| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹21.1 CrAccepted-AOC 2 HOUSE NO 214 FRIENDS COLONY RAJIV NAGAR MANDI DABWALI 125104 | MANDI DABWALI | SIRSA | HARYANA | 125104 | ₹21.1 Cr | 1 | Accepted-AOC DUE TO LOWER SIDE |
| 2 | 2₹21.2 CrRejected-AOC HSVP PANCHKULA | PANCHKULA | HARYANA | 133301 | ₹21.2 Cr | 2 | Rejected-AOC DUE TO HIGHER SIDE |
| 3 | 3₹21.8 CrRejected-AOC | ₹21.8 Cr | 3 | Rejected-AOC DUE TO HIGHER SIDE |
Tender Value
₹22.4 Cr
EMD Value
₹44.8 L
Closing Date
7 Sept 2022, 2:00 pmClosed
EXECUTIVE ENGINEER
EXECUTIVE ENGINEER PUBLIC HEALTH ENGINEERING DIVISION NO.2 HISAR
Design Const Testing Commissioning Of 8point50mld Plc Scada Based WTP CWT At Mt WW Including Civil Electrical Mechanical Instrumentation Works Complete In All Respect Const Of Inlet Channel Raw Water Pumping Station SS Tanks PC BWall CC Roads At Newl
2022_HRY_236164_1
14155 DT 23.08.2022
Open Tender
Civil Works
14 days
HISAR
Please refer Tender documents.
3 documents required · 3 mandatory
₹20,000
₹44.8 L
Yes
11 Oct 2022
25 Aug 2022
7 Sept 2022
25 Aug 2022
7 Sept 2022
25 Aug 2022
Amount
Designing , Testing , Commissioning of fully automated PLC & SCADA controlled Water Treatment Plant of 8.50 MLD capacity at MT Water Works, Barwala Town capable of delivering potable drinking water as per CPHEEO manual/BIS specifications under all climatic conditions, all other mechanical, electrical, instrumentation, all types of valves, installationetc., inlet chamber, inlet channel, parshall flume, Alum dozing, Flash mixer, Clari-flocoulator, Rapid Sand Filters, pipe gallery, overhead reservoir for back wash including pump sets and PLC/SCADA controlled electric control panels, waste water recirculation/Supernatant liquid tank, sludgeholding sump/sludge pit, filter press/volute press including pump sets and PLC/SCADA controlled filter press/volute press room (30sqm) electric control panel, DI pipes, DI specials, manhole covers, air scouring equipment, chemical house G+1 storeyed (260sqm) including gaseous chlorination equipment, laboratory equipment, RCC retaining walls/Breastwalls, thrust block, Site development, Land retaining scaping and arrangement of flow measurement with PLC & SCADA based automation of WTP, Interconnecting Structures/piping from inlet chamber to sand filters to CWT to C.W. suction well earthing, walkways with SS-304 railing complete in all respects as per DNIT.including O&M 12 month DLP afeter trial run of 3 months and 5 year thereafter.
Supplying, erection, testing and commissioning of Wet installed submerged centrifuga portable Horizontal pump sets (single stage) with base frame coupled with motor of 960/1500/3000 rpm, Volute Casing type with the Impeller mounted directly onto the Extended Solid Motor Shaft (without any couplings) as per Technical Specifications o Wet Installed, Submerged Centrifugal Pump Sets(as per Schedule-4 of DNIT )complete with lowering pipes of suitable dia., submersible cables of suitable size from panel to motor accessories, base frame and all fittings for pumps. (For Raw Water Pumping) including O&M 12 month DLP afeter trial run of 3 months and 5 year thereafter RAW WATER PUMPING SET PROPOSED PUMPING STATION FOR WATER WORKS ATNEW ACQUIRED LAND. 9100 LPM, 40BHP, 12m HEAD
PROPOSED PUMPING STATION FOR MT WORKS. 11000 LPM, 50BHP, 12m HEAD
Supplying, erection, testing and commissioning of Wet installed submerged centrifuga portable Horizontal pump sets (single stage) with base frame coupled with motor of 960/1500/3000 rpm, Volute Casing type with the Impeller mounted directly onto the Extended Solid Motor Shaft (without any couplings) as per Technical Specifications o Wet Installed, Submerged Centrifugal Pump Sets(as per Schedule-4 of DNIT) complete with lowering pipes accessories, base frame and fittings for pumps. (For Clear Water Pumping) including O&M 12 month DLP afeter trial run of 3 months and 5 year thereafter CLEAR WATER PUMPING SET Poposed Pumping Station for MT works 8300 LPM,140 BHP, 45 m Head ( Replacement)
AT WATER WORKS TO FILL BOOSTING STATIONS 5700 LPM, 70BHP, 30m HEAD
AT BOOSTING STATION NO.2 2200 LPM, 30 BHP, 35 m Head ( Replacement)
AT BOOSTING STATION NO.8 1250 LPM, 17.50BHP, 35m HEAD
Supplying, erection, testing & commissioning of PLC/SCADA controlled fully automatic electric control panel board for Wet Installed, Submerged Centrifugal Raw Water Pumping Set consisting of CRCA sheet of thickness 2mm duly powder coated box type floor mounted made of angle Frame containing 1 no. fullyautomatic air brake starter suitable for Motor of the followingcapacity, Main switch, Isolating switch of suitable range with HRC fuses, 1 no. digital volt meter (0 to 500 volts), 1 No. digital Amp. Meter of O to 100 amp., Current Transformers (CT's), indicating lamps, capacitor of suitable capacity and 1 no. single phase preventers with the timer switch including wiring in panel board and suitable wiring in Electric Control Panel Board from electric energymeter complete in al respect including suitable capacity MCB, Power Capacitor, hour meter, earth leakage relay, moisture controller, winding protection relay, digital MFM meter, Change overswitch of suitable capacity etc. as per site requirement complete inall respects (as per Schedule- 4 of DNIT) including O&M 12 month DLP afeter trial run of 3 months and 5 year thereafter. RAW WATER PUMPING SET PROPOSED PUMPING STATION FOR WATER WORKS ATNEW ACQUIRED LAND. 9100 LPM, 40BHP, 15m HEAD
PROPOSED PUMPING STATION FOR MT WORKS. 11000 LPM, 50BHP, 15m HEAD
Supplying, erection, testing & commissioning of PLC/SCADA controlled fully automatic electric control panel board for Wet Installed, Submerged Centrifugal Pump Clear Water Pumping Setconsisting of CRCA sheet of thickness 2mm duly powder coated box type floor mounted made of angle Frame containing 1 no. fullyautomatic ATS starter suitable for Motor of the following capacity,Main switch, Isolating switch of suitable range with HRC fuses, 1 no. digital volt meter (0 to 500 volts), 1 No. digital Amp. Meter of Oto 100 amp. Current Transformers (CT's), indicating lamps, capacitor of suitable capacity and 1 no single phase preventers with the timer switch including wiring in panel board and suit able wiring in Electric Control Panel Board from electric energy meter complete in all respec including suitable capacity MCB, Power Capacitor, hour meter, earth leakage relay moisture controller, winding protection relay, digital MFM meter, Change overswitch o suitable capacity etc. as per site requirement complete inall respects. (as per Schedule- 4 of DNIT) including O&M 12 month DLP afeter trial run of 3 months and 5 year thereafter. CLEAR WATER PUMPING SET PROPOSED PUMPING STATION FOR MT WORKS 8300 LPM, 140BHP, 45m HEAD
AT WATER WORKS TO FILL BOOSTING STATIONS 5700 LPM, 70BHP, 30m HEAD
Supplying, erection, testing & commissioning of PLC/SCADA controlled fully automatic electric control panel board for Wet Installed, Submerged Centrifugal Clear Water Pumping Set consisting of CRCA sheet of thickness 2mm duly powder coated box type floor mounted made of angle Frame containing 1 no. fullyautomatic air brake starter suitable for Motor of the followingcapacity, Main switch, Isolating switch of suitable range with HRC fuses, 1 no. digital volt meter (0 to 500 volts), 1 No. digital Amp. Meter of O to 100 amp., Current Transformers (CT's), indicating lamps, capacitor of suitable capacity and 1 no. single phase preventers with the timer switch including wiring in panel board and suitable wiring in Electric Control Panel Board from electric energymeter complete in al respect including suitable capacity MCB, Power Capacitor, hour meter, earth leakage relay, moisture controller, winding protection relay, digital MFM meter, change overswitch of suitable capacity etc. as per site requirement complete inall respects.(as per Schedule- 4 of DNIT). including O&M 12 month DLP afeter trial run of 3 months and 5 year thereafter. CLEAR WATER PUMPING SET AT BOOSTING STATION NO.2 2200 LPM, 30BHP, 35m HEAD
AT BOOSTING STATION NO.8 1250 LPM, 20BHP, 35m HEAD
Supply erection, testing & commissioning of HT metering panel 11KV consisting of One No. Electric Trivector meter 3 phase 4 wire 0.5 class of accuracy on KW hour point basis complete with HT CTs of 20/5 amp 15 VA burden and class of 0.5 accuracy and HT PT 11000 V. 15 VA burden and class of 0.5 including metering cubical complete in all respects as per site requirement. including O&M 12 month DLP afeter trial run of 3 months and 5 year thereafter. For Raw Water Pump House (New Acquired Land) & MT WaterWorks
Bidder Name
Amount
ashok kumar jain cont.(GSTN-06ABCFA7958G1ZB)
ROHTASH KUMAR CONTRACTOR(GSTN-NA)
M/s Sourabh Construction Pvt. Ltd.(GSTN-NA)
ROHTASH KUMAR CONTRACTOR
ashok kumar jain cont.
ashok kumar jain cont.
M/s Sourabh Construction Pvt. Ltd.
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid