潳瑦眠瑡牥慬潢牵挠慨杲獥映牯洠硩湩Ⱨ琠慲獮潰瑲湩Ⱨ氠祡湩愠摮挠牵湩潣据敲整Ⱐ眠牯楫杮愠⁴敤瑰獨Ⱐ琠潯獬愠摮瀠慬瑮湡慭湩慴湩湩景瀠潲整瑣癩畢摮ⱳ挠景敦摲浡ⱳ猠潨楲杮瑳畲瑴湩瑥潣灭敬整愠数敲敬慶瑮猠慴摮牡灳捥晩捩瑡潩獮潦但呏义升传⁆䉁呕䕍呎䥐剅⁓乁⁄䥗䝎⁓䉁噏⁅䥓䱌䰠噅䱅였ԁࠁ楖牢瑡摥†敒湩潦捲摥䌠浥湥⁴潃据敲整漠牧摡㍍‰敤楳湧洠硩†獵湩䤠卓猠穩䉈⁇牧摡摥洠瑥污椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污潴猠瑩湩汣摵湩潣瑳漠散敭瑮†瑡猠瑩椠据畬楤杮挠獯⁴景映牯睭牯Ⱬ猠景⁴慷整Ⱳ氠扡畯档牡敧潦業楸杮牴湡灳牯楴杮慬楹杮†湡畣楲杮挠湯牣瑥潷歲湩瑡搠灥桴潴汯湡汰湡獴椠据畬楤杮愠汬漠桴牥椠据摩湥慴档牡敧瑥㭣挠浯汰瑥獡瀠牥爠汥癥湡⁴瑳湡慤摲猠数楣楦慣楴湯ⱳ映牯䐠剉⁔䅗䱌䌠䵕䈠䑅䈠佌䭃传䕖⁒䉁呕䕍呎⁓乁⁄䕂⁄䱂䍏⁋噏剅倠䕉卒㸮꼀ԁ瘀ࠁ牐癯摩湩湡楦楸杮猠敥慰敧瀠灩獥漠〱洰楤倠䍖瀠灩獥漠敲畱物摥氠湥瑧獨映牯愠畢浴湥獴愠摮眠杮湩汣摵湩潣瑳愠摮挠湯敶慹据景愠汬洠瑡牥慩獬琠潷歲猠瑩ⱥ挠獯⁴湡慬潢牵映牯㤠〰浭搠慩敳業猭桰牥捩污戠捡楦汬愠牲湡敧敭瑮楷桴ㄠ〰浭猠穩牢歯湥朠慲楮整挠楨獰愠⁴桴数楲桰牥⁹湡慬潢牵挠慨杲獥映牯映硩湩Ⱨ攠捴Ⱞ潴搠慲湩漠桴慢正楦汬䤠⁎䡔⁅䉁呕䕍呎⁓乁⁄䥗䝎⹓;šÖ倀潲楶楤杮愠摮映硩湩剋䙁⁔䅐䕐⁒潦畦汬眠摩桴漠敳瑡湩景搠捥汳扡愠摮椠据畬楤杮挠獯⁴湡潣癮祥湡散琠潷歲楳整慬潢牵映牯映硩湩桴慳敭椠潣牲捥⁴潰楳楴湯愠摮愠汬漠桴牥椠据摩湥慴档牡敧瑥潣灭敬整뤮ࠁ楖牢瑡摥†敒湩潦捲摥䌠浥湥⁴潃据敲整漠牧摡㍍‰敄楳湧䴠硩†獵湩䤠卓猠穩䉈⁇牧摡摥洠瑥污椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污潴猠瑩湩汣摵湩潣瑳漠散敭瑮†瑡猠瑩椠据畬楤杮挠獯⁴景映牯睭牯Ⱬ猠景⁴慷整Ⱳ氠扡畯档牡敧潦業楸杮牴湡灳牯楴杮慬楹杮†湡畣楲杮挠湯牣瑥潷歲湩瑡搠灥桴潴汯湡汰湡獴椠据畬楤杮愠汬漠桴牥椠据摩湥慴档牡敧瑥㭣挠浯汰瑥獡瀠牥爠汥癥湡⁴瑳湡慤摲猠数楣楦慣楴湯ⱳ映牯䐠䍅⁋䱓䉁㸮ꨀԁ︀ࠁ牐癯摩湩楦瑬牥洠摥慩戠桥湩桴扡瑵敭瑮湡楷杮楷桴挠敬湡䤠䥉朠慲敤慭整楲污㔠洳潴㔠㘮浭琠〶洰桴捩湡眠汥潣灭捡整湩氠祡牥眠瑩浳污敬楳敺潴慷摲桴潳汩愠摮戠杩敧楳敺琠睯牡獤琠敨眠污湩汣摵湩潣瑳愠摮挠湯敶慹据潴眠牯楳整椠据畬楤杮†污慬潢牵湡瑯敨湩楣敤瑮污挠慨杲獥椠据畬楤杮栠物档牡敧潦潴汯湡汰湡獴攠灭潬敹瑥潦楦瑬牥洠摥慩愠数位呓猧⠠潒摡楗杮 灳捥晩捩瑡潩獮映牯删慯獤愠摮䈠楲杤獥∠䘠畯瑲敒楶楳湯䌠㌠㤰㌭㈭ㄭ″湡〳‵㐭㐭攠捴Ⱞ挠浯汰瑥5ŪȈ䘀汩楬杮戠桥湩扁瑵敭瑮湡楗杮楷桴挠敬湡朠楲瑴⁹牧癡汥椠据畬楤杮挠獯⁴湡潣癮祥湡散漠牧癡汥琠潷歲楳整慬楹杮慨摮楬杮挠慨杲獥愠摮映汩楬杮椠慬敹獲慴灭湩湵敤灯楴畭潭獩畴敲挠湯整瑮琠敧⁴桴慭楸畭敤獮瑩⁹湩汣摵湩慷整楲杮楷桴愠汬氠慥獤映牯眠瑡牥愠摮愠汬漠桴牥椠据摩湥慴档牡敧瑥Ᵽ挠浯汰瑥潦䥆䱌义⁇䕂䥈䑎吠䕈䄠啂䵔久協䄠䑎圠义升㬮䌀ԁ휀ࠀ牐癯摩湩湡楦楸杮倠䍖䔠偘乁䥓乏䨠䥏呎椠敢睴敥敤正猠慬獢漠敶扡瑵敭瑮愠摮瀠敩獡猠潨湷椠桴牤睡湩湩汣摵湩潣瑳愠摮挠湯敶慹据景攠灸湡楳湯樠楯瑮湩汣摵湩桳污浩牡瀠摡愠摮樠楯瑮猠慥慬瑮攠捴潣灭敬整嘮혀Ԁࠁ畓灰祬愠摮映扡楲慣楴湯漠敆㔭〰猠整汥爠煥極敲潦污䍒⁃瑩浥景眠牯獫椠癮汯敶湩琠敨猠档摥汵潣瑳漠瑳敥瑡猠瑩慦牢捩瑡潩Ɱ慬潢牵挠慨杲獥映牯挠敬湡湩桴潲獤猠牴楡桧整楮杮畣瑴湩Ⱨ戠湥楤杮祴湩牧汩獬湩汣摵湩癯牥慬灰湩潴琠敨爠煥極敲敬杮桴眠敨敮敶敮散獳牡⁹湡汰捡湩桴敲湩潦捲浥湥⁴湩瀠獯瑩潩獡猠数楣楦摥椠桴牤睡湩獧湩汣摵湩潣瑳漠楢摮湩楷敲牰癯獩潩景猠慰散慢獲潣敶汢捯獫愠摮愠汬漠桴牥椠据摩湥慴档牡敧瑥Ᵽ潣灭敬整敆㔭〰朠慲敤'ǘNjȈ嘀扩慲整敃敭瑮䌠湯牣瑥ㅍ‵牧摡ⱥ丠浯湩污䴠硩ㄠ㈺㐺獵湩〴浭䤠卓栠牡牧湡瑩牢歯湥洠瑥污椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污潴猠瑩湡散敭瑮愠⁴楳整椠据畬楤杮挠獯⁴景映牯睭牯Ⱬ氠慥潦潳瑦眠瑡牥慬潢牵挠慨杲獥映牯洠硩湩牴湡灳牯楴杮慬楹杮湡畣楲杮挠湯牣瑥潷歲湩湩栠楥桧獴愠摮栠物档牡敧潦潴汯湡汰湡獴湡污瑯敨湩楣敤瑮污挠慨杲獥攠捴挠浯汰瑥獡瀠牥爠汥癥湡⁴灳捥晩捩瑡潩潦䅂䕓䌠問卒⁅䕂佌⁗偁剐䅏䡃匠䅌⹂7ƪūȈ嘀扩慲整敲湩潦捲摥挠浥湥⁴潣据敲整䴠〳搠獥杩業⁸獵湩卉⁓牧摡摥栠牡牧湡瑩牢歯湥洠瑥污椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污潴猠瑩湩汣摵湩散敭瑮愠⁴楳整椠据畬楤杮氠扡畯档牡敧潦業楸杮慬楹杮畣楲杮挠湯牣瑥ⱥ眠牯楫杮愠⁴敨杩瑨ⱳ栠物档牡敧潦潴汯湡汰湡獴湩汣摵湩污瑯敨湩楣敤瑮污挠慨杮獥攠捴Ⱞ挠浯汰瑥潦偁剐䅏䡃匠䅌⹂3ŜǏȈ嘀扩慲整敒湩潦捲摥䌠浥湥⁴潃据敲整䴠㐭ⰰ䜠慲敤敄楳湧䴠硩甠楳杮䤠卓猠穩慨摲朠慲楮整戠潲敫牧摡摥洠瑥污椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污潴猠瑩湩汣摵湩散敭瑮愠⁴楳整戠瑵攠捸畬楤杮挠獯⁴湡慦牢捩瑡潩景猠整汥湩汣摵湩慬潢牵挠慨杲獥映牯洠硩湩Ⱨ琠慲獮潰瑲湩Ⱨ氠祡湩Ⱨ愠摮挠牵湩潣据敲整潷歲湩瑡栠楥桧獴楨敲挠慨杲獥映牯琠潯獬愠摮瀠慬瑮ⱳ椠据畬楤杮愠汬漠桴牥椠据摩湥慴档牡敧瑥Ⱜ挠浯汰瑥潦䍒⁃剃十⁈䅂剒䕉卒传䕖⁒䕄䭃匠䅌⁂>ƬƦȈ嘀扩慲整敃敭瑮䌠湯牣瑥㉍‰牧摡ⱥ丠浯湩污䴠硩甠楳杮㐠洰卉⁓楳敺栠牡牧湡瑩牢歯湥朠慲敤敭慴湩汣摵湩潣瑳愠摮挠湯敶慹据景愠汬洠瑡牥慩獬琠楳整愠摮挠浥湥⁴瑡猠瑩湩汣摵湩慬潢牵挠慨杲獥映牯洠硩湩Ⱨ琠慲獮潰瑲湩Ⱨ氠祡湩Ⱨ愠摮挠牵湩潣据敲整潷歲湩瑡栠楥桧獴楨敲挠慨杲獥映牯琠潯獬愠摮瀠慬瑮ⱳ椠据畬楤杮愠汬漠桴牥椠据摩湥慴档牡敧ⱳ瑥挬浯汰瑥獡瀠牥猠慴摮牡灳捥晩捩瑡潩潦䍐⁃倠剁偁呅⁓噏剅圠义升〮贀ԁ⨀ࠁ畓灰祬愠摮映硩湩景䠠杩畑污瑩⁹景倠䍖瀠灩獥漠㔱洰楤䤠据畬楤杮挠獯⁴湡潣癮祥湡散漠楰数潴琠敨猠瑩湡楦楸杮椠潰楳楴湯琠牰灯牥朠慲敤愠摮氠癥汥湩汣摵湩慬潢牵挠慨杲獥映牯映硩湩湡湩汣摵湩污瑯敨湩楣敤瑮污挠慨杲獥攠捴挠浯汰瑥潦牰癯湩瑵汩瑩⁹敳癲捩獥椠潦瑯慰桴=˙Ј䌀湯瑳畲瑣潩景䈠硯挠汵敶瑲愠⁴浫㜠㠴‰䔠牡桴潷歲攠捸癡瑡潩湩†污汣獡敳景猠楯硥散瑰猠景⁴敤楳瑮来慲整潲正攠捸灥⁴態歮牡⼠†潓瑦搠獩湩整牧瑡摥爠捯潮⁴敲畱物湩汢獡楴杮†湡慨摲爠捯敲畱物湩汢獡楴杮愠摮搠灥獯瑩湩湯戠湡楷桴愠汬氠慥獤愠摮氠晩獴愠数卓〲ⱂ椠据畬楤杮挠獯⁴景愠汬氠扡畯Ⱳ攠畱灩敭瑮湡污湩楣敤瑮污挠慨杲獥猠捵獡戠污湩畯慷整Ⱳ瀠潲楶楤杮愠摮洠楡瑮楡楮杮渠捥獥慳祲挠景敦摲浡ⱳ猠敨瑥湩Ⱨ猠潨楲杮戠慲楣杮愠摮琠敨物猠扵敳畱湥⁴敲潭慶ⱬ爠浥癯污漠污潬獧瑳浵獰牧扵湡瑯敨敤敬整楲畯慭瑴牥愠摮漠獢牴捵楴湯ⱳ琠楲浭湩潢瑴浯漠硥慣慶楴湯戠捡晫汩楬杮湡汣慥楲杮琠敨猠瑩湡楤灳獯污漠污畳灲畬慭整楲污瑥潣灭敬整愠数敲敬慶瑮猠慴摮牡灳捥晩捩瑡潩潦戠硯挠汵敶瑲(µˍǏȈ嘀扩慲整敒湩潦捲摥䌠浥湥⁴潃据敲整漠牧摡㍍‰䐨獥杩業⥸甠楳杮㈠洰卉桓牡牢歯湥朠慲楮整洠瑥污椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污潴猠瑩湡潣瑳漠散敭瑮攠捸畬楤杮挠獯⁴湡慦牢捩瑡潩景猠整汥戠瑵椠据畬楤杮挠獯⁴景映牯潷歲慬潢牵挠慨杲獥映牯洠硩湩Ⱨ琠慲獮潰瑲湩Ⱨ氠祡湩湡畣楲杮挠湯牣瑥ⱥ眠牯楫杮愠⁴敨杩瑨ⱳ栠物档牡敧潦潴汯湡汰湡獴椠据畬楤杮愠汬漠桴牥椠据摩湥慴档牡敧瑥潣灭敬整映牯䈠獡汓扡楓敤圠污湁潔⁰汓扡>ƭŁȈ嘀扩慲整散敭瑮挠湯牣瑥㉍‰丨浯湩污洠硩 獵湩〴浭䤠卓猠穩慨摲戠潲敫牧湡瑩敭慴湩汣摵湩潣瑳愠摮挠湯敶慹据景愠汬洠瑡牥慩獬琠楳整椠据畬楤杮挠獯⁴湡慬潢牵挠慨杲獥映牯映牯睭牯Ⱬ挠湥整楲杮慬潢牵挠慨杲獥映牯†慬楹杮挠浯慰瑣湩Ⱨ挠牵湩污湩楣敤瑮污挠慨杲獥攠捴Ⱞ挠浯汰瑥潦楗杮眠污敂潬⁷牧畯摮氠癥汥6ĥłȈ嘀扩慲整散敭瑮挠湯牣瑥㉍‰丨浯湩污洠硩 獵湩〴浭䤠卓猠穩慨摲戠潲敫牧湡瑩敭慴湩汣摵湩潣瑳愠摮挠湯敶慹据景愠汬洠瑡牥慩獬琠楳整椠据畬楤杮挠獯⁴湡慬潢牵挠慨杲獥映牯映牯睭牯Ⱬ挠湥整楲杮慬潢牵挠慨杲獥映牯†慬楹杮挠浯慰瑣湩Ⱨ挠牵湩污湩楣敤瑮污挠慨杲獥攠捴Ⱞ挠浯汰瑥潦楗杮眠污䄠潢敶䜠潲湵慷汬央␀ԁⰀࠁ楖牢瑡摥挠浥湥⁴潣据敲整䴠〲⠠潎業慮業⥸甠楳杮㐠洰卉⁓楳敺栠牡牢歯湥朠慲楮整洠瑥污椠据畬楤杮挠獯⁴湡潣癮祥湡散漠污慭整楲污潴猠瑩湩汣摵湩潣瑳愠摮氠扡畯档牡敧潦潦浲潷歲散瑮牥湩Ⱨ氠扡畯档牡敧潦氠祡湩Ⱨ†潣灭捡楴杮畣楲杮愠汬椠据摩湥慴档牡敧瑥潣灭敬整映牯倠牡灡瑥?ĥĹȈ嘀扩慲整散敭瑮挠湯牣瑥㉍‰丨浯湩污洠硩 獵湩〴浭䤠卓猠穩慨摲戠潲敫牧湡瑩敭慴湩汣摵湩潣瑳愠摮挠湯敶慹据景愠汬洠瑡牥慩獬琠楳整椠据畬楤杮挠獯⁴湡慬潢牵挠慨杲獥映牯映牯睭牯Ⱬ挠湥整楲杮慬潢牵挠慨杲獥映牯†慬楹杮挠浯慰瑣湩Ⱨ挠牵湩污湩楣敤瑮污挠慨杲獥攠捴Ⱞ挠浯汰瑥潦楗杮眠污潆湵慤楴湯+ĥŀȈ嘀扩慲整散敭瑮挠湯牣瑥㉍‰丨浯湩污洠硩 獵湩〴浭䤠卓猠穩慨摲戠潲敫牧湡瑩敭慴湩汣摵湩潣瑳愠摮挠湯敶慹据景愠汬洠瑡牥慩獬琠楳整椠据畬楤杮挠獯⁴湡慬潢牵挠慨杲獥映牯映牯睭牯Ⱬ挠湥整楲杮慬潢牵挠慨杲獥映牯†慬楹杮挠浯慰瑣湩Ⱨ挠牵湩污湩楣敤瑮污挠慨杲獥攠捴Ⱞ挠浯汰瑥潦楗杮眠污敂潬⁷潧湵敬敶⭬␀ԁ䄀ࠁ楖牢瑡摥挠浥湥⁴潣据敲整䴠〲⠠潎業慮
湩〴浭䤠卓猠穩慨摲戠潲敫牧湡瑩敭慴湩汣uding cost and conveyance of all materials to site including cost and labour charges for formwork, centering, labour charges for laying, compacting, curing all incidental charges etc., complete for Wing wall above gound level.+$%äProviding and erecting single sided Double Guard Metal Beam Crash Barrier System 1.70m high, comprising of 3mm thick wall "W" beams and spacer channels be made by cold roll forming using HR conform to IS 5986 Fe 410/360 and dip galvanized having Zinc Mass of 550 gms/Sqm, mimimum 950mm above road/ground level fixed on ISMC series channel vertical post 150x75x5 mm spaced 2m centre to centre 312mmX83mm flange width 3mm thick, 4318mm long post directly embedded in the concrete (M15) pit size 350x350x800mm for a depth of 750mm below ground. All fixing bolts and nuts hot dip galvanized confirming to IS:1367 clause 4.60 all complete as per Technical Specifications and as directed by the Engineer-in-charge. Junction At km 7/6 JÈÞ2m - 3m Height
Calculation of SubTotal, GST and Total Amount carried out by system automatically Basic cost of value put to tender as per estimate
Add GST at 18%
Total Value put to Tender
Negotiated Percentage
Final Negotiated Value
Add GST at 18% of Final Negotiated Value
Total Value of Contract Including 18% of GST
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.21 MB
BOQ_766835.xls
BOQ • 0.39 MB
PQsivagangaiJunction.pdf
Tender Documents • 0.36 MB
TenderdocumentSivajunction.pdf
Tender Documents • 0.61 MB
Drawings.rar
Additional Documents • 0.39 MB
Download all tender documents and submit your bid