| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹56.0 LAccepted-AOC HOUSE NO 214 WARD NO 2 TEHSIL SUJANPUR DISTT HAMIRPUR HP | HAMIRPUR | HIMACHAL PRADESH | 174304 | L-1 | Accepted-AOC L1 | |
| 2 | L-2₹57.8 L+₹41,176 (0.72%)Rejected-Finance | L-2 | Rejected-Finance l2 |
Tender Value
₹54.9 L
EMD Value
₹1.1 L
Closing Date
24 Jun 2026, 6:00 pmClosed
Executive Engineer
HPPWD ROHRU
RR Damages to Dhara Narpa Road Km 000 to 5500 SH Co RWall at RD 3880 to 4030
2026_PWD_136845_15
11218-11317 dated 12-06-2026
Open Tender
Civil Works - Roads
Percentage
120 days
Rohru
Please refer Tender documents.
9 documents required · 9 mandatory
₹2,000
₹1.1 L
29 Jul 2026
18 Jun 2026
25 Jun 2026
18 Jun 2026
24 Jun 2026
18 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in soil in Hilly Area by manual means including cutting and trimming of side slopes and disposing of excavated earth with a lift upto 1.5 m and a lead upto 20 m as per drawing and Technical Specification Clause 1603.1 | 177 | Cum | 324.83 | ₹57,494.91 |
| 2 | Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. | 282 | Cum | 407 | ₹1,14,774 |
| 3 | Providing and laying concrete for plain/reinforced concrete in open foundations complete as per drawing and technical specification clause 802,803,1202 and 1203.PCC nominal mix 1:6:12(40mm aggregates) And curing complete including the cost of form work and hauling of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge. | 78 | Cum | 5,109.04 | ₹3,98,505.12 |
| 4 | Providing and laying concrete for plain/reinforced concrete in open foundations complete as per drawing and technical specification clause 802,803,1202 and 1203.PCC nominal mix 1:4:8(25mm aggregates) And curing complete including the cost of form work and hauling of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge. | 39 | Cum | 5,710.66 | ₹2,22,715.74 |
| 5 | Stone masonry in cement mortar for substructure complete as per drawing& technical specification Clause 702,704,1202 and1204 Random rubble masonry in cement motar(1:6 ) And curing complete including the cost of form work and hauling of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge. | 769.5 | Nos | 5,893.23 | ₹45,34,840.48 |
| 6 | Providing and laying Stoe filling behind abutment , wing wall and return wall complete as per drawing and technical specification cl;ause 1204.3.8. | 121.5 | Cum | 1,331.51 | ₹1,61,778.47 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.01 MB
SBD15.pdf
Tender Documents • 4.17 MB
BOQ_202538.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .