| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 LAccepted-AOC | L1 | Accepted-AOC AWARD OF WORK TO L1 BIDDER AND REJECT L2 AND L3 BIDDER DUE TO NOT L1 BIDDER | |
| 2 | Rejected-Technical | - | Rejected-Technical NOT L1 BIDDER | |
| 3 | Rejected-Technical JAYANT NEAR JAI HIND SCHOOL LAXMI MARKET SINGRAULI 486890 MADHYA PRADESH INDIA | SINGRAULI | MADHYA PRADESH | 486890 | - | Rejected-Technical NOT L1 BIDDER |
Tender Value
₹1.7 L
EMD Value
₹2,200
Closing Date
31 Aug 2024, 11:00 amClosed
GENERAL MANAGER EXCAVATION, NCL KHADIA PROJECT
NCL KHADIA PROJECT, SHAKTINAGAR,SONEBHADRA, U.P.-231222
Repairing of Bucket and Boom eye housing and fitting of Cartridge pin of CAT 992K Payloader Sl. No. ZMX00642 of Khadia Project.
2024_NCL_315172_1
KHD/G.M. (Excv)/E-Tender/24-25/399
Open Tender
Excavation Department Work
Item Rate
7 days
NCL KHADIA PROJECT, SHAKTINAGAR
Please refer Tender documents.
6 documents required · 6 mandatory
₹2,200
31 Oct 2024
14 Aug 2024
2 Sept 2024
14 Aug 2024
31 Aug 2024
16 Aug 2024
14 Aug 2024 - 20 Aug 2024
Amount
Scope of Work/Technical Specifications etc: 1. Removal of both side bucket & boom cartridge. 2. Cleaning of boom eye housing after removing of both side boom cartridge and bucket. 3. Under cutting of bucket eye housing inner & outer of both side. 4. Re-building of all housing of both side of boom and bucket by welding. 5. Co-axial line boring of both side boom eye housing & inner and outer area of bucket eye housing. 6. Fitment of both boom cartridge and bucket.
Labour Charges for removal of both side bucket and boom cartridge including contractor's profit. . Note: It includes a group of 03 Nos. Skilled Fitter, 01 No. Skilled Welder and 03 Nos. Un-Skilled Manpower in 02 Shifts per day for 02 days.
Labour Charges for Cleaning of boom eye housing after removing of both side boom cartridge and bucket including contractor's profit. . Note: It includes a group of 01 No. Un-Skilled Manpower in 02 Shifts for 01 day.
Cost of undercut of boom eye housing of both side boom housing (Per side approx. 164.24 Cu. Cm.).
Cost of undercut of bucket eye housing (inner) of both side (Per side approx. 79.91 Cu. Cm.).
Cost of undercut of bucket eye housing (outer) of both side (Per side approx. 124.30 Cu. Cm.).
Labour Charges for re-building of all housing false including contractor's profit. . . Note: It includes a group of 02 Nos. Skilled Welder and 02 Nos. Un-Skilled Manpower in 02 Shifts per day for 02 days.
Cost of final machining (Co-axial line boring) of both side boom eye housing (Per side approx. 159.89 Cu. Cm.).
Cost of final machining (Co-axial line boring) of both side bucket eye housing inner area (Per side approx. 77.78 Cu. Cm.).
Cost of final machining (Co-axial line boring) of both side bucket eye housing outer area (Per side approx. 120.99 Cu. Cm.).
Labour Charges for fitting of both boom cartidge and bucket including contractor's profit. . Note: It includes a group of 03 Nos. Skilled Fitter, 01 No. Skilled Welder & 03 Nos. Un-Skilled Manpower in 02 Shifts per day for 02 days.
Hiring Charges for 01 No. Welding Machine with accessories.
Hiring Charges for Gas cutting set with all accessories.
Charges for Tool and tackles.
Hiring Charges for Grinding machine with all accessories.
Total impact of GST for the purpose of CTC
SARWESHWARI ENTERPRISES
Neelkamal Enterprises
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_326621.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .