| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance GATHA BHADERWAH DISTRICT DODA P O UDRANA J K PIN 182221 | DODA | JAMMU AND KASHMIR | 182221 | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
| 3 | Admitted-Finance | Admitted-Finance |
| 4 | Admitted-Finance | Admitted-Finance |
| 5 | Not Admitted-Fee/PreQual/Technical | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
Refer Docs
EMD Value
₹25,000
Closing Date
14 May 2022, 4:00 pmClosed
Executive Engineer ED Doda
Office of the Executive Engineer JPDCL ED Doda
Repairing of Distribution Transformers of various capacities at Divisional Workshop
2022_PDD_168371_1
ED Doda/JPDCL/07
Open Tender
Electrical Works
Item Rate
365 days
Divisional Workshop ED Doda
Kindly refer to NIT and SBD
2 documents required · 2 mandatory
₹1,000
Executive Engineer ED Doda
₹25,000
20 Jul 2022
4 May 2022
18 May 2022
5 May 2022
14 May 2022
5 May 2022
Amount
Repair/Reclamation of Damaged Distribution Transformers (11KV/6.6KV/0.44KV) 25KVA DTR
Opening of transformer, draining of oil, opening of HV /LV connections, taking out core, opening of side channel lamination complete job.
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage HT Coils (Three limbs)
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage LT Coils (Three limbs)
Labour Charges for cleaning & washing of transformer tank, radiators top covers etc.
Labour Charges for repairing, welding of transformer tank, radiators, Arresting of Oil Leakages etc., if any
Labour Charges for painting of Transformer tank, radiators (Complete Job).
Impregnation and heat treatment of coils (upto 630 KVA)
Winding of HV Leg Coil (Copper/Aluminium).
Winding of LV Leg Coil (Copper/Aluminium).
Rewinding of LV leg (Copper/Aluminium).
Labour charges for filtration of transformer oil
Refitting/ Replacement of Bushing only HV/LV
Refitting/ Replacement of Bush rod only HV/LV
Labour Charges for Re-assembling, refitting of coils, including all sundry items to be replaced & re-tanking up of assembled core, refitting & testing of transformer .
Repair/Reclamation of Damaged Distribution Transformers (11KV/6.6KV/0.44KV) 50/63KVA DTR
Opening of transformer, draining of oil, opening of HV /LV connections, taking out core, opening of side channel lamination complete job.
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage HT Coils (Three limbs)
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage LT Coils (Three limbs)
Labour Charges for cleaning & washing of transformer tank, radiators top covers etc.
Labour Charges for repairing, welding of transformer tank, radiators, Arresting of Oil Leakages etc., if any
Labour Charges for painting of Transformer tank, radiators (Complete Job).
Impregnation and heat treatment of coils
Winding of HV Leg Coil (Copper/Aluminium).
Winding of LV Leg Coil (Copper/Aluminium).
Rewinding of LV leg (Copper/Aluminium).
Labour charges for filtration of transformer oil
Refitting/ Replacement of Bushing only HV/LV
Refitting/ Replacement of Bush rod only HV/LV
Labour Charges for Re-assembling, refitting of coils, including all sundry items to be replaced & re-tanking up of assembled core, refitting & testing of transformer .
Repair/Reclamation of Damaged Distribution Transformers (11KV/6.6KV/0.44KV) 100KVA DTR
Opening of transformer, draining of oil, opening of HV /LV connections, taking out core, opening of side channel lamination complete job.
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage HT Coils (Three limbs)
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage LT Coils (Three limbs)
Labour Charges for cleaning & washing of transformer tank, radiators top covers etc.
Labour Charges for repairing, welding of transformer tank, radiators, Arresting of Oil Leakages etc., if any
Labour Charges for painting of Transformer tank, radiators (Complete Job).
Impregnation and heat treatment of coils
Winding of HV Leg Coil (Copper/Aluminium).
Winding of LV Leg Coil (Copper/Aluminium).
Rewinding of LV leg (Copper/Aluminium).
Labour charges for filtration of transformer oil
Refitting/ Replacement of Bushing only HV/LV
Refitting/ Replacement of Bush rod only HV/LV
Labour Charges for Re-assembling, refitting of coils, including all sundry items to be replaced & re-tanking up of assembled core, refitting & testing of transformer .
Repair/Reclamation of Damaged Distribution Transformers (11KV/6.6KV/0.44KV) 200/250KVA DTR
Opening of transformer, draining of oil, opening of HV /LV connections, taking out core, opening of side channel lamination complete job.
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage HT Coils (Three limbs)
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage LT Coils (Three limbs)
Labour Charges for cleaning & washing of transformer tank, radiators top covers etc.
Labour Charges for repairing, welding of transformer tank, radiators, Arresting of Oil Leakages etc., if any
Labour Charges for painting of Transformer tank, radiators (Complete Job).
Impregnation and heat treatment of coils
Winding of HV Leg Coil (Copper/Aluminium).
Winding of LV Leg Coil (Copper/Aluminium).
Rewinding of LV leg (Copper/Aluminium).
Labour charges for filtration of transformer oil
Refitting/ Replacement of Bushing only HV/LV
Refitting/ Replacement of Bush rod only HV/LV
Labour Charges for Re-assembling, refitting of coils, including all sundry items to be replaced & re-tanking up of assembled core, refitting & testing of transformer .
Repair/Reclamation of Damaged Distribution Transformers (11KV/6.6KV/0.44KV) 300KVA DTR
Opening of transformer, draining of oil, opening of HV /LV connections, taking out core, opening of side channel lamination complete job.
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage HT Coils (Three limbs)
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage LT Coils (Three limbs)
Labour Charges for cleaning & washing of transformer tank, radiators top covers etc.
Labour Charges for repairing, welding of transformer tank, radiators, Arresting of Oil Leakages etc., if any
Labour Charges for painting of Transformer tank, radiators (Complete Job).
Impregnation and heat treatment of coils
Winding of HV Leg Coil (Copper/Aluminium).
Winding of LV Leg Coil (Copper/Aluminium).
Rewinding of LV leg (Copper/Aluminium).
Labour charges for filtration of transformer oil
Refitting/ Replacement of Bushing only HV/LV
Refitting/ Replacement of Bush rod only HV/LV
Labour Charges for Re-assembling, refitting of coils, including all sundry items to be replaced & re-tanking up of assembled core, refitting & testing of transformer .
Repair/Reclamation of Damaged Distribution Transformers (11KV/6.6KV/0.44KV) 400KVA DTR
Opening of transformer, draining of oil, opening of HV /LV connections, taking out core, opening of side channel lamination complete job.
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage HT Coils (Three limbs)
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage LT Coils (Three limbs)
Labour Charges for cleaning & washing of transformer tank, radiators top covers etc.
Labour Charges for repairing, welding of transformer tank, radiators, Arresting of Oil Leakages etc., if any
Labour Charges for painting of Transformer tank, radiators (Complete Job).
Impregnation and heat treatment of coils
Winding of HV Leg Coil (Copper/Aluminium).
Winding of LV Leg Coil (Copper/Aluminium).
Rewinding of LV leg (Copper/Aluminium).
Labour charges for filtration of transformer oil
Refitting/ Replacement of Bushing only HV/LV
Refitting/ Replacement of Bush rod only HV/LV
Labour Charges for Re-assembling, refitting of coils, including all sundry items to be replaced & re-tanking up of assembled core, refitting & testing of transformer .
Repair/Reclamation of Damaged Distribution Transformers (11KV/6.6KV/0.44KV) 500KVA DTR
Opening of transformer, draining of oil, opening of HV /LV connections, taking out core, opening of side channel lamination complete job.
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage HT Coils (Three limbs)
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage LT Coils (Three limbs)
Labour Charges for cleaning & washing of transformer tank, radiators top covers etc.
Labour Charges for repairing, welding of transformer tank, radiators, Arresting of Oil Leakages etc., if any
Labour Charges for painting of Transformer tank, radiators (Complete Job).
Impregnation and heat treatment of coils
Winding of HV Leg Coil (Copper/Aluminium).
Winding of LV Leg Coil (Copper/Aluminium).
Rewinding of LV leg (Copper/Aluminium).
Labour charges for filtration of transformer oil
Refitting/ Replacement of Bushing only HV/LV
Refitting/ Replacement of Bush rod only HV/LV
Labour Charges for Re-assembling, refitting of coils, including all sundry items to be replaced & re-tanking up of assembled core, refitting & testing of transformer .
Repair/Reclamation of Damaged Distribution Transformers (11KV/6.6KV/0.44KV) 630KVA DTR
Opening of transformer, draining of oil, opening of HV /LV connections, taking out core, opening of side channel lamination complete job.
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage HT Coils (Three limbs)
Taking out of all the coils after opening the connection and inspection of coils to ascertain the damage LT Coils (Three limbs)
Labour Charges for cleaning & washing of transformer tank, radiators top covers etc.
Labour Charges for repairing, welding of transformer tank, radiators, Arresting of Oil Leakages etc., if any
Labour Charges for painting of Transformer tank, radiators (Complete Job).
Impregnation and heat treatment of coils
Winding of HV Leg Coil (Copper/Aluminium).
Winding of LV Leg Coil (Copper/Aluminium).
Rewinding of LV leg (Copper/Aluminium).
Labour charges for filtration of transformer oil
Refitting/ Replacement of Bushing only HV/LV
Refitting/ Replacement of Bush rod only HV/LV
Labour Charges for Re-assembling, refitting of coils, including all sundry items to be replaced & re-tanking up of assembled core, refitting & testing of transformer .
Topping of oil Level of transformers at site
Collection,Packing ,Weighing and Loading of scrap of wire in to vehicle at Divisional workshop
Dinkum Enterprises
Madina Electrical Works
M/S UNIQUE ENGINEERS AND SUPPLIERS
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .