| 1 | 1₹17.2 LAccepted-AOC | ₹17.2 L Quoted ₹17.7 L | 1 | Accepted-AOC work awarded |
| 2 | 2₹19.9 LRejected-Finance | ₹19.9 L | 2 | Rejected-Finance finance bid rejected |
| Sl No | Description | Qty | Unit | Pavalam Engineering Contractor L1 | L.MANI&CO L2 |
|---|---|---|---|---|---|
| 1.00Supply of material & Erection for Replacement of old RCC poles to RSJ poles and related clamps, bus bars connectors etc., at 33/11KV Vallipatti SS, in Dindigul EDC | |||||
| 1.01 | Labour, machinery, Consumables for the Fabrication for steel structures.with electricity supplied by Department at free of cost for Heavy section (14 kg/m and above) | 8.77 | - | 19,600 ₹1,71,892 | 23,000 ₹2,01,710 |
| 1.02 | Labour for the Erection of the Fabricated Steel Structures with electricity supplied by Department at free of cost. Heavy section (14 kg/m and above) | 8.77 | - | 12,000 ₹1,05,240 | 14,000 ₹1,22,780 |
| 1.03 | Labour, machinery, Consumables for the Fabrication for steel structures.with electricity supplied by Department at free of cost. Light section (below 14 kg/m) | 4.08 | - | 46,500 ₹1,89,720 | 47,000 ₹1,91,760 |
| 1.04 | Labour for the Erection of the Fabricated Steel Structures with electricity supplied by Department at free of cost. Light section (below 14 kg/m) | 4.08 | - | 16,500 ₹67,320 | 17,000 ₹69,360 |
| 1.05 | Labour, machinery, consumables for fabrication, erection of earrthmat, earth connection, earth electrode, earthspike (including sharpening of earth spike). As directed by the field engineer with electricity supplied by Department at free of cost. | 2.56 | - | 56,300 ₹1,44,128 | 55,000 ₹1,40,800 |
| 1.06 | Labour for erection of 33 KV AB Switches with proper allingments including accessories, Meggering and cost of consumables and lubricants and as directed by the field engineer. with electricity supplied by Department at free of cost. | 4 | E | 11,200 ₹44,800 | 11,728 ₹46,912 |
| 1.07 | Labour for erection of 11 KV AB Switches with proper allingments including accessories, Meggering and cost of consumables and lubricants and as directed by the field engineer. with electricity supplied by Department at free of cost. | 13 | E | 7,900 ₹1,02,700 | 8,300 ₹1,07,900 |
| 1.08 | Labour for erection of 33 and 11 KV LAS station/Distribution type single unit including monitors & accessories. | 30 | E | 900 ₹27,000 | 977 ₹29,310 |
| 1.09 | Labour for the Erection of upto 33 KV Single conductor Strung bus/phase and all related hardwares, fittings, clamps including Meggering, hoisting of insulators, and consumables and as directed by the field engineer. with electricity supplied by Department at free of cost. | 18 | E | 2,300 ₹41,400 | 2,443 ₹43,974 |
Tender Value
₹18.2 L
EMD Value
₹18,200
Closing Date
24 Oct 2025, 3:00 pmClosed
Superintending Engineer/DEDC/Dindigul
O/o The Superintending Engineer, Dindigul EDC, TNPDCL, Meenatchi Nayakan Patti, Dindigul 624 002 Mobile-9445852664
Dindigul EDC - Supply of material and Erection for Replacement of old RCC poles to RSJ poles and related clamps, bus bars connectors etc at 33/11KV Vallipatti SS in Dindigul EDC
2025_EB_613127_1
68/DEDC/25-26
Open Tender
Electrical and Maintenance Works
365 days
DINDIGUL
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹18,200
Yes
20 Jan 2026
10 Oct 2025
25 Oct 2025
10 Oct 2025
24 Oct 2025
10 Oct 2025
Amount
Supply of material & Erection for Replacement of old RCC poles to RSJ poles and related clamps, bus bars connectors etc., at 33/11KV Vallipatti SS, in Dindigul EDC
Labour, machinery, Consumables for the Fabrication for steel structures.with electricity supplied by Department at free of cost for Heavy section (14 kg/m and above)
Labour for the Erection of the Fabricated Steel Structures with electricity supplied by Department at free of cost. Heavy section (14 kg/m and above)
Labour, machinery, Consumables for the Fabrication for steel structures.with electricity supplied by Department at free of cost. Light section (below 14 kg/m)
Labour for the Erection of the Fabricated Steel Structures with electricity supplied by Department at free of cost. Light section (below 14 kg/m)
Labour, machinery, consumables for fabrication, erection of earrthmat, earth connection, earth electrode, earthspike (including sharpening of earth spike). As directed by the field engineer with electricity supplied by Department at free of cost.
Labour for erection of 33 KV AB Switches with proper allingments including accessories, Meggering and cost of consumables and lubricants and as directed by the field engineer. with electricity supplied by Department at free of cost.
Labour for erection of 11 KV AB Switches with proper allingments including accessories, Meggering and cost of consumables and lubricants and as directed by the field engineer. with electricity supplied by Department at free of cost.
Labour for erection of 33 and 11 KV LAS station/Distribution type single unit including monitors & accessories.
Labour for the Erection of upto 33 KV Single conductor Strung bus/phase and all related hardwares, fittings, clamps including Meggering, hoisting of insulators, and consumables and as directed by the field engineer. with electricity supplied by Department at free of cost.
Labour for the Erection of Jumper/ Droppers using Zebra Conductors including Modification of End clamps, providing holes etc wherever necessary as directed by the field engineer.
Labour for the erection of 50 mm Busbar including suitable Modifications of End Clamps, providing holes wherever necessary as directed by the field engineer.
Labour for the erection of Insulator single pole stack for supports Uprights/Underhang including Meggering & other consumables and as directed by the field engineer. 28 upto 33kV
Labour for Dismantling of steel structures including all consumables heavy section below 14 kg/m
Labour for Dismantling of steel structures including all consumables. Light section below 14 kg/m
Labour for Dismantling of Jumper/Droppers using Zebra Conductors including consumables.
Labour for Dismantling of Busbar including consumables. 73 50 mm busbar 1 length
Labour for Dismantling of Insulator single pole stack for supports/Underhang including consumables. 74
Labour for Dismantling of LAS station/Distribution type single unit including monitos, accessories & consumables. 11kV LAS
Labour for Dismantling of Isolators including accessories and consumables. 33 KV isolator
Labour for Dismantling of Isolators including accessories and consumables. 11KV isolator
Clearing the site with scrub jungle
Labour for Earth work excavating and depositing on bank with initial lead of 10m & initial lift of 2m in Sand, silt or other loose soil, wet sand or silt not under water, light black cotton soil, sandy loam and ordinary soil including excavated earth (ORDINARY SOIL)
Labour for Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Slush and silt under water upto 0.75m depth requiring the aid of basket and vessels.(Sand and Silt under water)
Labour for HGS SS.20.B. Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders.
PCC 1:3:6 using 40 mm HBS jelly including cost of all materials, lead, lift, etc., complete without form work. with electricity supplied by Department at free of cost.
PCC 1:2:4 using 20 mm HBS jelly including cost of all materials, lead, lift, etc., complete with form work with electricity supplied by Department at free of cost.
Plastering with CM 1:3, 12 mm thick including cost of all materials, lead, lift, curing etc., complete.
L.MANI&CO (BID ID -1494709)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.94 MB
BOQ_732611.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid