| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹9.9 LAccepted-AOC | ₹9.9 L | 1 | Accepted-AOC L1 |
| 2 | 2₹10.3 LRejected-AOC VPO SIGRA DISTRICT M GARH | SIGRA | M GARH | HARYANA | ₹10.3 L | 2 | Rejected-AOC L2 |
| 3 | 3₹14.5 LRejected-Finance | ₹14.5 L | 3 | Rejected-Finance L3 |
Tender Value
₹13.3 L
EMD Value
₹26,587
Closing Date
17 Feb 2026, 11:00 amClosed
XEN Water Services Division No.1, Rewari
W.S. Divn. No.1 Rewari
Estimate for connecting village pond Pranpura by NP-3 (350MM DIA) Pipe line from Km 2.000/L of Khori Minor..
2026_HRY_501869_1
2026E8317602 0790 4A4F AC34 D180004269AD136IRR
Open Tender
Civil Works
240 days
XEN Water Services Division No.1
3 documents required · 3 mandatory
₹1,000
₹26,587
Yes
9 Apr 2026
10 Feb 2026
17 Feb 2026
10 Feb 2026
17 Feb 2026
10 Feb 2026
10 Feb 2026 - 12 Feb 2026
Civil Works
HSR Item 4.14.1-Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil
HSR Item 22.159.2-Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536) : 2. 150 mm dia C.I. Double Flanged Pipe
HSR Item 6.1.2-Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
HSR Item 4.16.1.3-Excavating trenches of required width and depth for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m. 1.3. All kind of soil Pipes, cables etc, exceeding 300 mm dia but not exceeding 600 mm dia
HSR Item 21.95.1-Providing lowering cutting jointing and testing RCC pipe class NP3 as per IS-458-2003 with spigot and socketed joints manufactured with ISI marked sulphate resistance cement as per ISI 12330 with rubber rings ISI marked antiternmite as required at site in to trenches for all depths and laying out the same to correct alignment gradients and levels including dressing and trimming and cutting of concrete beds and side of trenches, if required jointing with rubber rings in trenches and jointing with 1:3/2 cement sand mortar and with end dowels filled with 1:3/2 cement sand mortar and finishing the joints at an angle of 45 degree with faces of spigot of socket joints cutting and finishing the cut surface to a uniform finish etc. as fully described in item No. 21.38, item 21.44, item 21.45, and item 21.46 including cartage loading and unloading complete in all respects. the internal diametric of the sewer being: 1. 350 mm
HSR Item 7.21.1-Brick work with common burnt clay nonmodular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand)
HSR Item 22.162.3.2-Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc. (the tail pieces if required will be paid separately) : 3.2. 150 mm diameter Class II
HSR Item 11.5.3-12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand)
HSR Item 7.22.1-Brick work with common burnt clay nonmodular bricks of class designation 10.5 in superstructure above plinth level up to floor IV level in all shapes and sizes in : 1. Cement mortar 1:4 (1 cement : 4 coarse sand)
HSR Item 6.38.1-Providing and fixing up to floor four level precast cement concrete string or lacing courses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers, steps, stair cases, etc., including hoisting and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), cost of required Centering complete. 1. 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20mm nominal size)
HSR Item 6.33.3-Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars
HSR Item 21.28-Providing and fixing steel bar embedded plastic steps of size 263mm x 165mm of orange colour, confirming to specification in pump chambers, manholes etc., having minimum 3mm thick polypropylene polymer confirming to is:10910 encapsulated on 12mm dia ribbed steel bars per IS :1786. The rate include cost of setting the same to correct lines and levels duly embedded in 1:2:4 cement concrete including carriage, loading, uploading, stacking, handling, rehandling etc., comp
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
techsummary_580522.pdf
finance_580522.pdf
BOQ Comparative Chart
xlsx
finsummary_580522.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.69 MB
BOQ_580522.xls
BOQ • 0.31 MB
OT0151387.pdf
Other Document • 2.94 MB
Download all tender documents and submit your bid