| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹98.1 LAccepted-AOC | L1 | Accepted-AOC work awarded to L1 contractor 0.05 percentage less than the estimate rate | |
| 2 | L2₹1.1 Cr+₹7.9 L (8.06%)Rejected-Finance | L2 | Rejected-Finance L2rejected |
| Sl No | Description | Qty | Unit | Alexander L2 | shree and co L1 |
|---|---|---|---|---|---|
| 1.00Strengthening of Sennal Managar Road Km 0/0-0/990 (R 88) in Korkai Panchayat in Srivaikundam Block of Thoothukudi District | |||||
| 2.00 | Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m | 370 | Sqm | 25.23 ₹9,335.1 | 23.35 ₹8,639.5 Lowest |
| 3.00Providing and Laying Red Gravel for side berms including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete. | |||||
| 4.00 | Km 0/0-0/99 | 89.1 | Cum | 602.33 ₹53,667.6 | 557.43 ₹49,667.01 Lowest |
| 5.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 166.5 | Cum | 2,626.03 ₹4,37,234 | 2,430.29 ₹4,04,643.29 Lowest |
| 6.00 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 25mm using 13.20mm IRC size HBG metal with 44 Kg of Bitumen-for 1cum of metal mixed in hot mix plant laying at site | 6.53 | Cum | 5,292.76 ₹34,561.72 | 4,898.25 ₹31,985.57 Lowest |
| 7.00 | Providing and laying TACK COAT over BT surface using 3 Kg of RS-1 Bitumen Emulsion/ 10 sq.m for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery,fuel and all other incidental charges etc complete.including labour for spraying, hire charges for bitumen sprayer etc. Comp. | 1,860 | Sqm | 36.49 ₹67,871.4 | 33.77 ₹62,812.2 Lowest |
| 8.00 | Providing and laying Tack Coat over WBM/ WMM surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 | 1,110 | Sqm | 21.36 ₹23,709.6 | 19.77 ₹21,944.7 Lowest |
| 9.00 | Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen (SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5 | 1,110 | Sqm | 92.07 ₹1,02,197.7 | 85.21 ₹94,583.1 Lowest |
| 10.00 | BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and  Plastic Waste Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic (6%) for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 (Using Plastic Waste) | 74.25 | Cum | 12,482.88 ₹9,26,853.84 | 11,552.44 ₹8,57,768.67 Lowest |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
3 Sept 2025, 3:00 pmClosed
Additional Collector (D), DRDA, Thoothukudi
Additional Collector (D), DRDA, Thoothukudi
Thoothukudi District -TN/Tut-16/2025-26-MGSMT/Phase III-Srivaikundam Block - Strengthening / Renewal of 2 No of Rural Roads
2025_RDTN_594190_14
DRDPR/DIPR/4437/dt18.08.2025
Open Tender
Civil Works
Item Rate
180 days
Thoothukudi District
As per Tender Documents
4 documents required · 4 mandatory
₹0
₹1.1 L
DRDA, Thoothukudi
7 Nov 2025
19 Aug 2025
3 Sept 2025
19 Aug 2025
3 Sept 2025
19 Aug 2025
28 Aug 2025
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .