| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹67.1 LAccepted-AOC | ₹67.1 L | L1 | Accepted-AOC L1 bidder |
| 2 | L2₹67.7 L+₹56,333.80 (0.84%)Rejected-Finance DIGHALIPUKHURI GUWAHATI 781001 | KAMRUP METRO | ASSAM | 781001 | ₹67.7 L+₹56,333.80 (0.84%) | L2 | Rejected-Finance L2 bidder |
| 3 | Not Admitted-Fee/PreQual/Technical OFFICE OF THE CHIEF GENERAL MANAGER D S UPPER ASSAM BIJULEE BHAWAN PALTANBAZAR GUWAHATI | GUWAHATI | KAMRUP | ASSAM | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | M/S D.K. (ASSAM) ASSOCIATES PVT. LTD. L2 | Sourav Baruah L1 |
|---|---|---|---|---|---|
| 1.00 | Earthwork in excavation by mechanical means (Hydraulic excavator)/manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),including dressing of sides and ramming of bottoms,lift upto1.5m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50m. | 25.44 | Cum | 286.85 ₹7,297.46 Lowest | 286.85 ₹7,297.46 Lowest |
| 2.00 | Filling available excavated earth (excluding rock) in trenches, plinth, sides
of foundations etc. in layers not exceeding 20cm in depth, consolidating
each deposited layer by ramming and watering, lead up to 50 and for all lift. | 47.63 | Cum | 253.95 ₹12,095.64 Lowest | 253.95 ₹12,095.64 Lowest |
| 3.00 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | 15.88 | Cum | 2,161.2 ₹34,319.86 Lowest | 2,161.2 ₹34,319.86 Lowest |
| 4.00 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 1.2 | Cum | 7,365.18 ₹8,838.22 | 7,365.15 ₹8,838.18 Lowest |
| 5.00 | Providing and laying in position specified grade of reinforced cement
concrete, excluding the cost of centering, shuttering, finishing and
reinforcement - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 7.15 | Cum | 7,945.65 ₹56,811.4 Lowest | 7,945.65 ₹56,811.4 Lowest |
| 6.00 | Reinforced cement concrete work in walls (any thickness), including
attached pilasters, buttresses, plinth and string courses, fillets, columns,
pillars, piers, abutments, posts and struts etc. above plinth level up to
floor five level, excluding cost of centering, shuttering, finishing and
reinforcement :1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from
natural sources : 3 graded stone aggregate 20 mm nominal
size derived from natural sources) | 2.7 | Cum | 10,185.05 ₹27,499.64 Lowest | 10,185.05 ₹27,499.64 Lowest |
| 7.00 | Reinforced cement concrete work in beams, suspended floors, roofs
having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands,
plain window sills, staircases and spiral stair cases above plinth level up
to floor five level, excluding the cost of centering, shuttering, finishing and
reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived
from natural sources : 3 graded stone aggregate 20 mm nominal size
derived from natural sources). | 5.2 | Cum | 10,719.3 ₹55,740.36 Lowest | 10,719.3 ₹55,740.36 Lowest |
| 8.00 | Centering and shuttering including strutting, propping etc. and removal
of form for: Foundations, footings, bases of columns, etc. for mass
concrete | 27.2 | Sqm | 307.95 ₹8,376.24 Lowest | 307.95 ₹8,376.24 Lowest |
| 9.00 | Centering and shuttering including strutting, propping etc. and removal
of form for:Lintels, beams, plinth beams, girders, bressumers and
cantilevers | 34.56 | Sqm | 608.35 ₹21,024.58 Lowest | 608.35 ₹21,024.58 Lowest |
| 10.00 | Centering and shuttering including strutting, propping etc. and removal
of form for: Columns, Pillars, Piers, Abutments, Posts and Struts | 32.4 | Sqm | 804.25 ₹26,057.7 Lowest | 804.25 ₹26,057.7 Lowest |
Tender Value
₹67.1 L
EMD Value
₹1.3 L
Closing Date
15 Jul 2026, 4:30 pmClosed
Executive Officer, Palashbari Municipal Board
O/o Palashbari Municipal Board
under 1st Ins. For the year 2022-23 during 2023-24 2nd Ins. For the year 2023-24 during 2024-25 1st instalment of Tied Grant under 15th FC for the year 2024-25 during the year 2025-26
2026_UDD_52835_1
PMB/SBM/15th FC/2023-24/195
Open Tender
Civil Works - Others
Works
Area under Palashbari Municipal Board
Please refer Tender documents.
2 documents required · 2 mandatory
₹4,500
₹1.3 L
17 Sept 2026
23 Jun 2026
16 Jul 2026
23 Jun 2026
15 Jul 2026
23 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in excavation by mechanical means (Hydraulic excavator)/manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),including dressing of sides and ramming of bottoms,lift upto1.5m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50m. | 25.44 | Cum | 1.25 | ₹31.8 |
| 2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides
of foundations etc. in layers not exceeding 20cm in depth, consolidating
each deposited layer by ramming and watering, lead up to 50 and for all lift. | 47.63 | Cum | - | - |
| 3 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | 15.88 | Cum | 100 | ₹1,588 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 1.2 | Cum | 53 | ₹63.6 |
| 5 | Providing and laying in position specified grade of reinforced cement
concrete, excluding the cost of centering, shuttering, finishing and
reinforcement - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 7.15 | Cum | 10 | ₹71.5 |
| 6 | Reinforced cement concrete work in walls (any thickness), including
attached pilasters, buttresses, plinth and string courses, fillets, columns,
pillars, piers, abutments, posts and struts etc. above plinth level up to
floor five level, excluding cost of centering, shuttering, finishing and
reinforcement :1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from
natural sources : 3 graded stone aggregate 20 mm nominal
size derived from natural sources) | 2.7 | Cum | 11 | ₹29.7 |
| 7 | Reinforced cement concrete work in beams, suspended floors, roofs
having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands,
plain window sills, staircases and spiral stair cases above plinth level up
to floor five level, excluding the cost of centering, shuttering, finishing and
reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived
from natural sources : 3 graded stone aggregate 20 mm nominal size
derived from natural sources). | 5.2 | Cum | 10 | ₹52 |
| 8 | Centering and shuttering including strutting, propping etc. and removal
of form for: Foundations, footings, bases of columns, etc. for mass
concrete | 27.2 | Sqm | 22 | ₹598.4 |
| 9 | Centering and shuttering including strutting, propping etc. and removal
of form for:Lintels, beams, plinth beams, girders, bressumers and
cantilevers | 34.56 | Sqm | - | - |
| 10 | Centering and shuttering including strutting, propping etc. and removal
of form for: Columns, Pillars, Piers, Abutments, Posts and Struts | 32.4 | Sqm | 1 | ₹32.4 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.98 MB
BOQ_83349.xls
BOQ • 0.33 MB
biddocfinal345.pdf
Tender Documents • 0.96 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .