| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹43.2 LAccepted-AOC | ₹43.2 L Quoted ₹50.6 L | L1 | Accepted-AOC L1 |
| 2 | L2₹53.7 LRejected-AOC | ₹53.7 L | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | S.S.SOUNDAR ENTERPRISES L2 | S.GOPALA KRISHNAN CONTRACTOR L1 |
|---|---|---|---|---|---|
| 1.00 | Charges for clearing the spillage coal on walkways, return side under belt to the entire length of the Conveyor deck sheet, head end, tail end of the Conveyor-13A,14,15 and 16 including hire charges for T&Ps cost of consumables, etc., complete. | 244 | ACTVY | 39,04,000 ₹46.1 L | 36,35,600 ₹42.9 L |
| 2.00 | Charges for assisting work for providing belt joint in Conveyors-13A,14,15, and 16,including arresting the belt by providing clamps, lifting the counter weight, dismantling the idlers and idler frames and skirt board assembly and refixing the same after vulcanizing the joint, including T&P hire charges and cost of consumables etc., complete. | 8 | No. | 4,96,000 ₹5.9 L | 4,80,000 ₹5.7 L |
| 3.00 | Charges for assisting work for pulley lagging works in Conveyors-13A,14,15 and 16 including arresting the conveyor belt, lifting the counter weight and normalizing the system after pulley lagging trial operation including T&P hire charges and cost of consumables, safety appliances etc., complete | 6 | No. | 3,72,000 ₹4.4 L | 3,60,000 ₹4.2 L |
| 4.00 | Charges for overhauling and inspection of gear coupling in Conveyors-13A,14,15 and 16 including arresting the conveyor belt, lifting the counter weight, dismantling the gear coupling, removal of old grease, cleaning the gear teeth, arranging for inspection, packing the new grease and normalizing the system, trial operation including cost of consumables, safety appliances and T&P hire charges etc., complete. | 6 | Operation | 4,38,000 ₹5.2 L | 4,29,000 ₹5.1 L |
| 5.00 | Charges for overhauling and inspection of pulley bearings and replacement if necessary in head pulley/head snub pulley/ drive pulley/ tail pulleys/take up pulleys/ bend pulleys in Conveyor-13A,14,15, and 16 including arresting the conveyor belt, lifting the counterweight and normalizing the system after bearing overhauling, trial operation including cost of consumables and T&P hire charges etc., complete. | 2 | Operation | 1,64,000 ₹1.9 L | 1,60,000 ₹1.9 L |
Tender Value
Refer Docs
EMD Value
₹35,800
Closing Date
2 Jan 2026, 2:00 pmClosed
Chief Engineer/TTPS
O/o CE/TTPS
ECHP-I- Attending Breakdown, Preventive mechanical maintenance works in Conveyor-13A, 14,15 16.
2025_EB_633244_1
CE/SE/MI/TTPS/40/2026-2027
Open Tender
Miscellaneous Works
365 days
TTPS
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹35,800
Yes
24 Mar 2026
17 Dec 2025
3 Jan 2026
17 Dec 2025
2 Jan 2026
17 Dec 2025
Charges for clearing the spillage coal on walkways, return side under belt to the entire length of the Conveyor deck sheet, head end, tail end of the Conveyor-13A,14,15 and 16 including hire charges for T&Ps cost of consumables, etc., complete.
Charges for assisting work for providing belt joint in Conveyors-13A,14,15, and 16,including arresting the belt by providing clamps, lifting the counter weight, dismantling the idlers and idler frames and skirt board assembly and refixing the same after vulcanizing the joint, including T&P hire charges and cost of consumables etc., complete.
Charges for assisting work for pulley lagging works in Conveyors-13A,14,15 and 16 including arresting the conveyor belt, lifting the counter weight and normalizing the system after pulley lagging trial operation including T&P hire charges and cost of consumables, safety appliances etc., complete
Charges for overhauling and inspection of gear coupling in Conveyors-13A,14,15 and 16 including arresting the conveyor belt, lifting the counter weight, dismantling the gear coupling, removal of old grease, cleaning the gear teeth, arranging for inspection, packing the new grease and normalizing the system, trial operation including cost of consumables, safety appliances and T&P hire charges etc., complete.
Charges for overhauling and inspection of pulley bearings and replacement if necessary in head pulley/head snub pulley/ drive pulley/ tail pulleys/take up pulleys/ bend pulleys in Conveyor-13A,14,15, and 16 including arresting the conveyor belt, lifting the counterweight and normalizing the system after bearing overhauling, trial operation including cost of consumables and T&P hire charges etc., complete.
S.S.SOUNDAR ENTERPRISES (BID ID -1541319)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.30 MB
BOQ_757613.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid