Loading…
Loading…
Tender Value
₹69.4 L
EMD Value
₹69,402
Closing Date
23 Jul 2026, 5:00 pm
Divisional Officer
ROADS and BUILDINGS DIVISION, CHARBATIA
Construction of compound wall and Gate in Odisha Adarsha Vidyalaya at Kandarkana under Tangi Block in Cuttack district Buildings.
2026_EICCL_135107_1
SE CBT (R and B)-02/2026-27
Open Tender
Civil Works - Buildings
120 days
Cuttack
2 documents required · 2 mandatory
₹10,000
₹69,402
Yes
9 Jul 2026
9 Jul 2026
24 Jul 2026
9 Jul 2026
23 Jul 2026
9 Jul 2026
9 Jul 2026 - 18 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation of foundation trenches in hard soil inlcuidng dressing of sides and levelling the bed up to the required depth and depositing the excavated materials away from the work site within 50m initial lead and 1.5m initial lifts with sundries and t and P required for the work etc complete including cost of all labour T and P etc complete as per specification and direction of the engineer-in-charge | 227.45 | cum | 210.52 | ₹47,882.77 |
| 2 | Filling foundation trenches and plinth with excavated earth inlcuidng laying the earth in layers not exceeding 23.5cm thick ramming and watering with all leads and lifts inlcuidng cost of all labour T&P etc complete as per direction of the engineer-in-charge | 145.88 | cum | 157.16 | ₹22,926.5 |
| 3 | Supplying and filling in foundation and plinth with good quality river sand including watering, ramming with cost, conveyances, royalties of all materials and cost of all labour with T&P required for the work etc. complete as per specification & direction of Engineer-in-charge | 28.19 | cum | 659.79 | ₹18,599.48 |
| 4 | Cement concrete (1:3:6) in foundation and floors using 4cm(1½) size hard crusher broken granite stone metal of approved quality and from approved quarry including lowering, laying concrete watering, curing etc, complete to required levels laid in layers not exceeding 0-6 thick including cost, conveyances, royalties, taxes of all materials and cost of all labour with T&P required for the work etc, complete as per specification & direction of the Engineer-in-charge. | 28.32 | cum | 6,326.26 | ₹1,79,159.68 |
| 5 | Fly ash Brick masonry using Fly ash Bricks in SUPERSTRUCTURE having crushing strength not less than 75Kg/sqcm in cement mortar (1:6) after immersing the bricks for six hours in water before use including splays, cutting, circular moulding, corbelling, champhering and similar such type of works, scaffolding, watering, curing, including cost, conveyances, royalties, taxes of all materials and cost of all labour with T&P required for the work etc. complete as per specification & direction of Engineer-in-charge. | 146.28 | cum | 5,497.69 | ₹8,04,202.09 |
| 6 | RCC M-25 using black hard granite crusher broken chips of 12mm to 20mm size (12mm 750% and 20mm 25% ) of approaved quality from approved quarry to achieve the minimum compressive strength of 200kg/cm2 250kg/cm2, 3.00 kg/cm2 of 150mm size cubes on 28 days test confirming to codal provision including hoisting lowering and laying concrete in layers not exceeding 15cm thick compacting in vibrators and watering for 28 days including centering shuttering from works finishing the exposed surface smooth providing grooves where necessary including cost conveyance royalty taxes of all materials with all leads and lifts and cost of all labour T&P mechineries required for the work de-watering if necessary compalete in all respect as directed by Engineer-in-charge including dismantling the centering and shuttering but excluding cost conveaynce of MS rod or tor steel & bind wire and labour charges for strengthening cutting beinding binding wilding and tying the grills etc hoisting and placing in positing (to be paid separetely for RCC work) Footing | 72.85 | cum | 7,136.37 | ₹5,19,884.55 |
| 7 | Column up to plinth | 15.71 | cum | 16,519.22 | ₹2,59,516.95 |
| 8 | Plinth Beam | 37.34 | cum | 8,010.77 | ₹2,99,122.15 |
| 9 | Column, RCC coping | 39.17 | cum | 16,519.22 | ₹6,47,057.85 |
| 10 | Supplying Cutting, straightening coiled or bent up M.S. Rod or tor steel including bending, binding, welding and joining if necessary and tying the grills and placing in position as required for R.C.C. Work and for providing fan hooks as required, hoisting, lowering, laying including cost, conveyances, taxes of M.S. Rod or tor steel and binding wires of 18 to 20 gauge and labour required for the work for bending, binding and tying the grills in all floors (payment will be made on standard weight of B.I.S. for M.S. Rods or tor steel only) etc. complete as per specification & direction of Engineer-in-charge. | 144.65 | qtl | 9,540.51 | ₹13,80,044.31 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_2.pdf
PDF • 1.13 MB
Tendernotice_1.pdf
PDF • 0.46 MB
BOQ_600638.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid