| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L3₹12.4 L+₹1.0 L (8.45%)Accepted-AOC | ₹12.4 L+₹1.0 L (8.45%) Quoted ₹13.4 L | L3 | Accepted-AOC Accept |
| 2 | L1₹12.4 LRejected-AOC AT POLORAJPUR PO SURANGI PS JARADA DIST GANJAM PIN 761037 | GANJAM | ODISHA | 761037 | ₹12.4 L | L1 | Rejected-AOC Reject |
| 3 | L2₹12.5 L+₹13,428.51 (1.08%)Rejected-AOC AT NIGAM NAGAR 3RD LANE ANKULI BERHAMPUR B N PUR DIST GANJAM ODISHA | BERHAMPUR | GANJAM | ODISHA | ₹12.5 L+₹13,428.51 (1.08%) | L2 | Rejected-AOC Reject |
Tender Value
₹14.9 L
EMD Value
₹14,920
Closing Date
8 May 2026, 5:00 pmClosed
Executive Engineer, L.I. Division, Berhampur
O/o the Executive Engineer, L.I. Division, Berhampur, Po- Panigrahy Pentho, Aska Road, Dist- Ganjam, Pin-760006
Installation Revival and Energisation of L.I. Project
2026_OLIC_128504_5
01/2026-27 OLIC (BAM)
Open Tender
Civil Works - Lift Irrigation Schemes
Percentage
180 days
Chadiyapada under Chikiti Block
Please refer Tender documents
3 documents required · 3 mandatory
₹7,080
₹14,920
Yes
30 Jul 2026
28 Apr 2026
11 May 2026
28 Apr 2026
8 May 2026
28 Apr 2026
28 Apr 2026 - 7 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0.0 | Chadiyapada R/L | - | - | - | - |
| 1.01 | Earth work in hard soil for excavation of foundation including dressing and levlling the bed and depositing the soil within 50 mtr. initial lead and 1.5 mtr. initial lift as per direction of Engineer-in-charge. | 28.9 | Cum | 270.9 | ₹7,829.01 |
| 1.02 | Filling in foundation and plinth with sand well watered and rammed including cost of sand as per direction of Engineer-in-charge. | 52.89 | Cum | 521.24 | ₹27,568.38 |
| 1.03 | C.C(1:4:8) with 4 Cm. size H.B.G metal laying and hoisting etc. complete with curing as per direction of Engineer-in-charge | 4.32 | Cum | 5,631.12 | ₹24,326.44 |
| 1.04 | Brick work with Fly ash bricks of (23cm x 11 cm x 8 cm ) in cement mortar (1:6) in foundation and plinth with curing etc.complete as per direction of Engineer-in-charge. | 5.09 | Cum | 5,753.13 | ₹29,254.67 |
| 1.05 | Cement concrete (1:2:4) for R.C.C. works with 12mm size h.g.b. chips including hoisting and laying etc. complete with curing as per direction of Engineer-in-charge | 10.22 | Cum | 8,000.04 | ₹81,728.41 |
| 1.06 | Providing & supplying of M.S.Rod for for M.S. Reinforcement for R.C.C work including cutting, bending, binding & tying the grills & placing in position including cost of binding wire etc.complete as per direction of Engineer-in-charge | 7.31 | Qntl | 8,515.65 | ₹62,215.34 |
| 1.07 | Rigid smooth centering and shuttering for R.C.C. works including false work and dismentling them after casting including cost of materials complete etc. complete for Column base etc | 15.96 | Sqm | 144.41 | ₹2,304.78 |
| 1.08 | Rigid smooth centering and shuttering for R.C.C. works including false work and dismentling them after casting including cost of materials complete etc. complete for Slab,Column,Beam etc. | 84.73 | Sqm | 658.92 | ₹55,830.29 |
| 1.09 | 12 mm thick cement plastering with cement mortar (1:6)over brick work with curing etc.complete.as per direction of Engineer-in-charge. | 137.24 | Sqm | 268.2 | ₹36,807.77 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 6.38 MB
Tendernotice_2.pdf
PDF • 1.79 MB
BOQ_588853.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .