| 1 | L1₹18.1 LAccepted-AOC AZARA BHARALIPARA NEAR AZARA PUBLIC HALL GUWAHATI 781017 ASSAM | KAMRUP METRO | ASSAM | 781017 | L1 | Accepted-AOC Being lowest | |
| 2 | L2₹18.5 L+₹28,525 (1.57%)Rejected-Finance 7TH MILE UPPER SHILLONG P O NONGLYER SHILLONG MEGHALAYA | EAST KHASI HILLS | MEGHALAYA | 793009 | L2 | Rejected-Finance Not lowest |
Tender Value
₹31.8 L
EMD Value
₹64,000
Closing Date
18 Mar 2020, 6:00 pmClosed
GE Umroi
GE Umroi, Umroi Militarty station
REPAIRS and REPLACEMENT OF VARIOUS PARTS OF STEEL FURNITURE AT UMROI MIL STN UNDER GE UMROI
2020_MES_330795_1
9208/E8
Open Tender
Civil Works
Item Rate
60 days
GE umroi
As per tender Documents
5 documents required · 5 mandatory
₹500
GE Umroi
₹64,000
Yes
2 Apr 2020
4 Mar 2020
20 Mar 2020
4 Mar 2020
18 Mar 2020
6 Mar 2020
Amount
Repair following item of Table office Clerk Steel (FD-84/1004)
Material & Labour for removing existing UNSV Top and S & F new Top made out of prelaminated particle board 18/19 mm exterior grade duly fixed with 4mm thick hard wood beading all round all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV leg and S&F new leg made out of square MS pipe 25 mm dia of 1.6 mm thick fix by contineous gas welding without damaging the other parts and match with the other parts all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV drawers S&F the new drawer by contineous gas welding without damaging the other parts and match with the other parts all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV locks of drawer and S&F new brass locks all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV rubber shoe and S & F new hard rubber shoes all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV stiffener S&F new stiffener made of 25 mm sq MS pipe 1.6 mm thick by contineous gas welding without damaging the other parts and match with the other parts all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the table applying two coats of synthetic enamel paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
Repair following item of Table office officer steel (FD-1002/1003)
Material & Labour for removing existing UNSV Top and S & F new Top made out of prelaminated particle board 18/19 mm exterior grade duly fixed with 4mm thick hard wood beading all round all as specified and shown on drawing or as directed by Engr-in-charge . .
Material & Labour for removing existing UNSV leg and S&F new leg made out of square MS pipe 25 mm dia of 1.6 mm thick fix by contineous gas welding without damaging the other parts and match with the other parts all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV drawers S&F the new drawer by contineous gas welding without damaging the other parts and match with the other parts all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV locks of drawer and S&F new brass locks all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV rubber shoe and S & F new hard rubber shoes all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV stiffener S&F new stiffener made of 25 mm sq MS pipe 1.6 mm thick by contineous gas welding without damaging the other parts and match with the other parts all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the table applying two coats of synthetic enamel paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
Repair following item of Table Dining OR (FD-165)
Material & Labour for removing existing UNSV Top and S & F new Top made out of block board commercial 18/19 mm BWP grade duly covered with 22 gauge aluminium sheet all as specified and shown on drawing or as directed by Engr-in-charge.
Material & Labour for removing existing UNSV long Rail and S&F new long rail made out of square MS pipe 25 mm dia of 1.6 mm thick fix by contineous gas welding without damaging the other parts and match with the other parts all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV short Rail and S&F new short rail made out of square MS pipe 25 mm dia of 1.6 mm thick fix by contineous gas welding without damaging the other parts and match with the other parts all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV legs and S&F new legs made out of square MS pipe 25 mm dia of 1.6 mm thick fix by contineous gas welding without damaging the other parts and match with the other parts all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV rubber shoe and S & F new hard rubber shoes all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the table applying two coats of synthetic enamel paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
Repair following item Teapoy Verandah (FD-208
Material & Labour for removing existing UNSV legs and S&F new legs of existing shape and size as required duly welded to all the places all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV Top and S & F new Top made out of prelaminated particle board 18/19 mm exterior grade duly fixed with 4mm thick hard wood beading all round all as specified and shown on drawing or as directed by Engr-in-charge . .
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the teapoy verandah applying two coats of synthetic enamel white paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
Repair following item of Almirah Large Steel with Shelves (FD-67/1031)
Material & Labour for removing existing UNSV handles and S&F new CP handles as per existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV locks and S&F new locks 6 lever harrison/Godrej make of existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV 3 way locking device and S&F new 3 way locking device including MS rod of existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV clamps and S&F new clamps of existing shape and size including adjustment of shelves where reqd all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV hinges and S&F new hinges of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV base/legs and S&F new base/legs of MS sheet 1mm thick of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV shelves and S&F new shelves made of MS sheet 1mm thick of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV door shutter and S&F new door shutter made of MS sheet 1mm thick of existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the Almirah large steel outer & inner portion by applying two coats of synthetic enamel paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
Repair following item of Almirah Medium/Small Steel with Shelves (FD-243/1032)
Material & Labour for removing existing UNSV handles and S&F new CP handles as per existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV locks and S&F new locks 6 lever harrison/Godrej make of existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV 3 way locking device and S&F new 3 way locking device including MS rod of existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV clamps and S&F new clamps of existing shape and size including adjustment of shelves where reqd all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV hinges and S&F new hinges of exising shape and size all as specified and shown on drawing or as directed.
Material & Labour for removing existing UNSV base/legs and S&F new base/legs of MS sheet 1mm thick of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV shelves and S&F new shelves made of MS sheet 1mm thick of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV door shutter and S&F new door shutter made of MS sheet 1mm thick of existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge .
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the Almirah medium steel outer & inner portion by applying two coats of synthetic enamel paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
Repair following item of Locker Steel (FD-1029 & FD-257)
Material & Labour for removing existing UNSV handles and S&F new CP handles as per existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV hasp and stapple S&F new CP hasp and stapple of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV hinges and S&F new hinges of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV base/legs and S&F new base/legs of MS sheet 1mm thick of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV shelves and S&F new shelves made of MS sheet 1mm thick of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV door shutter and S&F new door shutter made of MS sheet 1mm thick of existing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV conduit pipe S&F new conduit pipe of exising shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the Locker steel outer & inner portion by applying two coats of synthetic enamel paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
Repair following item of Charpoy GI with ply top (FD-220)
Removing of existing unserviceable ply wood from GI Charpoy, tihghtening all components of GI Charpoy and supply and fixing 12mm thick plywood size 1980x900mm, BWR grade, conforming to the requirement of IS : 303-1989, commercial face both side including replacing 25 x 5mm mild steel flat iron stiffener where required duly bolted with long rails at equal spacing. MS flat shall be painted with two coats of synthetic enamel paint over a coat of red oxide primer. 10 Nos flush headed bolts and nuts with washer shall be provided for fixing of plywood in the short rail /long rail with flat iron of suitable size as directed by Engineer-in-Charge. Edges of Plywood shall be smoothened all around and corners shall be rounded and smoothened as per direction of Engineer-in-Charge. One coat of water resistant adhesive/marine grade fevicol shall be given to edges all around after smoothened the edges.
Dismantling of existing unserviceable broken long rail of charpoy GI pipe and supply and fixing long rail made out of 32mm bore mild steel galvanised pipe medium grade ISI marked. The end of the pipe shall be threaded as required for fixing with the charpoy. (Note :- Old serviceable long rail shall be kept in safe custody for re-used as short rail and legs and unserviceable GI Pipe shall be contractors property against credit.)
Taking out old unserviceable short rail from the frame and making short rail from old long rail obtained from serial item No-8.02 above by cutting serviceable part to required length, threading both end and fixing complete all as directed. Note :- Old Unserviceable short rail shall be kept in safe custody for re-used as legs and unserviceale GI pipe shall be contrators property against credit
Taking out old unserviceable GI legs from the frame and making legs from old long and short rail obtained from serial item No-8.03 above by cutting serviceable part to required length, threading one end, another end shall be covered with block of hard wood and fixing complete all as directed. Note :- Unserviceable GI pipe shall be contrators property against credit
Supply and fixing galvanised iron 3 way elbow 32mm bore, ISI marked, medium grade length not less than 65mm in each way including dismantling of old elbow complete all as specified and directed.
Supply and fixing galvanised iron check nut, 5mm thick suitable for 32mm bore galvanised iron pipe including dismantling of old unserviceable check nut complete all as specified and directed.
Supply and fixing MNF clamp made out of flat iron 25mm x 3mm welded to GI pipe legs with end closed with 3mm thick MS plate welded to the clamp and 5mm thick MS plate welded properly at the bottom of leg including painting with two coats of synthetic enamel paint over a coat of red oxide zinc chrome primer complete all as sfecified and directed.
Repair following item of Charpoy Hard Top Iron Frame(FD-MAP-II/01)
Removing of existing unserviceable ply wood from Charpoy hard top iron frame and supply and fixing 12mm thick plywood of existing size, BWR grade, conforming to the requirement of IS : 303-1989, commercial face both side duly fixed with stiffners all as specified and shown on drawing or as directed by Engineer-in-Charge.
Material & Labourfor removing existing UNSV bolt and S&F new bolt of exisiing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labourfor removing existing UNSV rubber shoe and S&F new rubber shoe of exisiing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Repair following item of Bed Hard Iron Frame (FD/E6/MAP/08®)
Removing of existing unserviceable ply wood from Charpoy hard top iron frame and supply and fixing 12mm thick plywood of existing size, BWR grade, conforming to the requirement of IS : 303-1989, commercial face both side duly fixed with stiffners all as specified and shown on drawing or as directed by Engineer-in-Charge.
Material & Labour for removing existing UNSV head rest and S & F new head rest made out of prelaminated particle board 18/19 mm exterior grade all as specified and shown on drawing or as directed by Engr-in-charge . .
Material & Labour for removing existing UNSV foot rest and S & F new foot rest made out of prelaminated particle board 18/19 mm exterior grade all as specified and shown on drawing or as directed by Engr-in-charge . .
Material & Labourfor removing existing UNSV bolt and S&F new bolt of exisiing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labourfor removing existing UNSV rubber shoe and S&F new rubber shoe of exisiing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Repair following item of Chair writing Steel (FD/E6/MAP/12)
Material & Labour for removing existing UNSV seat and back with foam cushion incl tapestry cloth and S&F the same of chair writing steel all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV set of arm rest and S&F new arm rest set of chair writing steel all as specified and shown on drawing or as directed by Engr-in-charge ..
Repair following item of Shoe Rack Steel (FD/E6/MAP/02)
Material & Labour for removing existing UNSV shelves and S&F the new shelves of shoe rack steel all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV rubber shoes and S&F the new rubber shoes of shoe rack steel all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the shoe rack steel applying two coats of synthetic enamel black paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
Repair following item of Charpoy IP folding steel (FD-388 (R ))
Removing of existing unserviceable ply wood from Charpoy hard top IP and supply and fixing 12mm thick plywood of existing size, BWR grade, conforming to the requirement of IS : 303-1989, commercial face both side duly fixed with stiffners all as specified and shown on drawing or as directed by Engineer-in-Charge.
Material & Labourfor removing existing UNSV rubber shoe and S&F new rubber shoe of exisiing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the charpoy IP folding steel applying two coats of synthetic enamel black paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
Repair following item of Rack steel 1830x760x1905mm (FD-129)
Material & Labour for removing existing UNSV shelves and S&F the new shelves of rack steel all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labourfor removing existing UNSV angle and S&F new angle of exisiing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labourfor removing existing UNSV corner and S&F new corner of exisiing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labourfor removing existing UNSV nut & bolt and S&F new nut & bolt of exisiing shape and size all as specified and shown on drawing or as directed by Engr-in-charge ..
Material & Labour for removing existing UNSV paints by scrubbing with sand/emery paper and repaint the rack steel applying two coats of synthetic enamel black paints over a coat of red oxide primer complete all as specified and shown on drawing or as directed by Engr-in-charge .
kapoor and co
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .