| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.1 LAccepted-AOC | ₹1.1 L | 1 | Accepted-AOC L1 Bidder |
| Sl No | Description | Qty | Unit | M/s A.Chelladurai & Co L1 |
|---|---|---|---|---|
| 1.00 | Dismantling and clean removal of floor finished in cement mortar with glazed tiles and disposal of debries away from site of 10 and up to 100m including cost of all materials, labours lead, lift etc., complete. | 40 | m² | 70 ₹2,800 |
| 2.00 | Flooring with approved Vitrified tiles 600x600mm of approved Quality, design & colour (Johnson or equivalent make)laid in cement mortar 1:3 - 20mm thick including pointing with same coloured cement using 0.4kg/sqm, finishing the joints, including cost of all materials, water charges,labour, lead, lift, etc. complete. | 40 | m² | 1,700 ₹68,000 |
| 3.00 | Dismantling and clean removal of Pressed Tile Roof finish in cement mortar and disposal of debries away from site of 10 and up to 100m including cost of all materials, labours lead, lift etc., complete. | 10 | m² | 70 ₹700 |
| 4.00 | Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete. | 30 | Kg | 95 ₹2,850 |
| 5.00 | Providing PCC 1:2:4 mix using 6 mm and 10 mm HBG metal of a average thickness of 0.75 mm with water proofing compound and finishing the top with power trowelling including cost of all materials,pointing, labour, curing, finishing with proper slope, lead,lift, etc., complete as per the direction of site incharge. | 15 | m² | 650 ₹9,750 |
| 6.00 | Plastering with CM 1:3 mix 20mm thick for ceiling surface including cost of all materials,labour, lead, lift,etc complete. | 20 | m² | 580 ₹11,600 |
| 7.00 | SGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only for Tamil Nadu Contractor. If the contractor is outside Tamil Nadu may be quoted as "0" only | 1 | LS | 9 ₹8,613 |
| 8.00 | CGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only for Tamil Nadu Contractor. If the contractor is outside Tamil Nadu may be quoted as "0" only | 1 | LS | 9 ₹8,613 |
| 9.00 | Inter-state GST to be quoted in percentage (value alone) Ex. 18%, it should be entered as 18 only for other than Tamil Nadu contractor. If the contractor is within Tamil Nadu may be quoted as "0" only | 1 | LS | - |
Tender Value
₹1.1 L
EMD Value
₹1,200
Closing Date
14 Jun 2025, 2:00 pmClosed
Executive Engineer/Operation/Othakkalmandapam
168-1, Pollachi Main Road, 230/110kV Substation, Othakkalmandapam, Coimbatore - 641032
Replacement of existing damaged floor tiles with new Vitrified tiles and screed concrete with Water Proof Compound in EE quarters (T-Type) at 230/110kV Othakkalmandapam Substation under works contract in Coimbatore Operation circle.
2025_EB_562963_1
ET/EE/O/OKM/03/2025-26, Dated. 29.05.2025
Limited
Civil Works - Others
230/110KV Othakkalmandapam Substation
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹1,200
Yes
19 Feb 2026
29 May 2025
16 Jun 2025
29 May 2025
14 Jun 2025
29 May 2025
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf