| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.6 CrAccepted-AOC H NO 1051 60 20 320 3RD FLOOR MANJEERA MAJESTIC KPHB COLONY HYDERABAD 500072 TELANGANA | HYDERABAD | HYDERABAD | TELANGANA | 500072 | ₹3.6 Cr | L1 | Accepted-AOC Being L1 |
| 2 | L2₹4.3 Cr+₹68.7 L (19.0%)Rejected-AOC 121004 | ₹4.3 Cr+₹68.7 L (19.0%) | L2 | Rejected-AOC being not L1 |
| 3 | L3₹4.9 Cr+₹1.3 Cr (37.2%)Rejected-AOC NO 9 DR SEVALIYE SHIVAJI GANESAN NAGAR 3RD STREET DINDIGUL 624 001 | DINDIGUL | DINDIGUL | TAMIL NADU | 624001 | ₹4.9 Cr+₹1.3 Cr (37.2%) | L3 | Rejected-AOC Being not L1 |
| Sl No | Description | Qty | Unit | Neptune Engineers and Builders L2 | P Natesan and Co L3 | RVM CONSTRUCTIONS INDIA PRIVATE LIMITED L1 |
|---|---|---|---|---|---|---|
| .50BOQ Dated April 2026 | ||||||
| .75GENERAL SUMMARY NOTE: Schedule ‘A’ Part I to XI are prepriced by MES under Ser No. 1 to 11. Bidders shall insert their lumpsum amount in the Green coloured field under Col-6 only. | ||||||
| 1.00 | Lumpsum price worked out by the contractor for “BUILDINGS OR WORKS” as listed in Schedule ‘A’ Part–I | 1 | Lumpsum | 3,87,50,000 ₹3,87,50,000 | 4,55,00,000 ₹4,55,00,000 | 3,25,75,500 ₹3,25,75,500 Lowest |
| 2.00 | Lumpsum price worked out by the contractor for “INTERNAL WATER SUPPLY” as listed in Schedule ‘A’ Part–II | 1 | Lumpsum | 1,86,000 ₹1,86,000 | 1,86,057.3 ₹1,86,057.3 | 1,38,500 ₹1,38,500 Lowest |
| 3.00 | Lumpsum price worked out by the contractor for “INTERNAL ELECTRIC SUPPLY" as listed in Schedule ‘A’ Part–III | 1 | Lumpsum | 10,56,000 ₹10,56,000 | 11,33,926 ₹11,33,926 | 9,75,000 ₹9,75,000 Lowest |
| 4.00 | Lumpsum price worked out by the contractor for "HARDSTANDING" as listed in Schedule ‘A’ Part -IV . | 1 | Lumpsum | 3,18,050 ₹3,18,050 | 2,41,992 ₹2,41,992 | 1,85,000 ₹1,85,000 Lowest |
| 5.00 | Lumpsum price worked out by the contractor for “SEWAGE DISPOSAL” as listed in Schedule ‘A’ Part – V. | 1 | Lumpsum | 1,90,000 ₹1,90,000 | 1,99,983 ₹1,99,983 | 1,59,900 ₹1,59,900 Lowest |
| 6.00 | Lumpsum price worked out by the contractor for “AREA DRAINAGE” as listed in Schedule ‘A’ Part – VI. | 1 | Lumpsum | 5,28,650 ₹5,28,650 | 5,25,051 ₹5,25,051 | 4,45,000 ₹4,45,000 Lowest |
| 7.00 | Lumpsum price worked out by the contractor for “COMPOUND WALL” as listed in Schedule ‘A’ Part – VII. | 1 | Lumpsum | 8,65,000 ₹8,65,000 | 7,83,207 ₹7,83,207 | 6,59,999 ₹6,59,999 Lowest |
| 8.00 | Lumpsum price worked out by the contractor for “PERIMETER LIGHTING" as listed in Schedule ‘A’ Part- VIII . | 1 | Lumpsum | 3,35,000 ₹3,35,000 | 3,43,358 ₹3,43,358 | 2,77,560 ₹2,77,560 Lowest |
Tender Value
₹4.0 Cr
EMD Value
₹4.7 L
Closing Date
7 Apr 2026, 6:00 pmClosed
Chief Engineer AF Bangalore
Chief Engineer AF Bangalore No. 2 DC Area MES Road Yeshwantpur Post Bangalore 560022
CONSTRUCTION OF STANDALONE BUILDING WITH ASSOCIATED FACILITES FOR CHILDREN SCHOOL AT AFS SULUR
2026_MES_755079_1
801695/AF/E8
Open Tender
Civil Works
Lump-sum
540 days
GE(AF) SULUR
AS PER NIT
8 documents required · 8 mandatory
₹2,000
GE(AF) SULUR
₹4.7 L
Yes
22 Jun 2026
3 Mar 2026
14 Apr 2026
3 Mar 2026
7 Apr 2026
31 Mar 2026
4 Mar 2026 - 14 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0.5 | BOQ Dated 03 Mar 2026 | - | - | - | - |
| 0.75 | GENERAL SUMMARY
NOTE: Schedule ‘A’ Part I to XI are prepriced by MES under Ser No. 1 to 11. Bidders shall insert their lumpsum amount in the Green coloured field under Col-6 only. | - | - | - | - |
| 1 | Lumpsum price worked out by the contractor for “BUILDINGS OR WORKS” as listed in Schedule ‘A’ Part–I | 1 | Lumpsum | 3,50,00,000 | ₹3,50,00,000 |
| 2 | Lumpsum price worked out by the contractor for “INTERNAL WATER SUPPLY” as listed in Schedule ‘A’ Part–II | 1 | Lumpsum | 1,21,730.52 | ₹1,21,730.52 |
| 3 | Lumpsum price worked out by the contractor for “INTERNAL ELECTRIC SUPPLY" as listed in Schedule ‘A’ Part–III | 1 | Lumpsum | 9,06,031.83 | ₹9,06,031.83 |
| 4 | Lumpsum price worked out by the contractor for "HARDSTANDING" as listed in Schedule ‘A’ Part -IV . | 1 | Lumpsum | 2,05,077.8 | ₹2,05,077.8 |
| 5 | Lumpsum price worked out by the contractor for “SEWAGE DISPOSAL” as listed in Schedule ‘A’ Part – V. | 1 | Lumpsum | 1,69,476.5 | ₹1,69,476.5 |
| 6 | Lumpsum price worked out by the contractor for “AREA DRAINAGE” as listed in Schedule ‘A’ Part – VI. | 1 | Lumpsum | 4,68,794.95 | ₹4,68,794.95 |
| 7 | Lumpsum price worked out by the contractor for “COMPOUND WALL” as listed in Schedule ‘A’ Part – VII. | 1 | Lumpsum | 6,99,291.86 | ₹6,99,291.86 |
| 8 | Lumpsum price worked out by the contractor for “PERIMETER LIGHTING" as listed in Schedule ‘A’ Part- VIII . | 1 | Lumpsum | 2,83,766.24 | ₹2,83,766.24 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.23 MB
801695TENDER.pdf
Tender Documents • 1.02 MB
BOQ_845710.xls
BOQ • 0.55 MB
801695DRGS.pdf
Additional Documents • 24.67 MB
801695TDDRGS.pdf
Additional Documents • 18.67 MB
801695AMEND07.pdf
PDF • 1.21 MB
801695Corrigendum06.pdf
PDF • 0.09 MB
801695Corrigendum05.pdf
PDF • 0.09 MB
801695Corrigendum03.pdf
PDF • 0.09 MB
801695Corrigendum02.pdf
PDF • 0.08 MB
801695CORRIGENDUM01.pdf
PDF • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .