Tender Value
₹21.9 Cr
EMD Value
₹21.9 L
Closing Date
3 Oct 2026, 5:30 pm
Directorate of Municipal Administration
Superintending Engineer
Package No-01 Design, Build, Operate and Transfer (DBOT) of Interception and Diversion works in Badami, Belagali, Jamkhandi, Kamatagi, Mahalingpur, Mudhol, Rabkavi Banhatti and Shiruru ULBs of Bagalkote District with 5 years operation and maintenance (including 2 year Defect liability period) under Swachh Bharat Mission (Urban) 2.0 fund
DMA/2025-26/WT/WORK_INDENT56775/CALL-3
DMA/2025-26/WT/WORK_INDENT56775/CALL-3
Open
Water supply/sewage lines
Two Tender Document System(Two Cover)
DMA Directorate Office Bengaluru
1 document required · 1 mandatory
To qualify for award of this contract, The intending bidder can submit bids as an Individual / joint venture bidder, Satisfactorily completed (at least 90% of the contract value), as prime contractor, at least one similar work such as UGD project /I&D project/ water supply project/Lift - Irrigation Projects /Storm Water Drains/combined water supply & sewerage project/ combined water supply or Sewerage project with Road/ combined water supply or Sewerage project with Layout works/ combined water supply or Sewerage project with Building works of value not less than Rs 1094.53 Lakhs during the last 5 financial years (2021-22 to 2025-26),The certificate should be issued by an officer not below the rank of the Executive Engineer or Equivalent or Employer in case of Govt / Semi Govt. Authorities and General Manager in case of public sector Undertaking.
To qualify for award of this contract, The intending bidder can submit bids as an Individual /joint venture bidder, Executed in any one year (continuous in 12 months) of the last five years (2021-22 to 2025-26),1)Earthwork excavation/embankment-28985.00 cum,2)Cement concrete (Plain & Reinforced)-1360.00 cum,3)TMT Steel/ structural steel-97.00 MT,4)All types of pipes (RCC NP3/ DI/ u-PVC/ Stone ware/MSpipes/DWC/GSW/HDPE pipes)-18.87 km(The certificate should be issued by an officer not below the rank of the Executive Engineer or Equivalent or Employer in case of Govt / Semi Govt. Authorities and General Manager in case of public sector Undertaking)
To qualify for award of this contract, The tenderer or his identified electrical-contractor should possess valid Class-II and above electrical license and should have executed similar electrical works totalling to Rs. 31.56 Lakh in any one year of the last five years (2021-22 to 2025-26).
Each Tenderer should further demonstrate the intending bidder can submit bids as an Individual / joint venture bidder.(a)The critical equipment specified in the table below shall be made available for all the works on owning, lease/hire basis subject to the submission of valid commitment agreements or relevant documentation verifying its availability. 1)Excavators-3Nos (2Nos - own, 1No - Lease/hire), 2)Tippers-3Nos (2Nos - own, 1No - Lease/hire),3)Concrete Batching plant/Self-loading Concrete mixer 1/2 Nos, If the bid is submitted as joint venture, then any one partner/jointly should meet the requirement, Note: The bidder shall provide invoice / RC book copies for owned vehicles and for lease / hire vehicles, lease agreement along with RC book copy/invoice for vehicles
Each Tenderer should further demonstrate:Liquid assets and/or availability of credit facilities of not less than Rs.656.72 Lakhs credit lines/letter of credit/Certificates from banks) for meeting the fund requirement etc., (equivalent of the estimated cash flow for 3 months in the peak construction period) in the form of unconditional credit lines/ letter of credit/ certificate from any Nationalized Banks/ Scheduled Banks as per the format below.If the bid is submitted as joint venture, then any one partner/jointly should meet the requirement,Note: Liquid asset in the form of credit line/ letter of credit/ certificates from banks for meeting the fund requirement etc., shall be in the format appended with the bid document. Any conditional Banker Certificate will not be accepted and will lead to disqualification
Tenderers who meet the other specified minimum qualifying criteria, will only be qualified, if their available tender capacity is more than the total tender value. The available tender capacity will be calculated as under Assessed available tender capacity is(AxNx1.50 - B) where A, N & B as per tender document
The intending bidder(Including JV partner) should furnish the Class-I Registration Certificate of any State/Central-Government/Public-Sector Organization issued by competent authorities.
To qualify for award of this contract, the intending bidder can submit bids as an Individual / joint venture bidder achieved in at least two financial years a minimum financial turnover (in all classes of civil engineering construction works only) of Rs.4378.15 Lakhs. If the bid is submitted as JV, then the requirement of minimum financial turnover shall be considered on the basis of combined resources. The lead partner should have an annual financial turnover of not less than 51% of total turnover& JV member not less than 25% of total turnover indicated above in any two financial years and Combining should meet 100% during last 5 financial years (2021-22 to 2025-26). All document/certificates issued by a Charted Accountant should have a UDIN (unique document Identification Number) generated through the ICAI (The Institute of chartered Accountants of India) Portal. Certificate without UDIN the documents uploaded will be considered and treated as invalid document. Attached are copies of financial statements (Auditors Report, Profit and Loss Statements, Balance Sheets, Form 240 of Sales Tax Returns / GST Annual Returns in the state of Karnataka & Relevant documents whichever is applicable in respective states, including all related notes and income statements) for the last FIVE Years, as indicated above, complying with the following conditions.
₹7,500
₹21.9 L
16 Sept 2026
16 Sept 2026
5 Oct 2026
25 Sept 2026
25 Sept 2026
Package No-01 Design, Build, Operate and Transfer (DBOT) of Interception and Diversion work in Badami, ULB of Bagalkote District with 5 years operation and maintenance (including 2 year Defect liability period) under Swachh Bharat Mission (Urban) 2.0 fund
PART- A(i): Design, supply, construction, installation, testing & commissioning of Interception and Diversion (I&D)Unit including components but not limited to SS screens, Interception weir/barrier, s...
PART- A(ii):Design, supply, construction, installation, testing & commissioning of Wet Well with Electromechanical components such as Non-clog Sewage Pump sets and EOT crane, electrification,testing &...
PART- A(iii):Design, supply, construction, installation, testing & commissioning of rising main for a length as per site condition requirements, of Ductile Iron (K9 class) pipeline connecting from Pro...
PART- A(iv):Design, supply, construction, installation, testing & commissioning of New UGD line for damaged portion works as per specification(indicative) and drawings (indicative) as per bid document...
Part-B:Operation & Maintenance of the facility for 5 years:Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure wo...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Package No-01 Design, Build, Operate and Transfer (DBOT) of Interception and Diversion work in Belagali, ULB of Bagalkote District with 5 years operation and maintenance (including 2 year Defect liability period) under Swachh Bharat Mission (Urban) 2.0 fund
PART- A(i): Design, supply, construction, installation, testing & commissioning of Interception and Diversion (I&D)Unit including components but not limited to SS screens, Interception weir/barrier, s...
PART- A(ii):Design, supply, construction, installation, testing & commissioning of Wet Well with Electromechanical components such as Non-clog Sewage Pump sets and EOT crane,electrification, testing &...
PART- A(iii):Design, supply, construction, installation, testing & commissioning of rising main for a length as per site condition requirements, of Ductile Iron (K9 class) pipeline connecting from Pro...
Part-B: Operation & Maintenance of the facility for 5 years:Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure w...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Package No-01 Design, Build, Operate and Transfer (DBOT) of Interception and Diversion work in Jamkhandi ULB of Bagalkote District with 5 years operation and maintenance (including 2 year Defect liability period) under Swachh Bharat Mission (Urban) 2.0 fund
PART- A(i): Design, supply, construction, installation, testing & commissioning of Interception and Diversion (I&D)Unit including components but not limited to SS screens, Interception weir/barrier, s...
PART- A(ii):Design, supply, construction, installation, testing & commissioning of Wet Well with Electromechanical components such as Non- clog Sewage
Pump sets and EOT crane, electrification, testin...
PART- A(iii):Design, supply, construction, installation, testing & commissioning of rising main for a length as per site condition requirements, of Ductile Iron (K9 class) pipeline connecting from Pro...
Part-B: Operation & Maintenance of the facility for 5 years:Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure w...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Package No-01 Design, Build, Operate and Transfer (DBOT) of Interception and Diversion work in Kamatagi, ULB of Bagalkote District with 5 years operation and maintenance (including 2 year Defect liability period) under Swachh Bharat Mission (Urban) 2.0 fund
PART- A(i): Design, supply, construction, installation, testing & commissioning of Interception and Diversion (I&D)Unit including components but not limited to SS screens, Interception weir/barrier, s...
PART- A(ii):Design, supply, construction, installation, testing & commissioning of Wet Well with Electromechanical components such as Non-clog Sewage
Pump sets and EOT crane, electrification, testing ...
PART- A(iii):Design, supply, construction, installation, testing & commissioning of rising main for a length as per site condition requirements, of Ductile Iron (K9 class) pipeline connecting from Pro...
Part-B:Operation & Maintenance of the facility for 5 years:Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure wo...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Package No-01 Design, Build, Operate and Transfer (DBOT) of Interception and Diversion work in Mahalingpur ULB of Bagalkote District with 5 years operation and maintenance (including 2 year Defect liability period) under Swachh Bharat Mission (Urban) 2.0 fund
PART- A(i): Design, supply, construction, installation, testing & commissioning of Interception and Diversion (I&D)Unit including components but not limited to SS screens, Interception weir/barrier, s...
PART- A(ii):Design, supply, construction, installation, testing & commissioning of Wet Well with Electromechanical components such as Non-clog Sewage Pump sets and EOT crane,
electrification, testing ...
PART- A(iii):Design, supply, construction, installation, testing & commissioning of rising main for a length as per site condition requirements, of Ductile Iron (K9 class) pipeline connecting from Pro...
Part-B:Operation & Maintenance of the facility for 5 years:Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure wo...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Package No-01 Design, Build, Operate and Transfer (DBOT) of Interception and Diversion work in Mudhol ULB of Bagalkote District with 5 years operation and maintenance (including 2 year Defect liability period) under Swachh Bharat Mission (Urban) 2.0 fund
PART- A(i): Design, supply, construction, installation, testing & commissioning of Interception and Diversion (I&D)Unit including components but not limited to SS screens, Interception weir/barrier, s...
PART- A(ii):Design, supply, construction, installation, testing & commissioning of Wet Well with Electromechanical components such as Non-clog Sewage Pump sets and EOT crane,electrification, testing &...
PART- A(iii):Design, supply, construction, installation, testing & commissioning of rising main for a length as per site condition requirements, of Ductile Iron (K9 class) pipeline connecting from Pro...
Part-B: Operation & Maintenance of the facility for 5 years:Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure w...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Package No-01 Design, Build, Operate and Transfer (DBOT) of Interception and Diversion work in Rabkavi Banhatti ULB of Bagalkote District with 5 years operation and maintenance (including 2 year Defect liability period) under Swachh Bharat Mission (Urban) 2.0 fund
PART- A(i): Design, supply, construction, installation, testing & commissioning of Interception and Diversion (I&D)Unit including components but not limited to SS screens, Interception weir/barrier, s...
PART- A(ii):Design, supply, construction, installation, testing & commissioning of Wet Well with Electromechanical components such as Non-clog Sewage Pump sets and EOT crane,electrification, testing &...
PART- A(iii):Design, supply, construction, installation, testing & commissioning of Pipeline for a length as per site condition requirements, of Ductile Iron (K9 class) pipe (Pumping Main) connecting ...
Part-B:Operation & Maintenance of the facility for 5 years:Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure wo...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Package No-01 Design, Build, Operate and Transfer (DBOT) of Interception and Diversion work in Shiruru ULB of Bagalkote District with 5 years operation and maintenance (including 2 year Defect liability period) under Swachh Bharat Mission (Urban) 2.0 fund
PART- A(i): Design, supply, construction, installation, testing & commissioning of Interception and Diversion (I&D)Unit including components but not limited to SS screens, Interception weir/barrier, s...
PART- A(ii):Design, supply, construction, installation, testing & commissioning of Wet Well with Electromechanical components such as Non-clog Sewage Pump sets and EOT crane,electrification, testing &...
PART- A(iii):Design, supply, construction, installation, testing & commissioning of rising main for a length as per site condition requirements, of Ductile Iron (K9 class) pipeline connecting from Pro...
Part-B:Operation & Maintenance of the facility for 5 years:Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure wo...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Operation & Maintenance of Interception and Diversion Structure and Wetwell Structures and all other supporting facilities/ Infrastructure works built up under the package contract excluding power cha...
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
Bagalkote indicative dwg.zip
Others - indicative drawings • 10.13 MB
Bid document Bagalkote P1 call3.docx
Tender Document • 0.41 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .