Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAdmitted-Finance 99A PARK STREET KOLKATA 700016 | KOLKATA | KOLKATA | WEST BENGAL | 700016 | ₹1.2 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.2 Cr+₹5.9 L (5.00%)Admitted-Finance | ₹1.2 Cr+₹5.9 L (5.00%) | L2 | Admitted-Finance |
| 3 | L3₹1.3 Cr+₹9.5 L (8.09%)Admitted-Finance | ₹1.3 Cr+₹9.5 L (8.09%) | L3 | Admitted-Finance |
| 4 | L4₹1.3 Cr+₹14.1 L (12.0%)Admitted-Finance | ₹1.3 Cr+₹14.1 L (12.0%) | L4 | Admitted-Finance |
| Sl No | Description | Qty | Unit | NUNDYS L1 | AJAYA KUMAR SAMAL AND CO L4 | CIVCON CONSTRUCTION PRIVATE LIMITED L3 | PACIFIC ENGINEERS L2 |
|---|---|---|---|---|---|---|---|
| 1.00RE-CONSTRUCTION OF GATE-1 AT GRSE MAIN UNIT | |||||||
| 1.01 | a)Detail surveying, drawing and designing as mentioned below are required for the re-construction of the Gate-1
i)GA drawing
ii)Architectural drawing and detailing
iii)3D View / Max Presentation
iv)All Civil drawing and detailing
v)Structural Drawing and detailing
vi)Electrical Drawing and detailing
vii)Structural design vetting of final drawing by Reputed college/University like IIEST/JU/IIT
(All drawing should be submitted both in hard and soft copies along wthaAuto Cad files) | 1 | LS | 3,00,000 ₹3,00,000 | 1,80,000 ₹1,80,000 Lowest | 3,24,000 ₹3,24,000 | 3,15,000 ₹3,15,000 |
| 1.02 | Temporary barricading the gate area along with the adjacentnt area as necessary upto the existing height by using galvanised corrougated metal sheet or equivalent material and steel structural member as supporting frame along with providing of concentrina and barbaide wire at the top of the barricading. The barricade should be safe, secure,strong and stable and the baricadding be their until the gate re-construction work completed. | 1 | LS | 50,000 ₹50,000 Lowest | 85,000 ₹85,000 | 54,000 ₹54,000 | 52,500 ₹52,500 |
| 1.03 | Dismantling R.C. floor, roof, beams etc. including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars upto any height (Rates include the cost of steel scaffolding) | 15 | Cum | 2,100 ₹31,500 Lowest | 3,000 ₹45,000 | 2,268 ₹34,020 | 2,200 ₹33,000 |
| 1.04 | Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. upto any height (Rates include the cost of steel scaffolding) | 30 | Cum | 1,200 ₹36,000 Lowest | 1,500 ₹45,000 | 1,296 ₹38,880 | 1,200 ₹36,000 Lowest |
| 1.05 | Labour for lowering and stacking after dismantling in parts R.S. joists, channels, angles, tees, plates etc.complete as directed from any height | 16 | Qntl | 1,000 ₹16,000 | 800 ₹12,800 Lowest | 1,080 ₹17,280 | 1,100 ₹17,600 |
| 1.06 | Earth work in excavation of foundation trenches or drains, in all sorts of soil including removing,spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water,shoring as required complete. | 120 | Cum | 200 ₹24,000 Lowest | 600 ₹72,000 | 216 ₹25,920 | 200 ₹24,000 Lowest |
| 1.07 | Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge | 120 | Cum | 550 ₹66,000 | 300 ₹36,000 Lowest | 594 ₹71,280 | 575 ₹69,000 |
| 1.08 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (a) With earth obtained from excavation of foundation. | 50 | Cum | 150 ₹7,500 Lowest | 150 ₹7,500 Lowest | 162 ₹8,100 | 150 ₹7,500 Lowest |
| 1.09 | Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply
of sand. (payment to be made on measurement of finished quantity) | 100 | Cum | 1,000 ₹1,00,000 Lowest | 1,600 ₹1,60,000 | 1,080 ₹1,08,000 | 1,050 ₹1,05,000 |
Tender Value
Refer Docs
EMD Value
₹2.4 L
Closing Date
9 May 2023, 12:00 pmClosed
Mr. Nilanjan Kar, Sr. Manager (Contract)
Mr. Nilanjan Kar, Sr. Manager (Contract)
Construction of New Gates at GRSE Main Unit, Kolkata
2023_GRSE_92627_1
SCC/NK/NIC/OT/YM/ GATE/01/ET-1954
Open Tender
Miscellaneous
Item Rate
90 days
As per tender document
Please refer Tender documents.
4 documents required · 4 mandatory
₹500
Yes
Garden Reach Shipbuilders and Engineers Limited
₹2.4 L
Yes
Yard Modernisation Department
25 May 2023
13 Apr 2023
10 May 2023
13 Apr 2023
9 May 2023
28 Apr 2023
17 Apr 2023 - 21 Apr 2023
24 Apr 2023
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 10.67 MB
GRSEInstructionsToBidderForOnlineBidSubmission.pdf
Additional Documents • 0.22 MB
PPP-MII-Order-16.09.2020.pdf
Additional Documents • 7.88 MB
BOQ_102047.xls
BOQ • 0.49 MB
MATRIX.xls
Tender Documents • 0.19 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .