| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.4 CrAdmitted-Finance | -27.52% | ₹3.4 Cr | L1 | Admitted-Finance |
| 2 | L2₹3.6 Cr+₹26.9 L (7.96%)Admitted-Finance | -21.75% | ₹3.6 Cr+₹26.9 L (7.96%) | L2 | Admitted-Finance |
| 3 | L3₹3.7 Cr+₹29.9 L (8.86%)Admitted-Finance | -21.10% | ₹3.7 Cr+₹29.9 L (8.86%) | L3 | Admitted-Finance |
| 4 | L4₹3.8 Cr+₹42.8 L (12.7%)Admitted-Finance | -18.33% | ₹3.8 Cr+₹42.8 L (12.7%) | L4 | Admitted-Finance |
| 5 | L5₹3.9 Cr+₹52.7 L (15.6%)Admitted-Finance | -16.20% | ₹3.9 Cr+₹52.7 L (15.6%) | L5 | Admitted-Finance |
Tender Value
₹4.7 Cr
EMD Value
₹9.3 L
Closing Date
25 Mar 2026, 4:00 pmClosed
SE PWD R and B KATHUA SAMBA CIRCLE KATHUA
SE PWD R and B KATHUA SAMBA CIRCLE KATHUA
Please refers to BOQ
2026_PWDJK_304996_1
e-NIT No.PWD/SE/KS/38 of 2025-26 Dated 28-02-2026
Open Tender
Civil Works - Roads
Percentage
1080 days
KATHUA-BASOHLI
Please refers to NIT and SBD
4 documents required · 4 mandatory
₹6,000
SE PWD R and B KATHUA SAMBA CIRCLE KATHUA
₹9.3 L
SE PWD R and B KATHUA SAMBA CIRCLE KATHUA
3 Apr 2026
3 Mar 2026
27 Mar 2026
3 Mar 2026
25 Mar 2026
3 Mar 2026
18 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. a) All kinds of soil | 1,733.15 | cum | 187.3 | ₹3,24,619 |
| 2 | Earthwork in excavation in all kinds of soil by mechanical means (Hydraulic excavator) in trenches for foundation, drains, pipes etc. (not exceeding 1.5m in width) and for shafts, wells, cesspits and the like not exceeding 10sqm on Plan, including dressing of sides and ramming of bottoms lift upto 1.5m, including getting out the excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 mtr. | 33.13 | cum | 256.85 | ₹8,509.44 |
| 3 | Providing and laying cement concrete of specified grade including curing but excluding the cost of centering and shuttering. All work upto plinth level with: a) 1:5:10 (1 cement:5 coarse sand:10 graded stone aggregate 40mm nominal size). | 127.09 | Cum | 4,826.5 | ₹6,13,399.89 |
| 4 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts,struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchors blocks, plain window sills, fillets etcupto floor V level, including curing but excluding the cost of centring, shuttering and finishing with. a) 1:5:10 (1 cement : 5 coarse sand : 10 graded brick aggregate 40 mm nominal size | 78 | Cum | 4,469.25 | ₹3,48,601.5 |
| 5 | Providing and laying cement concrete of specified grade including curing but excluding the cost of centering and shuttering. All work upto plinth level with: a) 1:3:6 (1 cement:3 coarse sand:6 graded stone aggregate 20mm nominal size) | 83.24 | Cum | 5,733.6 | ₹4,77,264.86 |
| 6 | Providing and laying damp-proof Course 50 mm thick with cement concrete 1:2:4 (1 cement:2 coarse sand: 4 graded stone aggregate 20 mm nominal size) and curing complete | 42.04 | Sqm | 416.5 | ₹17,509.66 |
| 7 | Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in
charge. Note: - Cement in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is content considered payable or recoverable separately.
a) All works upto plinth level | 361.43 | cum | 8,021.1 | ₹28,99,066.17 |
| 8 | Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in
charge. Note: - Cement in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is content considered payable or recoverable separately.
a) All works above plinth level upto floor V level | 541.24 | cum | 9,412.05 | ₹50,94,177.94 |
| 9 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
position and binding all complete upto plinth level: a) Thermo-Mechanically Treated bars of grade Fe-500D or more. | 1,03,297 | Kg | 123.2 | ₹1,27,26,190.4 |
| 10Centering and shuttering including strutting propping etc. and removal of form work for:- | |||||
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.38 MB
MakeList.pdf
Additional Documents • 0.63 MB
BOQ_990713.xls
BOQ • 0.44 MB
CorrAll.pdf
PDF • 0.90 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .