Tender Value
₹5.6 Cr
EMD Value
₹11.2 L
Closing Date
22 Apr 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
Above/Below/Par
TRD
16 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or V whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
Note: In case, date of tender inviting is on or after date of statutory deadline for audit of balance sheet of previous FY (i.e. 30th Sept or as further extended for this FY), audited balance sheet of 4th previous year shall not be considered unless concerned CA certifies that balance sheet is not audited yet as on date of invitation of this tender.
Contractor/Firm should have Valid Electrical contractor license.
5 conditions · 2 needing a document upload
The tenderer shall clearly specify whether the tender is submitted on his own (Proprietary Firm) or on behalf of a Partnership Firm / Company / Joint Venture (JV) / Registered Society / Registered Trust / Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc. The tenderer shall submit all relevant documents as detailed in para 14 & 18.10 of Tender Form (Second Sheet) of Part I of GCC work-2022.
The tenderer whether sole proprietor / a company or a partnership firm / registered society / registered trust / HUF / LLP etc if they want to act through agent or individual partner(s), should submit along with the tender, a copy of power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, specifically authorizing him/them to sign the tender, submit the tender and further to deal with the Tender/ Contract up to the stage of signing the agreement except in case where such specific person is authorized for above purposes through a provision made in the partnership deed / Memorandum of Understanding / Article of Association /Board resolution, failing which tender shall be summarily rejected. (Para no. 15 of Tender Form (Second Sheet) of Part I of GCC-2022).
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Contractor should quote only the above/below percentage on estimated value, in the space provided at web portal for the purpose & nowhere else. Financial & Technical conditions quoted at any place other than prescribed space shall not be entertained while evaluating the offer.
Tenderer are required to go through the documents attached along with the tender and submit their bids accordingly.
TRD modification work in c/w Provision of expansion of traffic facilities work & Distributed Electronic Interlocking at Sri Ganganagar station and Shifting of cross over & provision of dead end at Pilibanga for safe movement of trains over Bikaner Division.
47-TRDGSBKN-ETENDER25-26
47-TRDGSBKN-ETENDER25-26
Open
Works - General
18 Months
Bikaner, Rajasthan
₹0
₹11.2 L
22 Apr 2026
28 Mar 2026
8 Apr 2026
29 items across 1 schedule · ₹34,50,081.5 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | NS8: Erection of single cantilever assembly complete with insulator for conventional OHE | Numbers | 160.00 | 2,745.38 | 4,39,260.8 |
| 2 | NS9: Adjustment of OHE turnout (2 turnouts to be considered as 1 no.) / x-overs. | Numbers | 7.00 | 19,779.93 | 1,38,459.51 |
| 3 | NS10: Adjustment insulated /uninsulated overlap. | Numbers | 2.00 | 1,340.66 | 2,681.32 |
| 4 | NS11: Transfer of OHE from one support to another and adjustment of droppers / slewing of OHE. | Each Span | 94.00 | 6,123.15 | 5,75,576.1 |
| 5 | NS13: Re-droppering of spans including making profiling and adjustment of height & adjustment of encumbrance including removal of kink. | Each Span | 94.00 | 1,871.51 | 1,75,921.94 |
| 6 | NS15: Erection of three Pulley type Regulating equipment (conventional type) with complete assembly. | Numbers | 14.00 | 10,655.01 | 1,49,170.14 |
| 7 | NS17: Erection of materials for termination of single/double conductor with insulator of OHE. | Numbers | 14.00 | 1,800.42 | 25,205.88 |
| 8 | NS19: Erection of Fixed Termination Anchor (FTA) standard arrangement with insulator. | Numbers | 5.00 | 2,468.78 | 12,343.9 |
| 9 | NS23: Erection of section insulator assembly incl. core and cut-in insulator. | Numbers | 6.00 | 7,733.36 | 46,400.16 |
| 10 | NS26: Erection (with insulator) of 25 kV single pole isolator without earth contact assembly and with jumpering arrangement. | Numbers | 6.00 | 7,519.74 | 45,118.44 |
| 11 | NS30: Erection of 25kV post insulator and all components such as pedestal cap, clamps, stud bolts etc. to support jumper/busbar. | Numbers | 26.00 | 395.29 | 10,277.54 |
| 12 | NS32: Erection of 18mm copper solid bus bar. | Metre | 90.00 | 602.12 | 54,190.8 |
| 13 | NS34: Erection of 9 tonne porcelain cut in insulator (including insulator testing). | Numbers | 12.00 | 1,274.67 | 15,296.04 |
| 14 | NS36: Erection of 130 sqmm stranded cadmium copper wire with fittings. | Metre | 700.00 | 123.77 | 86,639 |
| 15 | NS38: Erection of Anti creep arrangement with insulator. | Numbers | 6.00 | 4,240.68 | 25,444.08 |
| 16 | NS40: Erection of copper jumpers ATJ/C/F type. | Numbers | 32.00 | 328.22 | 10,503.04 |
| 17 | NS42: Erection of 'G' Jumpers. | Numbers | 7.00 | 2,458.24 | 17,207.68 |
| 18 | NS43: Splicing and extension of anchor OHE. | Numbers | 6.00 | 8,952.57 | 53,715.42 |
| 19 | NS45: Erection of overhead equipment including catenary and contact wire. | Per Track KM | 4.50 | 25,269.86 | 1,13,714.37 |
| 20 | NS64: Dismantling & removal of mast, portal, TTC & other small part steel. | MT | 65.50 | 10,473.45 | 6,86,010.98 |
| 21 | NS65: Dismantling Cantilever / bracket assembly. | Numbers | 138.00 | 1,806.91 | 2,49,353.58 |
| 22 | NS66: Dismantling of Regulating equipment. | Numbers | 9.00 | 10,220.58 | 91,985.22 |
| 23 | NS68: Dismantling of Section Insulator. | Numbers | 5.00 | 4,599.79 | 22,998.95 |
| 24 | NS69: Dismantling of Isolator. | Numbers | 4.00 | 1,579.71 | 6,318.84 |
| 25 | NS70: Dismantling of Anti-creep. | Numbers | 5.00 | 2,785.27 | 13,926.35 |
| 26 | NS71: Dismantling of G Jumper. | Numbers | 8.00 | 900.63 | 7,205.04 |
| 27 | NS72: Dismantling of OHE wires, contact, catenary, droppers etc. | Per Track KM | 4.30 | 57,949.96 | 2,49,184.83 |
| 28 | NS73: Checking and preparation of SED. | Numbers | 160.00 | 762.33 | 1,21,972.8 |
| 29 | NS86: Erection of copper jumper wire from AT to OHE with components. | Numbers | 5.00 | 799.75 | 3,998.75 |
| Schedule total | ₹34,50,081.5 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Tender Document
ATTACHMENT
TenderDocumentEtenderTRD4725-26.pdf
ATTACHMENT
TenderDocumentEtenderTRD4725-26C.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .