| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹350.8 CrAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | Rejected-Technical OFFICE 4 LEVEL 7 M AGILE BANER ROAD BANER PUNE PUNE MAHARASHTRA 411045 | PUNE | MAHARASHTRA | 411045 | - | Rejected-Technical Techno-commercially not acceptable for all quoted items |
| Sl No | Description | Qty | Unit | Offshore Infrastructures Ltd L1 |
|---|---|---|---|---|
| 1.00STRUCTURAL STEEL ERECTION | ||||
| 2.00 | Receipt of Structural Materials from OWNER's Store / Storage yard, loading, local transportation up to either Contractor's storage yard / erection site, unloading, assembly,pocket cleaning,foundation chipping,padding, erection, alignment, bolting, welding of Fabricated and painted Structural Steel Elements / Structural Modules in position along with supply & fixing of all type of Connection Bolts (Hot Dip Galvanised/Non-Galvanised Permanent bolts) as per Specifications, Layouts and Fabrication Drawings released for IFC. Scope shall include all activities like Bolting, Welding, Aligning, making necessary alterations caused due to mismatch of Bolt Holes and / or during fabrication, mechanical / Electrical / Pneumatic Torque Tightening of Bolts, cleaning, giving final touch up paint where ever required as per specification to the welded /fabricated parts or damage during transportation & erection etc as required complete in all respect. Making necessary arrangement of required labour, equipment, tools & tackles, Cranes, Manlift, steel scaffolding, consumables, etc to execute the works at all heights as per drawings and specifications along with all related works in order that the Structure is handed over to the complete satisfaction of the Engineer-in-charge.(Exclusions: Erection of steel flooring, ladders, stairways, and handrails).
Measurement shall be done as per AFC Fabrication drawing weight. Weight of erection bolts shall not be considered for payment. | 4,735 | MT | 35,000 ₹16,57,25,000 Lowest |
| 3.00 | Supply, Fabrication, surface preparation and Painting as per Painting Specification and installation of Structural Steel including plates etc. for Miscellaneous activities wherever required. Scope also includes preparation of fabrication drawing and getting it approved from owners/consultant. | 710 | MT | 1,98,000 ₹14,05,80,000 Lowest |
| 4.00 | Supply of Structural Steel including plates etc. for Miscellaneous activities wherever required as per EIC Instruction | 30 | MT | 1,00,000 ₹30,00,000 Lowest |
| 5.00 | Fabrication, surface preparation and Painting as per Painting Specification and installation of Structural Steel including plates etc. for Miscellaneous activities wherever required. Scope also includes preparation of fabrication drawing and getting it approved from owners/consultant. | 30 | MT | 86,000 ₹25,80,000 Lowest |
| 6.00 | STRUCTURAL MODULE ASSEMBLY AT GROUND, TRANSPORTATION & ERECTION IN MODULE AT SITE : Receipt of Pre Fabricated Structural Materials from OWNER's storage yard, assembly, erection at ground, alignment, bolting, welding of Fabricated and painted Structural Steel Elements to make Structural Module at yard/site with the pre-fabricated and painted Structural Steel Elements, loading and Transportation of Modules safely through suitable trailer, unloading at erection site and erection of Structural Modules in position along with Supply and fixing of all type of Connection Bolts (Erection, Hot Dip Galvanised/Non-Galvanised Permanent bolts) as per Specifications, Layouts and Fabrication Drawings released for IFC. Scope shall include all activities like Bolting, Welding, Aligning, making necessary alterations caused due to mismatch of Bolt Holes and / or during fabrication, Torque Tightening of Bolts, fixing in line and level, cleaning, giving final touches to the welded parts, etc as required complete in all respect. Making necessary arrangement of required labour, equipment, tools & tackles, with temporary staging and bracing and removal of the same after erection, consumables, etc to execute the works at all heights as per drawings and specifications along with all related works in order that the Structure/module is handed over to the complete satisfaction of the Engineer-in-charge.
Maximum sizes of Modules shall be be of length (~15 m), width (~10 m), height(~15m) and weight shall be ~80 mt. | 1,362 | MT | 35,000 ₹4,76,70,000 Lowest |
| 7.00 | Unloading of pre fabricated structure at owner's storage yard /Laydown Area from vendor's truck/trailor with all required tool tackle, machinery, labour, cranes tc as per direction of Engineer in charge | 4,140 | MT | 1,000 ₹41,40,000 Lowest |
| 8.00 | Shifting of Structural and piping material within refinery premises with all required tool tackle, machinery, labour, cranes etc as per direction of Engineer in charge | 500 | MT | 1,456 ₹7,28,000 Lowest |
| 9.00HANDRAIL ERECTION | ||||
| 10.00Receipt of fabricated Materials from OWNER's Store / Storage yard loading, local transportation up to Contractor's store / erection site, unloading, assembly, Erection of already fabricated and Painted Handrails as per requirements indicated in Standard Drawings, IFC Layouts and Fabrication Drawings. Scope shall include all activities like Supply and fixing of all type of Connection Bolts (Erection, Hot Dip Galvanized/Non-Galvanized Permanent bolts) as per Specifications, Welding, Aligning, making necessary alterations caused due to mismatch of Bolt Holes, Torque Tightening of Bolts, cleaning, giving final touch up paint as per specifications to the welded/fabricated parts, etc as required complete with all tools & tackles, equipment and labour,Cranes, Manlift, steel scaffolding for all and heights along with all related works in order that the Handrail is handed over to the complete satisfaction of the Engineer-in-charge. Supply of erection nuts and bolts / fasteners are included in this item. Measurement shall be As per AFC Fabrication Drawings. | ||||
Tender Value
Refer Docs
EMD Value
₹1.9 Cr
Closing Date
24 Oct 2025, 3:00 pmClosed
Mukesh Chugh
Technip Tower A4 Sector 1 Noida UP
Structural Erection Piping Fabrication and Erection Equipment Erection Insulation Painting and other associated works Part II for NREP Project at Numaligarh refinery limited including leftover jobs done by other CONTRACTOR
2025_NRL_876909_3
TPIL/CONS/NRL/200663C/013
Open Tender
Pipes and Pipe related activities
Works
480 days
Numaligarh Refinery Assam
Please refer tender documents
6 documents required · 6 mandatory
₹0
₹1.9 Cr
Yes
6 Nov 2025
8 Oct 2025
25 Oct 2025
8 Oct 2025
24 Oct 2025
8 Oct 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | STRUCTURAL STEEL ERECTION | - | - | - | - |
| 2 | Receipt of Structural Materials from OWNER's Store / Storage yard, loading, local transportation up to either Contractor's storage yard / erection site, unloading, assembly,pocket cleaning,foundation chipping,padding, erection, alignment, bolting, welding of Fabricated and painted Structural Steel Elements / Structural Modules in position along with supply & fixing of all type of Connection Bolts (Hot Dip Galvanised/Non-Galvanised Permanent bolts) as per Specifications, Layouts and Fabrication Drawings released for IFC. Scope shall include all activities like Bolting, Welding, Aligning, making necessary alterations caused due to mismatch of Bolt Holes and / or during fabrication, mechanical / Electrical / Pneumatic Torque Tightening of Bolts, cleaning, giving final touch up paint where ever required as per specification to the welded /fabricated parts or damage during transportation & erection etc as required complete in all respect. Making necessary arrangement of required labour, equipment, tools & tackles, Cranes, Manlift, steel scaffolding, consumables, etc to execute the works at all heights as per drawings and specifications along with all related works in order that the Structure is handed over to the complete satisfaction of the Engineer-in-charge.(Exclusions: Erection of steel flooring, ladders, stairways, and handrails).
Measurement shall be done as per AFC Fabrication drawing weight. Weight of erection bolts shall not be considered for payment. | 4,735 | MT | - | - |
| 3 | Supply, Fabrication, surface preparation and Painting as per Painting Specification and installation of Structural Steel including plates etc. for Miscellaneous activities wherever required. Scope also includes preparation of fabrication drawing and getting it approved from owners/consultant. | 710 | MT | - | - |
| 4 | Supply of Structural Steel including plates etc. for Miscellaneous activities wherever required as per EIC Instruction | 30 | MT | - | - |
| 5 | Fabrication, surface preparation and Painting as per Painting Specification and installation of Structural Steel including plates etc. for Miscellaneous activities wherever required. Scope also includes preparation of fabrication drawing and getting it approved from owners/consultant. | 30 | MT | - | - |
| 6 | STRUCTURAL MODULE ASSEMBLY AT GROUND, TRANSPORTATION & ERECTION IN MODULE AT SITE : Receipt of Pre Fabricated Structural Materials from OWNER's storage yard, assembly, erection at ground, alignment, bolting, welding of Fabricated and painted Structural Steel Elements to make Structural Module at yard/site with the pre-fabricated and painted Structural Steel Elements, loading and Transportation of Modules safely through suitable trailer, unloading at erection site and erection of Structural Modules in position along with Supply and fixing of all type of Connection Bolts (Erection, Hot Dip Galvanised/Non-Galvanised Permanent bolts) as per Specifications, Layouts and Fabrication Drawings released for IFC. Scope shall include all activities like Bolting, Welding, Aligning, making necessary alterations caused due to mismatch of Bolt Holes and / or during fabrication, Torque Tightening of Bolts, fixing in line and level, cleaning, giving final touches to the welded parts, etc as required complete in all respect. Making necessary arrangement of required labour, equipment, tools & tackles, with temporary staging and bracing and removal of the same after erection, consumables, etc to execute the works at all heights as per drawings and specifications along with all related works in order that the Structure/module is handed over to the complete satisfaction of the Engineer-in-charge.
Maximum sizes of Modules shall be be of length (~15 m), width (~10 m), height(~15m) and weight shall be ~80 mt. | 1,362 | MT | - | - |
| 7 | Unloading of pre fabricated structure at owner's storage yard /Laydown Area from vendor's truck/trailor with all required tool tackle, machinery, labour, cranes tc as per direction of Engineer in charge | 4,140 | MT | - | - |
| 8 | Shifting of Structural and piping material within refinery premises with all required tool tackle, machinery, labour, cranes etc as per direction of Engineer in charge | 500 | MT | - | - |
| 9 | HANDRAIL ERECTION | - | - | - | - |
| 10 | Receipt of fabricated Materials from OWNER's Store / Storage yard loading, local transportation up to Contractor's store / erection site, unloading, assembly, Erection of already fabricated and Painted Handrails as per requirements indicated in Standard Drawings, IFC Layouts and Fabrication Drawings. Scope shall include all activities like Supply and fixing of all type of Connection Bolts (Erection, Hot Dip Galvanized/Non-Galvanized Permanent bolts) as per Specifications, Welding, Aligning, making necessary alterations caused due to mismatch of Bolt Holes, Torque Tightening of Bolts, cleaning, giving final touch up paint as per specifications to the welded/fabricated parts, etc as required complete with all tools & tackles, equipment and labour,Cranes, Manlift, steel scaffolding for all and heights along with all related works in order that the Handrail is handed over to the complete satisfaction of the Engineer-in-charge. Supply of erection nuts and bolts / fasteners are included in this item.
Measurement shall be As per AFC Fabrication Drawings. | - | - | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 0.65 MB
BOQ_925481.xls
BOQ • 1.09 MB
NOTICEINVITINGTENDER.pdf
Tender Documents • 0.62 MB
MasterIndex.pdf
Tender Documents • 0.37 MB
PARTIUNPRICEDCOMMERCIALSECTION.pdf
Tender Documents • 26.33 MB
PARTIIPRICEDSECTION.pdf
Tender Documents • 1.70 MB
PARTIIITECHNICALSECTION1STRUCTURAL.pdf
Tender Documents • 23.12 MB
PARTIIITECHNICALSECTION2HSEMECHANICALMSLPCC.pdf
Tender Documents • 27.13 MB
PARTIIITECHNICALSECTION3PIPING1.pdf
Tender Documents • 30.48 MB
PARTIIITECHNICALSECTION4PIPING2.pdf
Tender Documents • 25.91 MB
PARTIIITECHNICALSECTION5PIPING3.pdf
Tender Documents • 24.46 MB
PARTIIITECHNICALSECTION6PIPING4ANDCONSTQAQC.pdf
Tender Documents • 25.60 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .