| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹58.6 LAdmitted-Finance 12 NANDGAON PO NIGAHI DISTT SINGRAULI MP 486884 | SINGRAULI | MADHYA PRADESH | 486884 | ₹58.6 L | L1 | Admitted-Finance |
| 2 | L2₹58.9 LAdmitted-Finance PLOT NO 17 18 EWS COLONY NEAR LIG COLONY SINGRAULI SINGRAULI SIDHI MADHYA PRADESH 486889 UDYAM MP 11 0000525 | SINGRAULI | MADHYA PRADESH | 486889 | ₹58.9 L | L2 | Admitted-Finance |
| 3 | L3₹61.4 LAdmitted-Finance MAIN ROAD BEALUNJI P O WAIDHAN DISTT SINGRAULI M P | SINGRAULI | MADHYA PRADESH | ₹61.4 L | L3 | Admitted-Finance |
| 4 | Rejected-Technical NEW MARKET SINGRAULI DISTT SINGRAULI MP 486889 | SINGRAULI | SINGRAULI | MP | 486889 | - | - | Rejected-Technical As per TC recommendation. |
| Sl No | Description | Qty | Unit | DUCK CONSTRUCTION COMPANY L1 | M/S SARCO ENGINEERING WORKS L2 | M/s Shiv Shankar Electrical Civil Engineering L3 |
|---|---|---|---|---|---|---|
| 1.00PART - A | ||||||
| 1.01 | Supply of MS Nut bolt and washer
(5/8'' x4'' - 5/8'' x 8'') | 910 | kgs | 85 ₹77,350 | 80 ₹72,800 | 100 ₹91,000 |
| 1.02 | Supply of GI Stay Wire 7/12 SWG | 2,500 | kgs | 85 ₹2.1 L | 70 ₹1.8 L | 65 ₹1.6 L |
| 1.03 | Supply of G.I. Earth wire 7/16 SWG | 3,100 | kgs | 85 ₹2.6 L | 70 ₹2.2 L | 65 ₹2.0 L |
| 1.04 | Supply of G.I. stay set complete (¾” x 6') | 390 | Nos | 400 ₹1.6 L | 400 ₹1.6 L | 460 ₹1.8 L |
| 1.05 | Supply of Tension Type Hardware | 300 | Nos | 280 ₹84,000 | 250 ₹75,000 | 350 ₹1.1 L |
| 1.06 | Supply of Suspension Type Hardware | 110 | Nos | 280 ₹30,800 | 250 ₹27,500 | 280 ₹30,800 |
| 1.07 | Supply of 11 KV Gr Stay Porcelien Insulator | 320 | Nos | 50 ₹16,000 | 50 ₹16,000 | 65 ₹20,800 |
| 2.00PART B | ||||||
| 2.01 | Excv. of pole pit size 0.8 x 0.8 x 1.8 mtr. In soft rock /soil.(1.152x 1190 nos) | 1,370.88 | cum | 90 ₹1.2 L | 140 ₹1.9 L | 110 ₹1.5 L |
Updated dates
Tender Value
₹90.0 L
EMD Value
₹1.1 L
Closing Date
20 Feb 2026, 11:30 amClosed
Staff Officer(EnM), Amlohri Area
Office of Area General Manager, Amlohri Area, NCL, Singrauli - 486887
Day to day Dismantling, Shifting, Erection etc.of HT OHL including Repairing and maintenance work of all HT Old existing Lines on day to day basis as well as during Faults, attending faults at S/S (as per requirement and instruction of Engg I/C)
2026_NCL_352034_1
AML/SO/ENM/ETN/26/660
Open Tender
Electrical and Maintenance Works
730 days
Amlohri Project, NCL
Please refer Tender documents.
3 documents required · 3 mandatory
₹1.1 L
17 Apr 2026
30 Jan 2026
21 Feb 2026
30 Jan 2026
20 Feb 2026
31 Jan 2026
30 Jan 2026 - 6 Feb 2026
PART - A
Supply of MS Nut bolt and washer (5/8'' x4'' - 5/8'' x 8'')
Supply of GI Stay Wire 7/12 SWG
Supply of G.I. Earth wire 7/16 SWG
Supply of G.I. stay set complete (¾” x 6')
Supply of Tension Type Hardware
Supply of Suspension Type Hardware
Supply of 11 KV Gr Stay Porcelien Insulator
PART B
Excv. of pole pit size 0.8 x 0.8 x 1.8 mtr. In soft rock /soil.(1.152x 1190 nos)
Excv. Of stay pit size 0.6 x 0.6 x 1.2 mtr. In soft rock /soil (0.432*910 nos)
Grouting of pole and stay with mine bolder along with 1/2 bag cement
Earth pit as per IS 3047 including supply of materials with connection
PART C
Erection of Tubular pole 13 to 16 mtr.long
Erection of Stay set with stay Insulator including tensioning as per requirement
Fabrication of MS Channel,angle,flat in shape of bracket/clamps and supports as per required
Erection of fabricated bracket of M S channel on DP/TP/FP as per required
Erection of Braket & support on each pole for conductor and strenthening of earth wire
Erection of 11 KV grade Disc insulator with hard ware
Laying & stringing of wolf/AAA conductor incl jumpering
Laying & stringing of Earth wire
Providing guarding on the line including fixing of brackets
Fault Clearing due to Lightning/Rainy ,Storm or any other Misc reasons in mines as well as substations etc as and when required as per instruction of Engineer Incharge ( By providing Min 02 unskilled,2 skilled and 1 highly skilled) Total LS frequency of fault clearing
Installation & Testing of 6.6 KV Gr,1250 Amp Isolator (GOAB switch) on Poles in mine
Dismantling,shifting,Erection & commissioning of 6.6 KV Gr,1250 Amp Isolator (GOAB switch) as per requirement in mine(during shifting of poles)
Trimming of tree Branches surrounding OHL
PART D
Dismantling & shifting of 13 to 16 mtr long tubular pole
Collection & shifting of wolf/AAA conductor after dismantling
Dismantling & shifting of Disc insulator with bracket
Dismantling & shifting of Channel,bracket/cross/clamp etc
HT Pole mounting cable erection/dismantling
Dismantling ,collection & shifting of Stay set with Stay wire
Total impact of GST for the purpose of CTC
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
techsummary_364833.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 2.05 MB
BOQ_364833.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid