| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹28,888Accepted-AOC | ₹28,888 | L1 | Accepted-AOC L1 Accept |
| 2 | L2₹29,049.04Rejected-Finance | ₹29,049.04 | L2 | Rejected-Finance L2 Reject |
| Sl No | Description | Qty | Unit | C MALATHY L1 | S. KANAGAMANI L2 |
|---|---|---|---|---|---|
| 1.00Renovation of Girls Toilet at Killukkottai PUES in Killukkottai Panchayat | |||||
| 1.01 | Plastering with cement mortor 1:5 (one cement and five sand) 12mm thick in all floor including curing etc. complete complying with standard specification | 5.33 | Sqm | 285 ₹1,519.05 | 288 ₹1,535.04 |
| 1.02 | Paving the flooring with special type of flooring tiles (Cement based Hydraulically pressed Anti skid tiles (20mm thick) in CM 1:3, 20mm thick including cost and conveyance of all materials to site and all labour charges etc complete | 1.86 | Sqm | 1,465 ₹2,724.90 | 1,470 ₹2,734.20 |
| 1.03 | Dadooing with glazed tiles of size 300x200x6mm including cost and conveyance of all materials to site and all labour charges etc complete | 4.56 | Cum | 1,573 ₹7,172.88 | 1,575 ₹7,182 |
| 1.04 | White washing two coats with shell lime including cost and conveyance of all labour charges ete, complete. | 2.4 | Sqm | 39 ₹93.60 | 40 ₹96 |
| 1.05 | Distempering the old walls and ceiling one coat with best oil bound distemper of approved quality including preparation of surfaces (the colour and quality should be got approved by the Executive Engineer before use) the rate includes cost of brushes, high scaffolding charges, neat finishing, cost of brushes etc., complete complying with standard specification and as directed by the Departmental Officer | 7.8 | Sqm | 150 ₹1,170 | 155 ₹1,209 |
| 1.06 | Re Painting the walls with Two coats with first class quality Plastic Emulsion paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) SI No 358 | 40.11 | Sqm | 267 ₹10,709.37 | 268 ₹10,749.48 |
| 1.07 | Painting two coats over old iron works using ready mixed enamel paint including cost and conveyance of all labour charges ete, complete | 7.04 | Sqm | 155 ₹1,091.20 | 158 ₹1,112.32 |
| 1.08 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package} | 1 | GST Amount (in Rupees) | 4,407 ₹4,407 | 4,431 ₹4,431 |
Updated dates
Tender Value
₹31,000
Closing Date
18 Feb 2026, 3:00 pmClosed
Block Development Officer (BP)
Block Development Officer (BP) Panchayat Union, Kunnandarkoil
Renovation of Girls Toilet at Killukkottai PUES in Killukkottai Panchayat
2026_RDTN_654658_1
A2/302/2026
Open Tender
Civil Works
180 days
Kunnandarkoil
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
Yes
16 Apr 2026
11 Feb 2026
18 Feb 2026
11 Feb 2026
18 Feb 2026
11 Feb 2026
11 Feb 2026 - 17 Feb 2026
Renovation of Girls Toilet at Killukkottai PUES in Killukkottai Panchayat
Plastering with cement mortor 1:5 (one cement and five sand) 12mm thick in all floor including curing etc. complete complying with standard specification
Paving the flooring with special type of flooring tiles (Cement based Hydraulically pressed Anti skid tiles (20mm thick) in CM 1:3, 20mm thick including cost and conveyance of all materials to site and all labour charges etc complete
Dadooing with glazed tiles of size 300x200x6mm including cost and conveyance of all materials to site and all labour charges etc complete
White washing two coats with shell lime including cost and conveyance of all labour charges ete, complete.
Distempering the old walls and ceiling one coat with best oil bound distemper of approved quality including preparation of surfaces (the colour and quality should be got approved by the Executive Engineer before use) the rate includes cost of brushes, high scaffolding charges, neat finishing, cost of brushes etc., complete complying with standard specification and as directed by the Departmental Officer
Re Painting the walls with Two coats with first class quality Plastic Emulsion paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) SI No 358
Painting two coats over old iron works using ready mixed enamel paint including cost and conveyance of all labour charges ete, complete
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
techsummary_784957.pdf
BOQ Comparative Chart
xlsx
finsummary_784957.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.68 MB
BOQ_784957.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid