Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.3 LAccepted-AOC | ₹5.3 L | L1 | Accepted-AOC Accepted |
| 2 | L2₹5.3 LRejected-AOC 22 27 JOTHI NAGAR PN ROAD TIRUPUR | ₹5.3 L | L2 | Rejected-AOC Rejected |
| 3 | L3₹5.4 LRejected-AOC | ₹5.4 L | L3 | Rejected-AOC Rejected |
| 4 | L4₹5.5 LRejected-AOC | ₹5.5 L | L4 | Rejected-AOC Rejected |
| Sl No | Description | Qty | Unit | NARPAVI TRADERS L1 | AHIRA DALMAIDA TERRIL DALMAIDA L4 | nagalingam L2 | PRABU ENGINEERING L3 |
|---|---|---|---|---|---|---|---|
| 1.00Name of Work: 1)Providing Paver Block Arrangement from petchithai house to Nirmala House (60 m) in Veerapandianpattnam Village Panchayat. | |||||||
| 2.00 | Earth work excavation for pavement & drain in all soils and sub soils and to full depth as may be directed except rock requiring blasting but inclusive of shoring strutting and baling out water wherever necessary etc., complete. | 5.4 | m3 | 113.62 ₹613.55 | 130 ₹702 | 110 ₹594 | 116.06 ₹626.72 |
| 3.00 | Cement concrete 1:4:8 (One cement four sand and eight aggregate) using 40mm gauge hard broken granite stone including all incidental charges, dewatering if found necessary etc., complete. | 2.7 | m3 | 4,905.35 ₹13,244.45 | 2,000 ₹5,400 | 4,900 ₹13,230 | 5,010.68 ₹13,528.84 |
| 4.00 | Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing | 68.4 | m2 | 314.45 ₹21,508.38 | 250 ₹17,100 | 300 ₹20,520 | 321.2 ₹21,970.08 |
| 5.00 | Plain Cement concrete 1:3:6 using 20mm HBG jelly including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks for 10 cum | 6.84 | m3 | 5,553.07 ₹37,983 | 5,000 ₹34,200 | 5,800 ₹39,672 | 5,672.31 ₹38,798.60 |
| 6.00 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 | 9.9 | m3 | 2,417.02 ₹23,928.50 | 2,000 ₹19,800 | 2,500 ₹24,750 | 2,468.92 ₹24,442.31 |
| 7.00 | Collection and supply of 6mm metal from approved quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete, | 19.8 | m3 | 1,116.51 ₹22,106.90 | 1,000 ₹19,800 | 1,200 ₹23,760 | 1,140.49 ₹22,581.70 |
| 8.00 | Providing and Laying of Interlocking Rubber moulded Hydraulic pressed Paver block Pavements specification clause 1504, M30 grade 63 mm thickness paver block | 198 | m2 | 620.78 ₹1.2 L | 700 ₹1.4 L | 625 ₹1.2 L | 634.11 ₹1.3 L |
| 9.00Name of Work:2)Construction of a New River Water Supply System in Shanthi Nagar in Veerapandianpattnam Village Panchayat. (410 m) | |||||||
| 10.00 | Supply and fixing of 75mm 6Ksc PVC pipe including all cost and conveyance charges | 410 | m | 62.89 ₹25,784.90 | 100 ₹41,000 | 60 ₹24,600 | 64.33 ₹26,375.30 |
Tender Value
₹6.7 L
EMD Value
₹6,670
Closing Date
10 Dec 2025, 3:00 pmClosed
Block Developmenet officer (VP)
Block Developmenet officer (VP) Panchayat Union office, Tiruchendur, Thoothukudi District
1)Providing Paver Block Arrangement from petchithai house to Nirmala House (60 m) in Veerapandianpattnam Village Panchayat.. 2)Construction of a New River Water Supply System in Shanthi Nagar(410 m).3)EPL Veerapandianpattinam Panchayat
2025_RDTN_629168_1
T2/2768/2025
Open Tender
Civil Works - Buildings
Tiruchendur Union
As per Tender Schedule
4 documents required · 4 mandatory
₹0
₹6,670
Panchayat Union office, Tiruchendur
20 Feb 2026
5 Dec 2025
10 Dec 2025
5 Dec 2025
10 Dec 2025
5 Dec 2025
9 Dec 2025
Earth work excavation for pavement & drain in all soils and sub soils and to full depth as may be directed except rock requiring blasting but inclusive of shoring strutting and baling out water wherever necessary etc., complete.
Cement concrete 1:4:8 (One cement four sand and eight aggregate) using 40mm gauge hard broken granite stone including all incidental charges, dewatering if found necessary etc., complete.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing
Plain Cement concrete 1:3:6 using 20mm HBG jelly including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks for 10 cum
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401
Collection and supply of 6mm metal from approved quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete,
Providing and Laying of Interlocking Rubber moulded Hydraulic pressed Paver block Pavements specification clause 1504, M30 grade 63 mm thickness paver block
Supply and fixing of 75mm 6Ksc PVC pipe including all cost and conveyance charges
GI pipe 65mm
Earth work execavation abd depositing on bank with in intial lead of 10 mts and lift of 2 mts in narrow trenches for laying the pipes in all kinds of soils as directed by the departmental officers
Laying and jointing pipeline including all cost and conveyance charges
Refilling the execavated soils in the trenches including all cost and conveyance charges
Supply and fixing of 75mm 6Ksc PVC pipe including all cost and conveyance charges
GI pipe 65mm
Earth work execavation abd depositing on bank with in intial lead of 10 mts and lift of 2 mts in narrow trenches for laying the pipes in all kinds of soils as directed by the departmental officers
Laying and jointing pipeline including all cost and conveyance charges
Refilling the execavated soils in the trenches including all cost and conveyance charges
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_752359.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.41 MB
TechnicalBidsinglecoverProvidingPaverblockarrangementsandEPLVPPpanchayat.pdf
Tender Documents • 0.58 MB
BOQ_752359.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid