Tender Value
₹1.4 Cr
EMD Value
₹2.7 L
Closing Date
5 Aug 2026, 5:30 pm
Dy. General Manager (Electrical)
DGM Elect Contract Division Teesta V Power Station Balutar Singtam Distt East Sikkim 737134
Replacement of Damaged Parts of HVAC System at Power House, Teesta-V Power Station.
2026_NHPC_917236_1
NH/TSV/CONT/MC-170/NIT-1088
Open Tender
Job Works
Works
90 days
Teesta-V Power Station, Balutar
As per Tender Document
5 documents required · 5 mandatory
₹1,180
NHPC Limited
₹2.7 L
Yes
15 Jul 2026
15 Jul 2026
11 Aug 2026
15 Jul 2026
5 Aug 2026
15 Jul 2026
15 Jul 2026 - 21 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling and shifting of damaged existing: 7238 CFM (30 mm SP) Exhaust Fan of Battery Room (Make: Alstom, Model: BFD30J/3K7-P4) of HVAC System in Power House | - | Nos | - | - |
| 2 | Dismantling and shifting of damaged existing: 7500 CFM (30 mm SP) Smoke Exhaust Fan installed in Access Tunnel (Make: Alstom, Model: BFD30J/3K7-P4) of HVAC System in Power House | - | Nos | - | - |
| 3 | Dismantling and shifting of damaged existing: 20950 CFM (20 mm SP) Fresh Air Fan installed in Ventilation Tunnel (Make: Alstom, Model: 38J1/2/5K5-P4-8) of HVAC System in Power House | - | Nos | - | - |
| 4 | Supply of 7238 CFM (30 mm SP) Exhaust Fan of Battery Room (Make: Alstom, Model: BFD30J/3K7-P4) of HVAC System (as per Annexure-I of SECTION-VIII-TECHNICAL SPECIFICATION of Tender Document) | - | Nos | - | - |
| 5 | Supply of 7500 CFM (30 mm SP) Smoke Exhaust Fan installed in Access Tunnel (Make: Alstom, Model: BFD30J/3K7-P4) of HVAC System (as per Annexure-I of SECTION-VIII-TECHNICAL SPECIFICATION of Tender Document) | - | Nos | - | - |
| 6 | Supply of 20950 CFM (20 mm SP) Fresh Air Fan installed in Ventilation Tunnel (Make: Alstom, Model: 38J1/2/5K5-P4-8) of HVAC System (as per Annexure-I of SECTION-VIII-TECHNICAL SPECIFICATION of Tender Document) | - | Nos | - | - |
| 7 | Installation, Testing & Commissioning of 7238 CFM (30 mm SP) Exhaust Fan of Battery Room (Make: Alstom, Model: BFD30J/3K7-P4) of HVAC System (as per Annexure-I of SECTION-VIII-TECHNICAL SPECIFICATION of Tender Document) | - | Nos | - | - |
| 8 | Installation, Testing & Commissioning of 7500 CFM (30 mm SP) Smoke Exhaust Fan installed in Access Tunnel (Make: Alstom, Model: BFD30J/3K7-P4) of HVAC System (as per Annexure-I of SECTION-VIII-TECHNICAL SPECIFICATION of Tender Document) | - | Nos | - | - |
| 9 | Installation, Testing & Commissioning of 20950 CFM (20 mm SP) Fresh Air Fan installed in Ventilation Tunnel (Make: Alstom, Model: 38J1/2/5K5-P4-8) of HVAC System (as per Annexure-I of SECTION-VIII-TECHNICAL SPECIFICATION of Tender Document) | - | Nos | - | - |
| 10 | Dismantling and shifting of existing rectangular & round ducting for Smoke Exhaust (Access Tunnel), Return Air (Transformer Hall), Return Air (Control Block), Fresh Air (Ventilation Tunnel), including fittings, supports, flanges, etc. | - | Sqm | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 8.18 MB
SafetyManualaug2024.pdf
Additional Documents • 0.73 MB
TenderdocumentMC170.pdf
Tender Documents • 7.33 MB
BOQ_964052.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].